HS2: Phase 2b Route (Manchester and Leeds) Debate

Full Debate: Read Full Debate
Department: Department for Transport

HS2: Phase 2b Route (Manchester and Leeds)

Rachael Maskell Excerpts
Wednesday 6th September 2017

(7 years, 2 months ago)

Westminster Hall
Read Full debate Read Hansard Text Read Debate Ministerial Extracts

Westminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.

Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Rachael Maskell Portrait Rachael Maskell (York Central) (Lab/Co-op)
- Hansard - -

I thank the hon. Member for Eddisbury (Antoinette Sandbach) for bringing this debate forward. It is so important that there is proper scrutiny in this House of the plans. After all, a Bill will not be laid before Parliament until 2019, so we have a window of opportunity to scrutinise every inch of track to make sure that the right decision is being made.

The clearest comment I have heard in this debate is that the Government have got to get a grip of what is happening. After all, it is the responsibility not of HS2 Ltd but of the Government to make sure that our infrastructure is right. That is why Labour wants to see the development of the UK’s infrastructure. We supported high-speed rail for that reason: to improve capacity and connectivity, and to boost the economies of cities, particularly in the midlands and the north.

We cannot have a siloed approach to HS2. It has to be embedded within a wider integrated transport strategy. Economic development across our towns and cities, which feel so ignored, has to be at the heart of everything. Therefore, while HS2 will provide a main artery, we cannot ignore that objective, which sometimes gets missed. The focus is often on the engineering expertise and the excitement around that, but that misses the point of what high-speed rail is all about. It is about moving goods and people to help the economy grow.

There is real disappointment among Labour Members at the Government’s strategy of late around rail, full stop. They are turning off the power in the north and we are not going to see the investment in HS3 that we were promised to make sure that there was east-west connectivity. Part of the original plans for high-speed rail was an inverted-A route, with high speed across the Pennines. There is a serious piece of the jigsaw missing. It was a deliberate ploy by the Government to make the announcement when even Network Rail had not made the decision. The Government jumped the gun, to cut off the north. Those kind of blatant decisions are really hurting people in my constituency and across the north.

We must recognise the need for investment in rail. We need to decongest the current networks and ensure better connectivity as we move forward, but not at any cost. That is what is so important. Points have been made powerfully today about ensuring that the details are right, understanding the engineering complexities and the environmental concerns that need to be at the forefront of the project, and making sure that people are at the heart of decision making.

Yes, we do want to see the economic benefit. I ask the Minister to ensure that clear economic benefit is mapped out from this development. If we get things in the wrong order and do not put the economic investment into cities in the north, I am concerned that their economies will be sucked down to the south-east and we will not realise the potential. I fear that that could happen to my city; we would just be another commuter zone. It is really important that we understand how the plans relate to the economy and economic investment, and that we get the sequencing absolutely right, to ensure that we see the benefit of high-speed rail. I take on board the point made by my hon. Friend the Member for Leigh (Jo Platt) that HS2 cannot stop at every town along the route, but if it is well-connected—we do not even have a draft national timetable yet—it will serve those purposes.

Just south-west of my constituency, the little village of Church Fenton is now being described as a massive interchange. The origins of HS2 were very much about making sure that there was connectivity between the major conurbations of the north and the midlands. Although Church Fenton may have that elevated status, we have to look at the impact that that will have on a small village in North Yorkshire. Obviously, it does not want to just be turned into a car park. Those considerations are incredibly important.

There has been much discussion about Sheffield and that discussion must continue. I have real concerns about taking the line into the heart of Sheffield, because not having the electrification and connectivity going north makes a nonsense of HS2. We are not achieving the original aim of joining up the major conurbations, and therefore HS2 does not meet its objectives. Given the cost of the investment, if it does not even do that and is not even able to make those connections across a county, it is right that we ask serious questions of the Government. We must look again at the proposals and make sure that we get this absolutely right.

Where we place stations and routes will be crucial in how our economy grows in the future. I want to hear much more from the Minister about the connectivity issues. I also want to hear about why lines cannot be moved. As we have heard, 800 metres in one direction could make a huge difference to an area of environmental protection and present an engineering challenge. If we can move lines to reduce the risk to our environment and beyond—it sounds like that would reduce cost as well—the Minister has an absolute responsibility to do that.

I recognise that progress has been made on parts of the line through the consultation with HS2. We need to keep bringing HS2 back to the table time and again over the next 18 months to make sure that we make clear progress on the outstanding issues. Clearly we want to ensure that when we are making such a serious investment in the future of our country, at a time when perhaps we are most challenged as to where our economy sits in the wider sphere, there is a response on those issues.

I ask the Minister to site this issue within the rest of our investment in the rail network. The east coast main line is in urgent need of repair and upgrade, with the overhead lines needing power to run high-speed. We know that it will cost about £900 million for the southern route, but the northern route also needs a proper upgrade to take on the HS2 line heading north of Church Fenton, York and beyond. I want to know the timing of those upgrades. When will they happen? I also want to ensure that we bring real connectivity across the network, to make sure that it works.

Finally, I want to hear what the Government are doing about the cost of the project, which is, again, a matter of major concern to our constituents. It is a massive investment, particularly at a time when there are people in our constituencies who are hungry and starving. Billions of pounds are being spent on a rail service that perhaps will not connect to them. I want to hear how the Minister is keeping a lid on the costs and ensuring that the investment brings benefit to constituencies across the north and the midlands.

Paul Maynard Portrait The Parliamentary Under-Secretary of State for Transport (Paul Maynard)
- Hansard - - - Excerpts

It is a pleasure to serve under your chairmanship, Mr McCabe. I shall do my best to cram as much as I can into the remaining 10 minutes. The hour-long debates in this place are neither fish nor fowl, I have rapidly learned.

I thank my hon. Friend the Member for Eddisbury (Antoinette Sandbach) for doughtily providing her usual list of issues for me to consider. She is a firm champion of the people of Eddisbury, and I shall try to focus on her main concerns, but I want briefly to address some of the points made by the hon. Member for York Central (Rachael Maskell) from the Labour Front Bench. I agreed with much of what she said about economic investment and the need to ensure that things all join up. However, I must gently chide her on one key point: we have not stopped work on east-west links across the north. I met only the other week with both Network Rail and Transport for the North to talk about how they are bringing forward Northern Powerhouse Rail. I have always argued that HS2’s full potential will not be fully delivered unless we properly improve east-west links as well. It is not for me to determine the engineering solution that Network Rail will alight on for any particular line or stretch of line, but that work is ongoing—on a cross-party basis, as Transport for the North is also governed by Labour local government leaders across the north, who are also setting the objectives. That seems to me to be how things should be taken forward.

Rachael Maskell Portrait Rachael Maskell
- Hansard - -

Will the Minister give way?

Paul Maynard Portrait Paul Maynard
- Hansard - - - Excerpts

If the hon. Lady will forgive me, I will not; I am sure it will not be the last time we have the discussion, and I must give some time to the concerns of my hon. Friend the Member for Eddisbury. Her main concerns focused largely on some of the ground instability problems that we encounter in Cheshire, crossing the salt fields. As someone born and bred in Northwich I have been brought up on photos of houses that have collapsed because of subsidence, and have suddenly disappeared into the Bull Ring in the town centre. I am more than aware of those issues; but I reassure hon. Members that we are seeking to manage them actively.

HS2 has commissioned a specialist mining engineer, in consultation with the Cheshire Brine Subsidence Compensation Board, to undertake a study on the consultation route using available data such as those from the British Geological Survey, the salt industry and local authorities. Those light detection and ranging surveys have been completed by HS2 Ltd, identifying the wet rockhead features to which my hon. Friend referred near to the route, and will be considered with other LIDAR surveys. I think it is fair to say that between Crewe and Manchester every route option presents risks and issues. It is a matter of balancing those carefully and working out which offers the optimum solution. We carefully weighed those matters both in 2013, when we listened to concerns, and on the now-confirmed 2016 route. On our assessment those risks were more manageable on the latest version of the route. One of the key reasons for that was to avoid the gas storage caverns to which my hon. Friend referred. The route has been moved to better avoid salt brining and gas storage infrastructure, reducing underlying mining and geological risks during construction and operation. The route has also been raised to better allow for drainage and options for ground stabilisation. In terms of travel through Cheshire, other alternatives were looked at, including tunnelling options, but this was felt to be the best option of those on the table.

My hon. Friend the Member for Eddisbury referred to the report by TerraConsult. Its first report was taken into account before the November 2016 announcement, as was its second report before the July 2017 announcement. I further understand that HS2 Ltd is meeting on Tuesday 12 September with TerraConsult and Mid Cheshire Against HS2 on how HS2 Ltd came to make its recommendation on the alignment between Middlewich and Pickmere. Senior engineers with a background in geotechnical engineering will attend that meeting. I also understand that HS2, accompanied by engineers, is more than happy to meet my hon. Friend to discuss her concerns and is waiting to confirm a date with her office. Once she has had that meeting, I will still be more than happy to put myself—with my limited expertise—at her disposal also.

I recognise that this is a sensitive and complex section of the route. There is more work to be done to further assess geological risks and to provide suitable mitigations for them. HS2 Ltd plans to carry out early geotechnical investigation work in the mid-Cheshire area to gather more advanced survey information. We will continue to work with my hon. Friend to try to ensure that the best mitigation possible occurs.

I also want to touch briefly on my hon. Friend’s concerns about the siting of the depot at Wimboldsley and its proximity to the primary school. The re-siting of the rolling stock depot to Wimboldsley has taken into account both the potential risks of the previous site in Golborne, which saw the demolition of a grade I listed property, and the potential impacts in Wimboldsley. The site is strategically located on the HS2 network, south of the Manchester junction, so that it can receive empty trains from both the HS2 main line—from Preston and indeed further north—and the HS2 Manchester spur. It is also located at the point where the line deviates from the existing west coast main line, so it is also well placed to receive empty HS2 trains from Liverpool. Other locations around Basford and Crewe are less proximate to where empty trains from Liverpool and Manchester might be coming from.

While I understand that there will be impacts associated with the rolling stock depot, I very much welcome the fact that HS2 Ltd is in conversation with the headteacher at Wimboldsley Primary, and I hope that any outstanding concerns get fed into me as well, so that I am aware of them.

In particular, this proposal avoids direct impacts on the grade II listed buildings to which my hon. Friend refers and also proximity to sites of special scientific interest. I recognise that there are still concerns about the Leeds and Liverpool canal. Indeed, other canals were also mentioned. As someone born in mid-Cheshire, I have a great fondness for canals and want to ensure they do not suffer in this process.