Flammable Cladding Removal Debate
Full Debate: Read Full DebateMeg Hillier
Main Page: Meg Hillier (Labour (Co-op) - Hackney South and Shoreditch)Department Debates - View all Meg Hillier's debates with the Ministry of Housing, Communities and Local Government
(4 years, 4 months ago)
Commons ChamberIt is beyond belief that it has been three years since that terrible night at Grenfell Tower. I want to begin by paying my respects to those who lost their lives, and we will remember them today in this debate. We are also incredibly grateful to their family members, their neighbours and the survivors for campaigning, despite all they went through, for the safety of properties that are clad with dangerous aluminium composite material and also of other properties that are a risk.
There are still an estimated 60,000 people living in homes with similar ACM cladding on the outside of their buildings, and many more living in buildings that are dangerous. According to the Fire Brigades Union, some 500,000 people are at risk from living in unsafe housing across the UK. Each night, they are going to bed, knowing that, if their building caught fire, it would spread quickly because of the flammable cladding, and they know, too, that their chances of survival are seriously lessened in that context. They know that progress to remove that cladding has been slow and has slowed further because of the pandemic. I have called for this debate because I think that it is vital that Ministers step up and make sure that the cladding and other dangerous materials on those blocks are removed as a matter of urgency.
It took a year for the Government to agree to fund the removal of ACM cladding in high-rise social housing blocks and then two years for private blocks and three years for others commitments to be made. That happened because of the actions of campaign groups such as Grenfell United, the UK Cladding Action Group and Inside Housing, as well as Members of Parliament and charities and housing organisations. It is not good enough that the Government have been forced kicking and screaming into doing these things, rather than taking responsibility, as was promised at the time of the fire. Although £1.6 billion of Government funding is welcome, they estimate themselves that between £3 billion and £3.5 billion is required to make all buildings safe.
Residents feel like prisoners in their homes. They cannot sell or remortgage their flats, and the external wall fire review and EWS1 form process is not sufficient, is costly and takes too long. They are trapped.
My hon. Friend raises an important point about the paperwork needed. Even many residents who live in homes that are not as unsafe as some others find that without that form they are unable to sell. One of the things the Public Accounts Committee picked up on in our recent hearing was that being unable to get professional indemnity insurance is a major brake. Does my hon. Friend agree that the Government need to step in on this issue?
Yes, absolutely, and I hope that the Minister will, along with his Treasury colleagues, look at this very quickly to resolve the matter, because it affects people who are trying to sell homes, as I have seen in my constituency.
I am obliged to my hon. Friend for that intervention. I will not dwell on any particular tower block or issue, but let me simply say that our intention is to make sure that leaseholders should not have to foot the bill; building owners and building managers and their agents should be looking after their buildings. That is why the Government have intervened with funding and specialist support, and we will not tolerate any further delays. Where building owners are failing to make acceptable progress, those responsible should expect local authorities and fire and rescue services to take tougher enforcement action.
By the end of May, of the 455 identified high-rise buildings with ACM cladding, 209 had either completed remediation or had their ACM cladding systems removed, while a further 86 had started remediation but not yet had ACM cladding removed. However, although there has been progress, there is much more to be done. We are under no illusion about that. For the removal of unsafe ACM cladding, we are aiming for all building owners to have works on site by the end of 2020, with completion of remedial works by the end of 2021. It is a challenge, but one that we are determined to meet.
Even with public funding available, the pace has been much too slow. We recognise that remediation is a complex undertaking and that every building is different; we also understand that building owners do not always have the requisite expertise or experience to advance the work. We have therefore recently appointed Faithful+Gould as specialist construction consultants to help responsible entities to increase capacity and capability and to support them directly through the remediation process. F+G is currently working with those buildings identified as most at risk of missing the end-of-year date. It is examining project plans and seeking ways to reduce timescales to mobilise projects.
Overall, the Government have set aside £1.6 billion in funding for the remediation of ACM and other types of unsafe cladding from high-rise residential buildings in the private and social housing sectors. We made that money available to support the remediation of unsafe cladding, and a large proportion of that support will protect leaseholders from costs. We recognise that there are wider remediation costs that will need to be met to ensure the safety of existing blocks of flats, but the public funding does not absolve the industry from taking responsibility for any failures that led to unsafe cladding materials being put on those buildings in the first place. We expect developers, investors and building owners who have the means to pay to take responsibility and cover the cost of remediation themselves, without passing on costs to leaseholders.
The Government have committed £600 million to remediate buildings in the public, social and private sectors and speed up the pace of remediation of ACM cladding. In the private sector, although some developers said that they would meet the costs, it became clear that a significant number of building owners could not or would not do so, and therefore funding needed to be made available to enable progress. That is why in May 2019 we announced that £200 million of funding would be available for ACM remediation in private sector buildings, and the fund was opened for applications in September that year. As of May 2020, the Department expects to pay for 94 projects in the private sector where the developer or building owner has not agreed to fund remediation work themselves. The owners of 84 private sector residential buildings have committed to funding the remediation works themselves, with a further 23 self- funded through accepted warranty claims. We are working with a handful of other buildings where a funding route has yet to be agreed. The availability of funding and a direct package of support for building owners means that there can be no excuses for further delays. For those who fail to make acceptable progress, tougher sanctions are coming, first through our Fire Safety Bill, currently before Parliament, and subsequently when our new building safety regime comes into place.
We have always acknowledged that there are materials other than ACM cladding that are of concern. We have been providing advice on their removal to building owners since 2017. The highest priority has been the removal of the type of ACM used on Grenfell Tower because it poses the most severe safety risk, but there are other unsafe cladding materials that must also be removed. That is why in March this year we announced an additional £1 billion of funding for the remediation of unsafe non-ACM cladding in the social and private residential sectors. We expect this funding to be fully committed by the end of March 2021. The new building safety fund will cover high-rise buildings with unsafe non-ACM cladding, such as some types of high-pressure laminate.
The issue of waking watch was raised by the hon. Member for Bethnal Green and Bow and by other hon. and right hon. Members. I know that leaseholders have concerns about costs of interim measures—costs that have been heightened due to the covid-19 emergency. These interim measures include waking watches. Waking watch is meant to be a short-term tool: it is no substitute for remediation. But the only way to remove the need for interim measures is to remove unsafe cladding as quickly as possible. That is why we are prioritising £1.6 billion of public subsidy on remediation of unsafe cladding. That said, my noble Friend Lord Greenhalgh, the Minister with responsibility for building safety, is investigating what we can do to reduce the cost of waking watch. This includes publishing data on the costs of waking watch to ensure greater transparency on costs. Moreover, the National Fire Chiefs Council is updating its guidance. We have asked the fire protection boards to advise fire and rescue services on how best to operationalise the revised guidance, including looking to measures such as installing building-wide fire alarm systems.
Will the Minister commit to looking at the issue of professional indemnity insurance? This does need a good political fix at the top.