Nickie Aiken
Main Page: Nickie Aiken (Conservative - Cities of London and Westminster)Department Debates - View all Nickie Aiken's debates with the Leader of the House
(4 years, 5 months ago)
Commons ChamberI beg to move,
That this House has considered Restoration and Renewal.
The Palace of Westminster is a magnificent building, which must be saved for future generations. Charles Barry and Augustus Pugin’s creation is a triumph of neo-Gothic architecture, recognised the world over. Within these walls, our history, architecture and politics are entwined together. It is a place that inspires us as politicians, just as it inspires the many schoolchildren who visit Westminster. On the Palace walls, the history of their nation is writ large: from the exploits of King Alfred to the stonework damaged by Nazi bombs, left unrepaired as a reminder that this House stood firm against tyranny; from the great Tudor portraits in the Prince’s Gallery to representations of both sides of the civil war, and to the great statesmen—Walpole, Pitt, Burke —who graced St Stephen’s with their rhetoric.
Then we have Westminster Hall—a space that has been at the heart of our national life for nearly a millennium. Built by William Rufus, its hammer-beam roof completed by Richard II, it was the one part of the building that the firemen fought to save as the rest of the Palace succumbed to the flames in 1834. There were the trials of Thomas More, Thomas Wentworth, Charles I. So many great events took place in Westminster Hall. It was the centre of justice and the seat of wisdom for centuries. I want the children and grandchildren of the 1 million pupils who have visited us in recent years to be able to come here and learn about their nation’s history. I want them to be as inspired as I was when I first visited here as a child and won a prize—a biro—for knowing more parliamentary facts than any of my fellow pupils at that time.
The prize we are now seeking is the Palace of Westminster itself. This is a building that must remain part of our national heritage for centuries to come, but it is also a building which, if we fail to act, risks being lost to history forever. Over the years, the Palace has become an increasingly complex and flawed proposition for those tasked with its preservation. Like the barnacled encrustations on the hull of a noble ship, layer upon layer of incremental changes have been built up over the years, just as the challenges of managing an ageing building have built up, too.
Since 2017, there have been over 40,000 problems reported and the Palace is now deteriorating faster than it can be repaired. Anyone who ventures into the basement will see for themselves why. Steam pipes run alongside electric cables. Hundreds of miles of cabling are now in need of replacement. A sewage ejector, installed in 1888, is still in use today. In short, there is a meandering multiplicity of multifarious materials all in need of urgent attention and all increasing the vulnerability of the building. Those who want to see what 150 years of patch and mend looks like are advised to descend into the depths of the Palace and see for themselves.
When I returned to the basement yesterday, I was pleased to find a newly installed system, which will fill the space with a fine mist in the event of a fire. That is among the remedial but temporary measures put in place in recent years to address the possibility that the building might be imperilled by a serious blaze. I am advised that steps such as extra emergency lighting, the installation of new alarms, day and night fire patrols and so on ensure that life will be safe. What cannot be guaranteed is that our historic palace can be saved from destruction in the event of a serious fire. We have known for a long time that, if a blaze were to take hold, the lack of compartmentation would endanger the entire building, so it is a matter of some frustration that comprehensive fire safety alterations have not begun because we have been waiting for the main R&R programme.
Fortunately, we are now moving towards the historic moment when this House is asked to approve a motion allowing the works to commence in the mid-2020s as planned. Such a decision, involving billions of pounds of public funds, taxpayers’ money, which would ideally be spent elsewhere, cannot be taken on a whim, so three requirements must be met if the restoration and renewal programme is to command the confidence of the House and of taxpayers: first, the proposal must be robust and evidence-based; secondly, it must give value for money and we must cut out unnecessary spending; and thirdly, the plans need to be up to date.
No one here today will forget for a moment that we are discussing this matter in the midst of a global pandemic, which is placing great strain on the nation’s purse strings. Today’s debate is a chance to set out our expectations in this context, and this should be a limited project to replace failing mechanical and engineering equipment, not an opportunity to create a second Versailles.
This debate also gives us an opportunity to note how far we have come since Deloitte produced its independent options appraisal in 2015. The Joint Committee’s report of September 2016 was followed by the motion of January 2018, which led in turn to the passage of the Parliamentary Buildings (Restoration and Renewal) Act 2019. This legislation addressed the first of our three requirements—that the proposals must be robust and evidence-based—by adopting the governance structures used to deliver major infrastructure projects such as the 2012 Olympic games. The Sponsor Body will act as the client on behalf of Parliament and oversee the delivery of the works, which will be entrusted to a Delivery Authority equipped with the expertise needed to keep costs down and to manage a project of this complexity.
The Delivery Authority is already showing the value of its professionalism by getting on with the basics, undertaking detailed investigations of the palace’s condition. Once these surveys are completed, it will then move on to preparing detailed proposals in the form of an outline business case. There can be no blank cheque for this work, which is why it so important that the outline business case will be fully costed. This will be the first time that we have had a proposition that we can assess in value-for-money terms, which is the second essential requirement before Members are asked to make their decision. Rather than hurrying along in an over-hasty fashion—[Laughter.] I am glad that I am creating such hilarity on such a serious subject. It is crucial that we take the time and accept the expense required to get this right—the right price to pay for the assurances we need that the project will be delivered on time and on budget.
I appreciate what my right hon. Friend is saying about the cost. Obviously, this marvellous palace is in the heart of my constituency, so it is a very precious place for me. None the less, at a time when we are spending billions of pounds in the economy following the covid-19 crisis and beyond, does he agree that we must be very careful about how much we spend on this project, because the public will expect us to be very careful about how we spend money on ourselves.
My hon. Friend is absolutely right: we must ensure value for money. I was going to refer to the example of the refurbishment of the Elizabeth Tower, because we have to know what we are going into. The refurbishment of the Elizabeth Tower offers a cautionary tale in this respect. Such is the nation’s affection for Big Ben that I have no doubt we would not have objected to spending £80 million on its refurbishment, if that had been the initial price tag placed on it. The mistake that was made was in initially releasing the figure of £29 million, which was little more than a guess. That is why it is right to spend the time and money on developing a business plan so that we know what we are going into.
It is with this in mind that I advise the House in the strongest possible terms to disregard the endlessly quoted estimates drawn from the Deloitte report of June 2015. These numbers were merely comparisons with other options at that time and before any detailed scoping could take place. We cannot know how much the programme will cost in reality until the outline business case is published, but we can be assured that we now have the programme and infrastructural professionals, drawn from industry, who will be able to produce the comprehensive plans we need.
The Delivery Authority is making good progress, but it needs further clarity on what is expected of it, and this stands to reason. As both the National Audit Office and the Infrastructure and Projects Authority have highlighted, the cost estimates or ranges cannot be set out before the scope and requirements of what is needed are fully understood. Doing that means ensuring that the proposals are fully up to date, which is our third and final requirement.
So much has changed since the Deloitte report of 2015, not least the pandemic, which is having an enormous effect on our way of life, our way of working and economic activity more generally. That is why it is quite proper for the Sponsor Body to conduct a strategic review to consider whether the basis for options developed over previous years has changed significantly enough to warrant a change in strategy. The review should determine how the various options should be assessed. Timelines for delivery, heritage benefits, fire safety and cost must all be considered in the round, and the views of parliamentarians on all this matter greatly. It comes down to a simple question: how much inconvenience are we prepared to accept?