Levelling Up: Project Delivery

Lord Shipley Excerpts
Thursday 23rd November 2023

(5 months, 2 weeks ago)

Lords Chamber
Read Full debate Read Hansard Text Watch Debate Read Debate Ministerial Extracts
Baroness Penn Portrait Baroness Penn (Con)
- Hansard - - - Excerpts

I thank my noble friend for drawing out some of the positives of that report, as there were indeed some. He is right that, while we are keen to see the delivery impact of this investment as soon as possible, there have been some delays. For example, we have talked about inflationary pressures, so for the levelling-up fund, the prospectus for both rounds 1 and 2 said that we expected all funding provided to be spent by March 2024 and March 2025 respectively. However, those deadlines can be extended by one year on an exceptional basis. Similarly, for the future high streets fund, we have given a six-month extension for the spend deadline, taking it to 30 September next year, giving local places additional time to deliver their transformational projects.

Lord Shipley Portrait Lord Shipley (LD)
- View Speech - Hansard - -

My Lords, I remind the House that I am also a vice-president of the Local Government Association. As has been pointed out, one of the reasons for the problems we have is rising cost pressures, both inflation and interest rate levels, and in some cases, of course, withdrawal of contractors. Will the Minister assure the House that, in such circumstances, it cannot just be an “exceptional case”? I quote the phrase that she used in her previous reply. The NAO has shown that there is an average delay of almost 10 months across projects as a whole. That is simply too much, and I ask the Minister to consider very carefully extra money to support the budgets of projects where there is a case and, secondly, for an automatic extension to the length of budgets, otherwise we will carry on having some of the problems that we have seen.

Baroness Penn Portrait Baroness Penn (Con)
- View Speech - Hansard - - - Excerpts

My Lords, as I have said, we are keen to see the delivery impact of the investment as soon as possible. That is why we have not moved to an automatic extension to the deadlines involved. However, we have moved to give local authorities more flexibility about how they spend their money without coming back to central government, to enable delivery. We have also put in place both more funding and more support to local authorities in the delivery of their projects, to help them meet their own deadlines.