South West Rail Resilience Programme Debate

Full Debate: Read Full Debate
Department: Department for Transport

South West Rail Resilience Programme

Lord Whitty Excerpts
Monday 22nd May 2023

(1 year, 7 months ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Berkeley Portrait Lord Berkeley
- Hansard - - - Excerpts

To ask His Majesty’s Government whether they intend to provide funding to ensure the timely completion of the works to protect the rail line at Dawlish from flooding, including Phase 5 of the South West Rail Resilience programme.

Lord Whitty Portrait Lord Whitty (Lab)
- Hansard - -

My Lords, on behalf of my noble friend Lord Berkeley, and with his permission, I beg leave to ask the Question standing in his name on the Order Paper.

Baroness Vere of Norbiton Portrait The Parliamentary Under-Secretary of State, Department for Transport (Baroness Vere of Norbiton) (Con)
- Hansard - - - Excerpts

My Lords, I can confirm that Network Rail has delivered two phases of the south-west resilience programme, providing protection to the railway at Dawlish from coastal flooding. The third and fourth phases addressing cliff protection measures are in delivery, with a combined budget of £85 million. Network Rail is being funding to deliver a detailed proposal for the fifth and final phase, which addresses cliff protection for a mile-long stretch of the railway.

None Portrait Noble Lords
- Hansard -

Order!

Lord Whitty Portrait Lord Whitty (Lab)
- Hansard - -

My Lords, I am glad to see that Members are so keen to speak. I thank the Minister for her reply, but it does not really answer the Question—or it does so only partly—and it does not reflect the importance of this line to the already existing problems of transport links to west Devon and Cornwall. Can she reassure us that the vital fourth and fifth phases—she mentioned the fourth, but not the fifth—will indeed be fully funded by Network Rail and the department? Can she give us an estimated date of completion to restore full resilience to this vital link to the far south-west?

Baroness Vere of Norbiton Portrait Baroness Vere of Norbiton (Con)
- Hansard - - - Excerpts

As I mentioned in my opening Answer, Network Rail is working on the fifth phase of the works in some detail; we need to establish detailed proposals for this mile-long stretch of the railway. Local consultations have happened, and there was some reluctance around some of the proposals put forward. Therefore, Network Rail is looking at the scope and costs of the fifth phase.