All 1 Debates between Sheryll Murray and Andy McDonald

Great Western Railway Routes

Debate between Sheryll Murray and Andy McDonald
Monday 8th February 2016

(8 years, 10 months ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Andy McDonald Portrait Andy McDonald (Middlesbrough) (Lab)
- Hansard - - - Excerpts

I congratulate the hon. Member for Torbay (Kevin Foster) on securing this debate on an important subject. There has been many an excellent contribution. I agree with the hon. Member for Newton Abbot (Anne Marie Morris) that the Great Western railway is more than just a transport system; it is vital to the areas that it serves, which is why it is so important that the Government deliver on their promises on electrification and improved resilience as a matter of urgency.

As was identified by my hon. Friend the Member for the Crown principality of Ogmore (Huw Irranca-Davies), the recent flooding in much of the country has further highlighted the importance of ensuring that our railways are resilient in extreme weather conditions, which we are witnessing with increased frequency. Commuters on the Great Western railway know that only too well. The breach of the Dawlish sea wall in 2014 forced the closure of the line for two months, creating significant disruption. We saw the rails hanging in the air like a rope bridge. I, too, applaud the heroic efforts of the engineers and workers of Network Rail who brought the repair to a speedy conclusion.

A report published in the Journal of Transport Geography on the likely future impact of weather on trains travelling to and from the south-west predicted that up to a third of rail services could be disrupted over the next 100 years. That report, which was described by Network Rail as “key” to long-term developments, underlines the importance of improving resilience in the region.

The Labour party agreed with the Prime Minister when he said that the Government “needed to find answers” because the Dawlish disaster of 2014 “must not happen again”, but his rhetoric has yet to be matched by action. Despite it being said that “money is no object”, the Peninsula Rail Task Force—we have heard a lot about that this evening—has been examining how to improve the south-west’s rail network following the storm damage, but is currently unable to complete its final report because funding is unavailable.

In a letter to the Secretary of State, Tim Jones, chairman of the Devon and Cornwall Business Council, said that the south-west would be at a “severe disadvantage” should no funding be found to complete those studies. If we are to accept what the Prime Minister told the House when he said that “money was no object”, and if we are to believe that the Government are serious about making our railways resilient to extreme weather conditions, they must ensure that funding is available to complete the report. It is of paramount importance that resilience is improved, and the Government should give their backing to the report so that the task force can get on with delivering a railway that is to be relied on come rain or shine.

A number of suggestions have been made for an additional route to Dawlish, including by my right hon. Friend the Member for Exeter (Mr Bradshaw), and by Labour South West, including Tudor Evans, the leader of Plymouth City Council. However, the Prime Minister appeared to prejudge any fair assessment of the options when he backed a new Okehampton railway route as the “most resilient” alternative to the vulnerable Dawlish route, saying that the UK is a “wealthy country” that should be making long-term investments in rail, and that the Okehampton line was worth a “long, hard look”. Will the Minister guarantee that all options for an additional route in the south-west will be assessed on a fair basis? Will she also reassure the House that the funding that the Prime Minister promised will be made available, and that no decision has yet been taken on the route that an avoiding line might take?

So far the Government’s track record on delivering the Great Western main line is poor. Electrification will be delivered late and cost substantially more than initially estimated. Labour committed to electrification of the Great Western main line in 2009, but the estimated cost of that has escalated dramatically since Network Rail made its first assessment in 2011.

Sheryll Murray Portrait Mrs Sheryll Murray
- Hansard - -

The hon. Gentleman has criticised this Government’s track record. Will he enlighten the House about the previous Labour Government’s track record on investing in the Great Western railway line?

Andy McDonald Portrait Andy McDonald
- Hansard - - - Excerpts

I will happily do so. Let me remind the hon. Lady of the pieces that we had to pick up when coming into government after the disaster of Railtrack and the deaths that were caused as a result of the privatisation of the railways. We do not want to hear any more about that—the investment was significant.

Sheryll Murray Portrait Mrs Murray
- Hansard - -

rose

Andy McDonald Portrait Andy McDonald
- Hansard - - - Excerpts

I have given way. Mark Carne, Network Rail’s chief executive, told Members of Parliament in October that the estimate for the project had been £874 million in January 2013, and £1.5 billion in September 2014. He said that because of “inadequate planning”, the cost of electrification could now reach £2.8 billion.

The upgrades that were expected to have been completed by 2018 are significantly behind schedule. Under the original plan, the Reading to Didcot route should already have been completed, and routes to Oxford and Bristol were on schedule to be completed this year. Didcot is now expected to be two years late, in 2017, and Newbury and Oxford three years late, in 2018 and 2019 respectively. Bristol Temple Meads will not have electric trains until 2020, and the east-west rail link from Oxford to Bletchley is delayed until the early 2020s.

Some of those improvements have been delayed by up to four years, significantly affecting commuters who rely on the Great Western line, as well as on the towns and cities that the line serves. Progress on the Great Western electrification has been hampered by this Government putting electrification on hold after the 2010 election, and not fully confirming the project until July 2012, meaning that essential planning work was delayed. The Office of Rail Regulation has said that because a number of major enhancements were added to control period 5 at a relatively late date, several important projects were started in 2014 without being fully assessed. At the start of control period 5, £7 billion of the £12 billion of enhancement spending had not been signed off by the regulator. Calvin Lloyd, Network Rail’s head of long-term planning and funding said:

“There are cost pressures across the whole portfolio of enhancement projects, which should not be a surprise to anyone given that we did not have the level of confidence we might have wished at the start.”

It is the taxpayer, commuters and those who rely on Great Western who will suffer the consequences of poor cost estimation and poor planning. If the Great Western tracks are not electrified according to schedule, the Department will be liable to pay compensation to the private consortium that is delivering the new generation of electric intercity express programme trains. The Department for Transport is considering converting electric IEP trains so they can run on diesel, at an unclear cost to the taxpayer. They may not be able to reach speeds of 125 mph, raising fears that some journeys could actually slow down, compared with today, if electrification is delayed.

The Government’s plans for replacing uncomfortable and inaccessible Pacer trains on branch lines in the south-west are dependent on the success of the electrification programme. If the Great Western electrification project is significantly delayed, passengers in the south-west could endure vehicles for years that the Government have, quite rightly, said are unacceptable in the north of England.

Poor planning and the premature announcement of projects have left commuters uncertain of the future of the Great Western, yet the Government were repeatedly warned that rising costs could lead to some projects being delayed or cancelled. Labour first raised problems with the Great Western main line electrification programme in May 2014, just weeks into the start of the investment period, and challenged the Government to explain which electrification projects will be delayed or cancelled as a consequence of rising costs. Those concerns were echoed by the Transport Committee, which warned in January 2015:

“We are concerned that key rail enhancement projects—such as electrification in the North and North West of England—have been announced by Ministers without Network Rail having a clear estimate of what the projects will cost, leading to uncertainty about whether the projects will be delivered on time, or at all.”

Worse still, commuters were kept in the dark by the Government throughout this period. The chief executive of Network Rail confirmed:

“In mid-March 2015, Network Rail informed the Department for Transport that decisions may need to be made in the coming months about the deferral of certain schemes.”

However, Ministers in the Department are still refusing to say whether they were informed before the election of the plans to defer major schemes. It is now clear that the agreed work could never have been delivered within the agreed budget and timeframe. Yet Network Rail, the Department for Transport and the regulator, the Office of Rail and Road, signed up to the plans anyway, resulting in a great deal of unnecessary uncertainty and confusion. It is passengers and the public who pay the price for such failures, and serious questions must be asked of the Government about how such a shambles was allowed to occur on their watch.

It will be a great relief to passengers reliant on the Great Western that track upgrades will arrive late rather than never. We on the Labour Benches encourage the Government properly to examine their adequacy and the adequacy of Network Rail in budgeting, planning and delivering such programmes in future. It is those issues that should be focused on, so it is an issue of concern that Nicola Shaw, who is heading the Department’s review of the future of Network Rail, has said that privatisation of Network Rail is an option that is on the table. The Government should be asking how better to deliver major projects such as rail electrification in the future, not looking to devote time to managing yet further privatisation and fragmentation of our national rail infrastructure.