The Government are well aware of the brake on economic development in my hon. Friend’s constituency and others in the area caused by the congestion at Dartford.
At the first spending review in 2010, we promised to introduce measures to tackle congestion at the crossing in the short to medium term. Indeed, autumn this year will see the introduction of free-flow charging on the Dartford-Thurrock crossing, as my hon. Friend the Member for Thurrock mentioned: motorists will no longer stop on the crossing to put money into a slot machine or to hand it to an attendant. We also committed to reviewing the options for a new crossing. Subsequently, the national infrastructure plan 2011, which identified a lower Thames crossing as one of the Government’s top 40 infrastructure projects, added a commitment to consult on those options. My Department has fulfilled both those commitments, and following the review of the options shortlisted by the 2009 study, the Department consulted the public from May to July 2013.
Knowing that our decision on the new crossing will affect many different interests, we engaged with the public in a variety of ways. In addition to online communications, both the Minister and officials met interested parties in a series of briefings, meetings and public information events. Numerous members of the public took advantage of opportunities to speak with officials to ask questions or raise concerns. In all, the Department recorded and analysed more than 5,700 responses to the consultation. The consultation feedback has confirmed that opinion is divided both on the need for a new crossing and where to locate it, and that there are serious issues at stake in reaching decisions on where to locate a new crossing and whether it should be a bridge or a tunnel.
I am grateful to the Minister for giving up his valuable time. Has his Department at any point considered the capacity of the M25 as a whole and whether that will need expansion at some point? We have already moved to four lanes in some areas, but if at some point in the next 50 years we need an outer ring road or outer link road, so that people are not all using the M25, regardless of the crossing, would it not be worth reconsidering options D or E, or a variant thereof, and putting in place the most expensive part of the infrastructure of an outer ring road at this point in the investment cycle, rather than waiting to look at it again at some point in the future?
I understand my hon. Friend’s point. Indeed, the Department is currently considering what further improvements may be needed on the M25, A282 and A13 to ensure that, when we address the bottleneck at the crossing, we do not push the congestion north and south to other parts of the M25, which is already a very congested road.
A number of consultation responses requested that we reopen other options previously rejected. Some, like my hon. Friend the Member for Thurrock, advocated options further east downstream, while others advocated options further west within London. However, given the Government’s objectives for the crossing, as set out in the consultation, 1 am not convinced there are any reasons that would justify reopening previously rejected options. I am sorry to disappoint her. Further information about the consultation feedback is set out in a consultation response summary published online by my Department alongside the Secretary of State’s announcement last December.
That brings us to the point we have reached in determining where to locate a new lower Thames crossing. As I said at the beginning, we have narrowed down the options and are obtaining further advice on points raised during the consultation in order to weigh up the relative merits of the remaining options. In pursuing further advice, I am listening to concerns expressed by respondents to the consultation. Specifically, I am seeking more information, first, on the scale of further improvements that may be required on the M25, A282 and A13. Secondly, I am seeking further information on potential implications for compliance with national and European air quality targets. Many hon. Members will have seen the coverage of our planned improvements to the A1 in South Yorkshire and Derbyshire, where we are having to take measures to reduce the speed of vehicles to reduce the pollution, particularly nitrogen oxides, that puts us in danger of breaching those targets. Thirdly, I am seeking more information on the scale of mitigation that may be needed to avoid impacts on protected habitats.
I make it clear that we have no plans to consult on additional options. The options we are still considering for a new lower Thames crossing are: option A, at the existing Dartford-Thurrock crossing; option C, connecting the M2 with the A13 and the M25 between junctions 29 and 30; and the option C variant that would additionally widen the A229 between the M2 and the M20.