Peter Fortune
Main Page: Peter Fortune (Conservative - Bromley and Biggin Hill)Department Debates - View all Peter Fortune's debates with the Department for Transport
(1 day, 7 hours ago)
Westminster HallWestminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.
Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
Fleur Anderson
I thank the hon. Member for his acknowledgment of the many years that I have been campaigning on this issue and that he has seen me raising it in the Chamber. I agree that there is no time to wait, because the longer we wait, the more the bill goes up, as well as the hardship continuing for us.
Built in 1887, Hammersmith bridge is one of the world’s oldest suspension bridges. It is a grade II listed structure made of wood and wrought iron; its suspension system rests on cast-iron pedestals. It is not just a piece of infrastructure, but part of Britain’s engineering heritage and a national landmark.
However, this is not just about history; it is about people. Hammersmith bridge has always been a lifeline, a critical connection across the Thames used by thousands of cars, people and cyclists—and six bus routes. For seven years, that connection has been broken. The bridge was closed in 2019 on public safety grounds after microfractures were identified in the now 138-year-old structure. It later reopened to pedestrians and cyclists, and in April 2025 the carriageway reopened to pedestrians, cyclists, wheelchair users and e-scooter users, but not to any vehicles or those buses. That ongoing closure continues to have profound and far-reaching consequences for my constituents, especially in Roehampton, which is directly south of the bridge, and in Putney, which has the alternative bridge if people are going east.
The impact on daily life has been severe, sustained and deeply felt. Residents in Putney, Barnes, Richmond and Hammersmith have endured years of longer journeys, unreliable transport and constant congestion. I conducted a survey of residents and found that 90% of respondents described the closure as “extremely disruptive”. That comes as no surprise to anyone living locally. This is the issue that comes up all the time, at every event that I go to and almost every door I knock on.
Before the closure, around 22,000 vehicles crossed the bridge each day. Those journeys have not disappeared; they have simply been forced on to other routes, creating daily gridlock across neighbouring areas such as Putney. The latest snapshot data from the Department for Transport shows that, between 2020 and 2023, the overall number of motor vehicles on Putney bridge increased by 16%. Bus services were among the first and hardest hit. Six major routes, including the 209, were withdrawn, and have still not been reinstated. Others, such as the 533, have been diverted, leaving services overcrowded, delayed and unreliable.
Congestion in Putney has now become so severe that in January last year I called together the bus services, Transport for London, the council and the utility services to say, “Look, there’s a real problem here in Putney.” Transport for London officials replied, “Yes, there is. We look across the whole of London, and Putney is especially congested.” In their opinion, part of the reason for that is the closure of Hammersmith bridge.
Peter Fortune (Bromley and Biggin Hill) (Con)
On that point, how does the hon. Lady feel about the funding that TfL offered for the reopening of the bridge? To my mind, as a former member of the London Assembly, it has not been sufficient over the last 10 years.
Fleur Anderson
I thank the hon. Member for that question; I will ask the Minister the same thing. Where is that funding? Has agreement been reached between the three bodies, Transport for London, Hammersmith and Fulham council and the Department for Transport? That was the agreement, but where is the agreement now? I am not sure where it is or what funding is on the table, so I am hoping to hear from the Minister later.
The bus taskforce that I mentioned has had to meet monthly since then and is still meeting. It is really good and we are getting a lot done—we are making changes to try to get the traffic moving—but we still have the constant background of the closure of Hammersmith bridge, which in effect makes transport, particularly on the roads in my constituency and those surrounding, less resilient. When one thing happens, there is a knock-on effect that significantly clogs up the roads.
Seven years on, residents, commuters and businesses in Putney are still paying the price. For many residents in Putney and Roehampton, it is not a minor inconvenience or something we could have just got over in the last seven years; it is a fundamental barrier to daily life. The majority of households in the London borough of Wandsworth do not have a car. They rely on buses to get to work, school and medical appointments, as well as to see family. The loss of these connections has made everyday life significantly harder.
Behind the statistics are real people, real stories and real consequences. Ana is a constituent from west Putney who came along to my recent action event at the bridge. She has a 12-year-old son, Santiago, who has Down’s syndrome and complex needs. He attends a specialist school in Hammersmith on the other side of the bridge, which is the nearest school equipped to support him. Before the closure, their journey was straightforward and manageable. Since then, it has become an exhausting and unpredictable ordeal, often taking well over an hour each way.
On one occasion, Ana allowed two full hours to take Santiago from school in Hammersmith back to a medical appointment at St George’s hospital. The journey took nearly three hours and they missed the appointment entirely. Even when the hospital kindly rescheduled, the same journey the following week still took two and a half hours. It should take nowhere near that and certainly would not if the bridge were reopened to vehicles. That is not just an inconvenience; it is missed healthcare.
Furthermore, the closure has cut Santiago off from important social opportunities. He used to attend weekly football sessions for children with Down’s syndrome in Shepherd’s Bush, which supported his physical health, confidence and social development, but the journey became so long and exhausting that he would fall asleep in the car. Eventually, he had to stop attending altogether, missing out on three years of those vital physical activities. I have spoken about Ana’s experience at length because it highlights something we must not overlook: although the closure affects everyone, disabled children and their families are hardest hit. Public transport is not always a viable option, and the long diversions that currently exist place enormous strain on already complex routines.
I have heard countless more stories from constituents before and since I told them about this debate. Caroline, another resident, drives to visit her 92-year-old mother for dinner on Fridays. What used to be a 40-minute journey before the bridge closure now takes up to two hours. Paula told me that her heart sinks every time she gets into her car to visit her daughter and family in Hammersmith. With only one viable route left via Fulham Palace Road, what was once a straightforward journey now often takes twice as long with no certainty about the delays she will face. These are the quiet, cumulative losses—a loss of time with loved ones, missed moments and added stress—that rarely make the headlines, but define people’s daily lives.
I have also heard from residents whose cancer treatments have been disrupted, from separated parents struggling to maintain contact with their children, and from students cut off from study opportunities. Some of the words my constituents have used to describe the reality of living with the bridge’s continued closure are: “nightmare”, “miserable”, “unsafe”, “disastrous”, “absurd” and “national scandal”. That is the human cost of inaction on the bridge.
The consequences are not just limited to individuals; they extend across the local economy as well. More than 75% of local businesses report moderate or severe negative impacts as a result of the closure. Reduced footfall in shops, delayed deliveries and staff struggling to get to work have all taken their toll. Small businesses in Putney have been hit hard. Customers are deterred by the congestion. Journeys that should take minutes take far longer. Deliveries are delayed and more expensive. The closure has created a drag on economic activity across Putney, Barnes, Hammersmith and beyond. At a time when local high streets are already under pressure, it is an added burden they can ill afford.
There is also a clear environmental cost. Thousands of additional vehicles are now being diverted through already congested roads, especially Putney High Street, because we can only go along to the next bridge—we do not have all the options that there would otherwise be in a different area. This has led to increased air pollution, higher noise levels and more dangerous conditions for road users. Cyclists are put off cycling through Putney because of the higher congestion and heavier traffic, making it feel more unsafe. I really am worried about potential cyclists—the people we want to get out of their cars and on to the roads using more active travel—because many in Putney are put off. Bus journeys, as I have said, are further delayed as well. The overall effect is a transport network that is less efficient, less safe and less sustainable, and that is not good for our environment.
The situation has now become even more acute. On the other side of us, the closure of Albert bridge in February 2026, again due to structural issues, is expected to last up to a year, and we do not know how much longer. That has placed even greater strain on the remaining crossings and has intensified congestion across south-west London. Albert bridge carried 20,000 vehicles a day before the February closure. With two key bridges affected, residents are effectively being cut off from travelling north of the river in a reasonable and reliable way. Of course they can travel, but it is the extra time and the unreliability that people tell me about. For a global city like London, that is not sustainable.
Connectivity is not a luxury. It is essential for economic growth, access to services, and the functioning of daily life. Since being elected in 2019, I have consistently campaigned for the full reopening of Hammersmith bridge to vehicles, including buses. I have raised the issue 26 times in Parliament. I have secured debates and led action days and public meetings in Putney. I have worked closely with residents and with Wandsworth borough council, which is also fully engaged and supportive of the restoring of the bridge. I have also worked with campaigners, including the Putney Action Group and Putney Society. I have raised the matter directly with the Prime Minister and pressed for leadership and urgency, and I have raised it with the Mayor of London.
Since April 2019, Hammersmith and Fulham council has spent nearly £54 million simply to make Hammersmith bridge safe. To put that into perspective, all London councils combined spent just £100 million between 2010 and 2021 on maintaining and repairing every road and river bridge across the capital, and even then much of that cost was ultimately picked up by Transport for London or central Government. The impact on Hammersmith and Fulham council’s budget is disproportionate. Thanks to the council’s action, Hammersmith bridge is no longer in danger of collapsing into the Thames, but it still costs the council around £2 million a year just to maintain its current restricted state. That money does not deliver a permanent solution; it merely postpones failure.
Hammersmith and Fulham council cannot afford to fund further repair works. Continuing to spend millions of pounds on temporary fixes is financially unsustainable and fundamentally unfair. The current approach is not viable and cannot continue. It is wholly unreasonable to expect Hammersmith and Fulham council to shoulder sole responsibility for a nationally significant, grade II listed heritage bridge. The unfair cost share must be addressed. In contrast to the Albert bridge, where funding is shared 75% by Transport for London and 25% by the Royal Borough of Kensington and Chelsea, responsibility for Hammersmith bridge falls disproportionately on Hammersmith and Fulham council, which is expected to fund around 33% of the enormous cost.
Where are we now? Years of stalemate have produced an internationally embarrassing situation and daily frustration for residents, businesses and commuters. That cannot be allowed to continue. I am glad that the new Government and the Minister have taken a much more active role, as the previous Government were so dismissive. The Minister has brought together key stakeholders for the taskforce. A meeting was held at the Department for Transport in January 2025, which I attended along with the key bodies, including the Department for Transport, Transport for London, Hammersmith and Fulham council, Richmond council, Wandsworth council, the deputy mayor for transport, Historic England and the Port of London Authority.
The taskforce considered six options, which I know really well because I get asked about them all the time on the doorstep; people want to know what the options were, what is happening and what will happen next.
Option zero, which is the one that is kind of on the table, is the Foster and Partners and COWI proposal to deliver a temporary double-deck crossing within the existing structure of Hammersmith bridge, allowing pedestrians, cyclists, buses and cars to use the bridge while the full repair and restoration works are carried out around it using barges.
Option one was bridge closure with no access allowed; the structure would remain a beautiful monument, but no more than that. Option two was bridge repair and restoration sufficient to allow for active travel by pedestrians, cyclists and two single-decker buses. That would restore the bridge to how it was before the closure.
Option three was bridge repair and restoration sufficient for active travel only. Option four was a replacement bridge with a 44-tonne weight limit—to just get rid of the bridge and build a new one. I cannot tell Members how many Putney residents are in favour of that one. Option five was an offline replacement bridge—one somewhere else—with the existing structure remaining in place either around it or next to it.
I really appreciate that the Minister took a back-to-basics approach at the meeting to assess all the options and to see where we are now. In the meeting, option zero—the Foster and Partners and COWI one—remained on the table, and options one, four and five were ruled out on cost grounds. At that meeting, the Minister was also clear that leaving the bridge as it is “is not an option”. Officials were tasked with properly costing the restoration, and Historic England agreed in the meeting to look at revisiting its requirements, which is an important step that could help reduce the previously estimated £240 million cost.
I welcome the confirmation since then that funding may be available through the national structures fund and the Minister’s recent statement that Hammersmith bridge would be a strong candidate for investment from that fund. More broadly, the continuing impasse exposes a deeper structural problem. Now is the time to review the ownership and responsibility for all the bridges in London. These strategic assets should sit under a single authority with responsibility for maintenance, repairs and long-term investment. They should be taken out of the responsibility of local councils and put in the responsibility of one single body.
In conclusion, Minister, what concrete actions have been taken since the last taskforce meeting in January 2025? Is the Foster and Partners and COWI option still being assessed and considered? What is the current estimated cost—the updated figure—of fully restoring Hammersmith bridge? Have there been meetings, with decisions made, between Hammersmith and Fulham council, Transport for London and the Department for Transport, and has a viable agreed plan been reached between those three bodies? Has an application been made under the structures fund? If not, when will it be made? Either way, when will a decision about the structures fund funding be made? When will the taskforce next meet—I hope it will be soon—and will a firm timetable be shared with it? Finally, has any assessment been made in consultation with the Mayor of London on transferring responsibility for all bridges to one London body?
Let me be clear: action must be taken now. Potential funding is not the same as secured funding, discussions are not the same as decisions and processes cannot become excuses for further delays. Residents have waited for seven long years—seven years of severed communities, gridlocked roads, lost bus routes and daily hardship. That is not acceptable for a major transport route in our capital city. It is not acceptable for families trying to get to school or hospital appointments. It is not acceptable for businesses trying to survive. It is not acceptable for the many residents who rely on public transport simply to live their daily lives. The social, economic and environmental costs are too high. The human impact is too great.
What is needed now is clear and urgent: a fully funded plan, a clear and credible timetable, and decisive action to begin—and then end—restoration without further delay. The bridge has stood since 1887; it has served generations of Londoners. Now is the time to restore it and to reconnect the communities who depend on it.