Fire Safety Remedial Work: Leaseholder Liability

Debate between Marsha De Cordova and Heather Wheeler
Thursday 19th April 2018

(6 years, 7 months ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Heather Wheeler Portrait Mrs Wheeler
- Hansard - - - Excerpts

The important thing is that the Hackitt review has already released interim recommendations, which we have accepted. We await the review to report later this summer. That will be the answer going forward.

All the social housing blocks and affected social sector buildings that we swiftly identified had the measures in place. In parallel, we tested different combinations of cladding and insulation to see which of them met the building regulations guidance. We published consolidated advice in September, confirming the results of the tests with advice for building owners. We have also been working with building owners and industry to support remediation work.

At the same time, the Government asked Dame Judith Hackitt to undertake an independent review of building regulations and fire safety to ensure that buildings are safe in future. We are taking forward all of the recommendations for Government contained in the interim report, and look forward to the publication of her final report shortly.

We believe we have identified all affected social housing blocks and public buildings. With regard to private sector buildings, the Government have made the testing facility at the Building Research Establishment available free of charge, and we continue to urge all building owners to submit samples for testing if they think that they may have unsafe cladding. In addition, the Secretary of State wrote to all local authorities in August asking them to identify privately owned buildings with potentially unsafe cladding in their area in line with their statutory duties.

Marsha De Cordova Portrait Marsha De Cordova
- Hansard - -

On that point, my local authority, Wandsworth Council, has still not published any information around those private blocks that could potentially have flammable cladding. Will the Minister take it on herself to continue to press the council to get on with the job and publish the information? She made the recommendations last summer.

Heather Wheeler Portrait Mrs Wheeler
- Hansard - - - Excerpts

I hear what the hon. Lady says. We have close contacts with Wandsworth Council.

In addition, the Secretary of State wrote to all local authorities in August asking them to identify these properties. The majority of local authorities recognised the urgency of that work and provided relevant information, and we are very grateful for their hard work. However, this is not a straightforward task, particularly when building owners cannot be traced or are unresponsive. We have been in constant dialogue with local authorities ever since. Last month, to support local authorities in that work, we announced a financial support package of £1 million to assist the most affected local authorities in identifying the remaining private high-rise buildings with potentially unsafe cladding.

We are progressing work to issue a statutory direction as to local authorities’ reviews of housing conditions in their area in respect of cladding-related issues. We are also working to publish additional operating guidance to support local authorities in assessing the risks to residents posed by potentially unsafe cladding.

These measures will help local authorities to take enforcement action to ensure that hazards in residential buildings in their areas are remediated as quickly as possible. I am confident that these steps will strengthen local authorities’ hands when carrying out this work. I can assure hon. Members that, as soon as we are notified of buildings with potentially unsafe cladding, we work with local authorities and the National Fire Chiefs Council to ensure that interim measures are put in place.

The Government have been clear that remediation should be done as quickly as possible, but it should also be done properly. Let us be clear: the remediation of buildings with ACM cladding is a complex process, involving major construction work which needs to be planned, consulted on and carried out carefully. Rushing any phase of the remediation process could jeopardise the safety of residents. I am encouraged that remediation has started on 103 affected social sector buildings and that, of those, seven have finished remediation work. There is clearly a long way to go, but that is significant progress.

I understand that funding is a concern for Wandsworth Council. In the social sector, all the local authorities and housing associations that we have spoken to have indicated that they have no plans to pass on the costs of essential remediation work to individual flat owners within their buildings. We will consider financial flexibilities for local authorities that are concerned about funding essential fire safety works to the buildings that they own.

In the private sector, we continue to urge those with responsibility to follow the lead from the social sector and not attempt to pass on costs. They can do that by meeting costs themselves or looking at alternative routes such as insurance claims, particularly warranties, or legal action.