Great Western Railway Routes Debate
Full Debate: Read Full DebateSheryll Murray
Main Page: Sheryll Murray (Conservative - South East Cornwall)Department Debates - View all Sheryll Murray's debates with the Department for Transport
(8 years, 9 months ago)
Commons ChamberAbsolutely. As I am sure my hon. Friend is aware, the early figures for the Borders railway that is being built in Scotland show higher than expected levels of usage. In St Ives, good park-and-ride services are crucial to the tourism industry. Having good trains makes for good tourism.
I will give way once more, but then I must make some progress so that I do not hog the time.
Does my hon. Friend agree that we should expand the existing park-and-ride services? In my constituency, there could be another park-and-ride station to the east of Bodmin Parkway to allow people from areas that do not have access to a railway station to commute and travel to places such as the city of Plymouth?
My hon. Friend is absolutely right that park and ride can play a huge part in giving rural communities in particular access to rail services via parkway-style stations. Looking at north-west Devon and north Cornwall, it might be an interesting project in years to come to provide parkway stations near the A30 as it comes into Devon, using the spur that heads towards Okehampton. That could provide a service to the area without competing with the Great Western main line in south Devon.
We must ask what investment can deliver. It is estimated that even a relatively modest improvement of 15 minutes in journey times between the south-west peninsula and London would deliver £300 million in increased productivity. However, this debate is not just about economics; it is about communities along the line and their needs for travel and growth.
I will not look to play our region off against another. Just as investment in Crossrail and new rail capacity in other parts of the UK will deliver for those communities over the next 10 to 15 years, delivering on the issues we are discussing can deliver for ours. It is worth bearing in mind the fact that investment in the Great Western railway supports other key projects across the UK. For example, the expansion of Heathrow as the UK’s hub will be supported by the western rail access. I hope the Minister sees the urgency of that.
I have said I am grateful for that station and that I am grateful for the investment programme that the Labour Government initiated. I say to the Minister simply that she has cut that investment programme over the last six years at a time when every sensible economist in the world thinks we should be investing in our infrastructure for the long term. We have record low long-term interest rates in this country and a faltering economy, so now is the time when we should be investing in infrastructure, and particularly in rail. I repeat that I am very grateful that the Minister did not cut the money for that station and that we are going to get another station—but, incidentally, the Labour Government initiated the plans for that, too.
I am going to end with the following suggestion to the Conservative MPs in Devon and Cornwall who were swept to victory last May on great and grandiose promises of a rail revolution and renaissance in the south-west. I got into a great deal of trouble with my Whips in the last Parliament for refusing to vote for the money for High Speed 2 up to the north. To give credit where it is due, one Conservative Member, the hon. Member for South West Devon (Mr Streeter)—sadly, he is not in his place tonight—did the same. We withheld our support for that money. The Government now have a majority of only 12—
No, I will not. I am finishing and the hon. Lady can speak in the debate.
More than 12 Conservative Members with constituencies in Devon and Cornwall could stop the Government putting that money through if they do not get what this Government promised over the next five years. I challenge them to do that—to stick up for their constituents, stick up for the south-west and stop taking no for an answer.
I think that all Conservative Members will be sticking up not just for their own constituents but for the country as a whole. What we want to see is growth and productivity improved. We have to repair the damage done by the previous Labour Government that resulted in our having to make the cuts that we are now making. It is undoubtedly this Government, and the previous coalition Government, who have focused on the need to do something about the whole infrastructure mess.
I congratulate my hon. Friend the Member for Torbay (Kevin Foster), my constituency neighbour, for securing tonight’s debate. It is undoubtedly true that the Great Western route is critical. It is fair to say—here the right hon. Member for Exeter (Mr Bradshaw) and I might agree —that we need to give some priority to the infrastructure in the south-west. Where we would disagree is that I believe that we have already seen action taken and seen more than just warm words. Frankly, as the Member representing Dawlish among other places, I have seen it in spades. We all want to see this commitment. I believe it is fair, but we need it on the record.
The very fact that the trains running between Penzance and Paddington were first introduced in 1976 just goes to show the lack of investment initiated by the Labour Government about which the right hon. Member for Exeter (Mr Bradshaw) talks. They did nothing for the south-west when they were in government for 12 years.
My hon. Friend makes a very fair point. It is this Government, and the former coalition Government, who have begun to look at the south-west and to recognise that we have a motorway, the M5, which ends at Exeter, and that the road infrastructure therefore needs sorting. They recognised, too, that broadband needed sorting, which is not something that the Labour Government did much about. They have also recognised that, frankly, our railway needs resolution.
The gross value added of the south-west is 72% of the national average, and if we could just deal with infrastructure issues, we would open up the opportunity and really deliver on the potential by raising the productivity of our area as a whole.
Given that so many colleagues have mentioned Dawlish, let me say a few words about it. This was an extraordinary event. It is, I suppose, a truism that after some of the most disastrous events, we sometimes see some of the best things emerge. It is undoubtedly true that what happened in Dawlish on that fateful day shined a light on the challenge. Rather than running away from it, the Government said, “This is something that matters; we are going to spend the money.”
I remember that storm in February 2014. The Government put in £35 million at the time, and I recall constituents telling me, “This can’t be fixed,” while the engineers were saying, “It can’t be done,” yet Network Rail and the Government told me, “It can; it will be; and it will be soon.” In the end, I think it took about six weeks. It was absolutely phenomenal. Having fixed it, they continued to spend another £6 million sorting out some further individual problems.
Clearly, there is more to be done, but if we look at what happened, we find that we had 300 engineers—that wonderful orange army—who worked solidly pretty much round the clock for two months, sorting out our railway. They were ingenious. Despite what the engineers said, they came up with the idea of using 19 sea containers to provide a temporary sea wall. That was quite an innovative idea. The only challenge they had, once it was put in place, was how they were going to remove it. That turned out to be more of a challenge than putting it in place. Yet 6,000 tonnes of concrete and 150 tonnes of steel later, along with the 25,000 tonnes of the cliff being removed, we are now in a good, resilient position for the railway at Dawlish. We have repaired 600 metres of wall and Dawlish station, including the platform, and we have 700 metres of new track.
Still more work is ongoing. The point made about signalling is absolutely right. More signalling repair and restoration is going on, along with more repairs to the sea wall, whose footpath has been repaired. Riviera terrace, which disappeared overnight, has now been rebuilt. As for Dawlish Warren along the coast, the point has been made that there are some natural climate change erosion problems, but work is already going on to deal with them through beach recharge and trying to realign how the natural coastal flow works.
The point of this debate—other than being able to say, “Well done, Government, you sorted out Dawlish; thank you very much”—is to flag up to everyone the need to do more. There is a bigger picture.
As my hon. Friend the Member for Torbay mentioned, the Peninsula Rail Task Force has been one of the key drivers. It was established to look at a 20-year plan, and I think that it has the support of everybody in the area. It is a great credit to the area and it shows how strongly we all feel about getting this right. If we can get this right, if that taskforce is allowed to complete its job and if we get that 20-year plan and the Government to commit to investment in the south-west, we could have a GVA uplift of £520 million by improving journey times.
It is fascinating that the potential for this area is so clear. Passenger numbers are many times that of any other area. I think they have gone up by 126% over the decade compared to a national increase of 61%. The tourism potential is already well demonstrated. In 2014, over £1 billion was spent by visitors to the south-west. Believe it or not, in 2013, Saudi and Russian visitors spent more in the south-west than in London.
If those who enjoy travelling using the “Lonely Planet” guides have a look, they will find that the south-west is situated in the league tables as the third best place to visit—ahead of Italy and Denmark. So the potential is there, and there is a win-win—not only for the south-west, but for the Government, because we will get productivity up, which is what the Chancellor wants to see above everything.
The Government have already committed £400 million, and we have had 11 individual reports since the Dawlish events, looking at resilience and reliability, faster journey times and sufficient capacity, and five more reports are coming. No one could honestly say that that did not represent a serious commitment to understanding the problem and then getting it right.
A number of crucial issues need to be addressed. I think every Member agrees that the Dawlish coastal route must be a priority, because unless it is running as a “forever, forever” resilient line, shoring up the whole peninsular network, everything else will begin to become secondary.
I take issue with the challenge from the right hon. Member for Exeter, who, like King Canute, seemed to fear that at some point we would all be washed away. I suggest that we should take account of British scientists, who have been incredibly resilient over the years—as, indeed, were those intrepid passengers who, when the line broke down all that time ago, simply got out of one carriage, climbed over the rocks, and got into another carriage to continue their journey. We are a resilient nation, and that line will survive. It too will be resilient, and it is there for the long term. I am sure that the Government will ensure that that can happen. Nothing is impossible; all that is needed is a little imagination and some intelligence.
The coastal route is crucial, but it is in all our interests to look at the whole area, and the east of Exeter project for resilience is equally important. Bridgwater and Taunton are also crucial, as are Yeovil and Castle Cary. They must be on the must-do list.
I congratulate the hon. Member for Torbay (Kevin Foster) on securing this debate on an important subject. There has been many an excellent contribution. I agree with the hon. Member for Newton Abbot (Anne Marie Morris) that the Great Western railway is more than just a transport system; it is vital to the areas that it serves, which is why it is so important that the Government deliver on their promises on electrification and improved resilience as a matter of urgency.
As was identified by my hon. Friend the Member for the Crown principality of Ogmore (Huw Irranca-Davies), the recent flooding in much of the country has further highlighted the importance of ensuring that our railways are resilient in extreme weather conditions, which we are witnessing with increased frequency. Commuters on the Great Western railway know that only too well. The breach of the Dawlish sea wall in 2014 forced the closure of the line for two months, creating significant disruption. We saw the rails hanging in the air like a rope bridge. I, too, applaud the heroic efforts of the engineers and workers of Network Rail who brought the repair to a speedy conclusion.
A report published in the Journal of Transport Geography on the likely future impact of weather on trains travelling to and from the south-west predicted that up to a third of rail services could be disrupted over the next 100 years. That report, which was described by Network Rail as “key” to long-term developments, underlines the importance of improving resilience in the region.
The Labour party agreed with the Prime Minister when he said that the Government “needed to find answers” because the Dawlish disaster of 2014 “must not happen again”, but his rhetoric has yet to be matched by action. Despite it being said that “money is no object”, the Peninsula Rail Task Force—we have heard a lot about that this evening—has been examining how to improve the south-west’s rail network following the storm damage, but is currently unable to complete its final report because funding is unavailable.
In a letter to the Secretary of State, Tim Jones, chairman of the Devon and Cornwall Business Council, said that the south-west would be at a “severe disadvantage” should no funding be found to complete those studies. If we are to accept what the Prime Minister told the House when he said that “money was no object”, and if we are to believe that the Government are serious about making our railways resilient to extreme weather conditions, they must ensure that funding is available to complete the report. It is of paramount importance that resilience is improved, and the Government should give their backing to the report so that the task force can get on with delivering a railway that is to be relied on come rain or shine.
A number of suggestions have been made for an additional route to Dawlish, including by my right hon. Friend the Member for Exeter (Mr Bradshaw), and by Labour South West, including Tudor Evans, the leader of Plymouth City Council. However, the Prime Minister appeared to prejudge any fair assessment of the options when he backed a new Okehampton railway route as the “most resilient” alternative to the vulnerable Dawlish route, saying that the UK is a “wealthy country” that should be making long-term investments in rail, and that the Okehampton line was worth a “long, hard look”. Will the Minister guarantee that all options for an additional route in the south-west will be assessed on a fair basis? Will she also reassure the House that the funding that the Prime Minister promised will be made available, and that no decision has yet been taken on the route that an avoiding line might take?
So far the Government’s track record on delivering the Great Western main line is poor. Electrification will be delivered late and cost substantially more than initially estimated. Labour committed to electrification of the Great Western main line in 2009, but the estimated cost of that has escalated dramatically since Network Rail made its first assessment in 2011.
The hon. Gentleman has criticised this Government’s track record. Will he enlighten the House about the previous Labour Government’s track record on investing in the Great Western railway line?
I will happily do so. Let me remind the hon. Lady of the pieces that we had to pick up when coming into government after the disaster of Railtrack and the deaths that were caused as a result of the privatisation of the railways. We do not want to hear any more about that—the investment was significant.
I have given way. Mark Carne, Network Rail’s chief executive, told Members of Parliament in October that the estimate for the project had been £874 million in January 2013, and £1.5 billion in September 2014. He said that because of “inadequate planning”, the cost of electrification could now reach £2.8 billion.
The upgrades that were expected to have been completed by 2018 are significantly behind schedule. Under the original plan, the Reading to Didcot route should already have been completed, and routes to Oxford and Bristol were on schedule to be completed this year. Didcot is now expected to be two years late, in 2017, and Newbury and Oxford three years late, in 2018 and 2019 respectively. Bristol Temple Meads will not have electric trains until 2020, and the east-west rail link from Oxford to Bletchley is delayed until the early 2020s.
Some of those improvements have been delayed by up to four years, significantly affecting commuters who rely on the Great Western line, as well as on the towns and cities that the line serves. Progress on the Great Western electrification has been hampered by this Government putting electrification on hold after the 2010 election, and not fully confirming the project until July 2012, meaning that essential planning work was delayed. The Office of Rail Regulation has said that because a number of major enhancements were added to control period 5 at a relatively late date, several important projects were started in 2014 without being fully assessed. At the start of control period 5, £7 billion of the £12 billion of enhancement spending had not been signed off by the regulator. Calvin Lloyd, Network Rail’s head of long-term planning and funding said:
“There are cost pressures across the whole portfolio of enhancement projects, which should not be a surprise to anyone given that we did not have the level of confidence we might have wished at the start.”
It is the taxpayer, commuters and those who rely on Great Western who will suffer the consequences of poor cost estimation and poor planning. If the Great Western tracks are not electrified according to schedule, the Department will be liable to pay compensation to the private consortium that is delivering the new generation of electric intercity express programme trains. The Department for Transport is considering converting electric IEP trains so they can run on diesel, at an unclear cost to the taxpayer. They may not be able to reach speeds of 125 mph, raising fears that some journeys could actually slow down, compared with today, if electrification is delayed.
The Government’s plans for replacing uncomfortable and inaccessible Pacer trains on branch lines in the south-west are dependent on the success of the electrification programme. If the Great Western electrification project is significantly delayed, passengers in the south-west could endure vehicles for years that the Government have, quite rightly, said are unacceptable in the north of England.
Poor planning and the premature announcement of projects have left commuters uncertain of the future of the Great Western, yet the Government were repeatedly warned that rising costs could lead to some projects being delayed or cancelled. Labour first raised problems with the Great Western main line electrification programme in May 2014, just weeks into the start of the investment period, and challenged the Government to explain which electrification projects will be delayed or cancelled as a consequence of rising costs. Those concerns were echoed by the Transport Committee, which warned in January 2015:
“We are concerned that key rail enhancement projects—such as electrification in the North and North West of England—have been announced by Ministers without Network Rail having a clear estimate of what the projects will cost, leading to uncertainty about whether the projects will be delivered on time, or at all.”
Worse still, commuters were kept in the dark by the Government throughout this period. The chief executive of Network Rail confirmed:
“In mid-March 2015, Network Rail informed the Department for Transport that decisions may need to be made in the coming months about the deferral of certain schemes.”
However, Ministers in the Department are still refusing to say whether they were informed before the election of the plans to defer major schemes. It is now clear that the agreed work could never have been delivered within the agreed budget and timeframe. Yet Network Rail, the Department for Transport and the regulator, the Office of Rail and Road, signed up to the plans anyway, resulting in a great deal of unnecessary uncertainty and confusion. It is passengers and the public who pay the price for such failures, and serious questions must be asked of the Government about how such a shambles was allowed to occur on their watch.
It will be a great relief to passengers reliant on the Great Western that track upgrades will arrive late rather than never. We on the Labour Benches encourage the Government properly to examine their adequacy and the adequacy of Network Rail in budgeting, planning and delivering such programmes in future. It is those issues that should be focused on, so it is an issue of concern that Nicola Shaw, who is heading the Department’s review of the future of Network Rail, has said that privatisation of Network Rail is an option that is on the table. The Government should be asking how better to deliver major projects such as rail electrification in the future, not looking to devote time to managing yet further privatisation and fragmentation of our national rail infrastructure.