Leaseholders and Cladding

Munira Wilson Excerpts
Tuesday 24th November 2020

(4 years ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Christopher Pincher Portrait Christopher Pincher
- Hansard - - - Excerpts

I can certainly confirm that buildings that are without cladding should not have an EWS1 form apply to them. EWS1 forms can be applied in other egregious circumstances, and we are working with the sector to make sure that we obviate, as far as is possible, the responsibility of leaseholders to provide those forms. There is more work to be done to ensure that buildings can have their value restored to them and that people can move effectively without recourse to an EWS1 form.

Munira Wilson Portrait Munira Wilson (Twickenham) (LD) [V]
- Hansard - -

In my local authority of Richmond upon Thames, remediation work has either been started or completed on fewer than 50% of buildings with dangerous cladding. Leaseholders living in these buildings, such as the residents of the Sandy Lane estate in my constituency, are living at constant personal and financial risk. So may I press the Minister again: will he, in the first instance, commit to covering the costs of both the assessment and the remedial work, to keep not just my constituents safe, but leaseholders across the capital and the country, and claim the money back from freeholders and developers later?

Christopher Pincher Portrait Christopher Pincher
- Hansard - - - Excerpts

As I said a moment ago, some 79% of all identified high-rise ACM buildings have either completed or started their remediation, and some 97% of social sector buildings have either completed or started their remediation. I know that there are specific challenges in London, which is why the Secretary of State and Lord Greenhalgh have undertaken roundtables with the Mayor, the fire brigade and the sector to ensure that the pace of acceleration is speeded up. We want to make sure that this work is done. We will continue to work with the developer community and with leaseholders to make sure that it is. Where necessary, as we have already demonstrated, public money will be spent, but in the first instance the responsibility should fall on those who built these buildings or who own them.