High Speed Rail (West Midlands–Crewe) Bill Debate

Full Debate: Read Full Debate
Department: Department for Transport

High Speed Rail (West Midlands–Crewe) Bill

Lord Rosser Excerpts
Report stage (Hansard) & Report stage (Hansard): House of Lords & Report stage
Monday 30th November 2020

(3 years, 4 months ago)

Lords Chamber
Read Full debate High Speed Rail (West Midlands-Crewe) Act 2021 View all High Speed Rail (West Midlands-Crewe) Act 2021 Debates Read Hansard Text Read Debate Ministerial Extracts Amendment Paper: HL Bill 142-R-I Marshalled list for Report - (25 Nov 2020)
Baroness Randerson Portrait Baroness Randerson (LD) [V]
- Hansard - - - Excerpts

My Lords, we received a useful briefing from HS2 prior to this debate. The final sentences read:

“Legislation to complete the Western leg of HS2 into Manchester is expected to come forward in 2022. Extending the line to Crewe is the first step to making this happen.”


There is a total absence of any reference there to the eastern leg. Other speakers have talked about the regenerative impact of HS2. This has already been demonstrated in Birmingham despite the line not being built yet. It is already a hotspot for inward investment, with high-quality jobs being created in major banks—HSBC and Deutsche Bank—as well as, importantly, in Jacobs Engineering.

The Government’s election rhetoric on levelling up won them seats in the north-east, and HS2 is an essential part of that. It is integral to delivering the plans of both the northern powerhouse and the Midlands engine. That means the whole of HS2; as the noble Lord, Lord Adonis, said, without the eastern leg it will be unable to improve the transport links across the country and to create new freight capacity.

This is all essential if the Government are to be able to decarbonise our transport system. Much more important than higher speeds is the capacity that HS2 will unlock. Only a very small percentage of commuters currently use rail in the north of England. For example, 7% of people commuting from Liverpool to Manchester, and 3% going from Hull to Sheffield, use rail. That is because services are slow and unreliable. HS2 will provide additional capacity on existing lines by freeing them up to enable faster, modern trains to provide many more services. Trains are the most carbon-efficient mass transport system available.

Existing rail freight services are far too slow. Freight is the most challenging part of our transport system to decarbonise. Road freight accounts for 5% of our nation’s CO2 emissions, so it has to be tackled. For example, it now takes 11 hours to send freight by rail from Liverpool to Selby, for the Drax power station. That is an unrealistically long time. It takes only three hours to take the same load by road. The Government cannot hope to improve productivity and create well-paid jobs in the north, while meeting our climate commitments, without revolutionising the infrastructure of the region. HS2 is the key to that—freeing us from reliance on a 19th-century rail system that is literally buckling under the strain.

What we need from the Minister today is a firm and unequivocal commitment to the eastern leg, with a timeframe that puts it on an equal footing with the west. We will be listening very carefully but, much more importantly, the people of the north-east are listening. They will not forgive, or forget, any attempt to renege on election promises. As noble Lords have made clear this afternoon, the case for the eastern leg has been made perfectly over the years. It is now well overdue for work to start on the details of this project.

Lord Rosser Portrait Lord Rosser (Lab) [V]
- Hansard - -

I do not intend to repeat all the points made so persuasively by my noble friend Lord Adonis and other noble Lords in support of his amendment. The Conservative Party manifesto for the 2019 election said that:

“HS2 is a great ambition”,


but, as we all know, great ambitions are not always realised in full. The manifesto went on to say that HS2,

“will now cost at least £81 billion and will not reach Leeds or Manchester until as late as 2040.”

Continuing, the manifesto said that:

“We will consider the findings of the Oakervee review into costs and timings and work with leaders of the Midlands and the North to decide the optimal outcome”.


In other words, there was no unambiguous commitment in the 2019 manifesto to complete HS2 via the East Midlands to Leeds, since the “optimal outcome” was dependent on government consideration of the findings of the Oakervee review into costs and timings.

In Committee, my noble friend Lord Tunnicliffe invited the Government to commit to building HS2 phase 2b to Leeds in full. In reply, the Government said that:

“Plans to provide the benefits of high-speed rail to the east Midlands, Yorkshire and beyond will be confirmed following the publication of the integrated rail plan”,


and,

“that a properly connected line from the Midlands up to the North will be a key part of the HS2 project.”—[Official Report, 9/11/20; col. GC 351.]

As we know, that reply was not a commitment to build HS2 phase 2b via the East Midlands to Leeds in full.

It would thus be helpful if the Government could clarify in their response what the phrases,

“plans to provide the benefits of high-speed rail to the east Midlands, Yorkshire and beyond”,

and,

“a properly connected line from the Midlands up to the North will be a key part of the HS2 project”,

actually mean. Do they mean that the Government are committed to building HS2 phase 2b via the East Midlands to Leeds in full, or do they mean not that the high-speed line will be built the whole way from Birmingham via the East Midlands to Leeds but that HS2 services could, for all or part of that journey, run over existing routes calling at existing stations?

The indications are that the Government are either looking to abandon or scale back the eastern leg of HS2 through to Leeds or, at best, seriously delay its construction and completion. The lack of a clear commitment to the HS2 project in full calls into question the Government’s declared commitment to levelling up, since the eastern leg is just as vital as the delivery of the western leg. Levelling up cannot just mean levelling up the north-west and the West Midlands. It is just as vital to communities in the East Midlands, Yorkshire and the Humber and the north-east. Indeed, only proceeding with the western leg would leave the cities and areas that would have been served by the eastern leg at a disadvantage.

The Government now have the opportunity to put to rest any concerns over their commitment to the eastern leg by saying, in their response today, that they are committed to the construction and bringing into operation of HS2 phase 2b to Leeds via the East Midlands in full, and giving the date by which they intend it will be completed. The Government can also accept the terms of this amendment. We will now have to see if they intend to take that opportunity. It will be for my noble friend Lord Adonis to decide whether he is satisfied with the Government’s response but, if he does decide to call for a vote, we will be supporting him.

Baroness Vere of Norbiton Portrait Baroness Vere of Norbiton (Con)
- Hansard - - - Excerpts

My Lords, I did a tally the other day; there are currently nine former Transport Secretaries in your Lordships’ House and I appreciate the wisdom of each and every one of them, including the noble Lord, Lord Adonis. I thank him for his amendment and hope that I will be able to satisfy him today. I will go as far as I possibly can. I hope that he will listen carefully to my words and take as much comfort from them as he is able. All noble Lords will recognise his enthusiasm for and commitment to HS2. I have read the amendment extremely carefully, but suggest that there is no need for it, as I hope to explain. The Prime Minister has been very clear that the Government’s plans for the HS2 eastern leg will be set out in the integrated rail plan and that this will be laid before Parliament within the timeframe referred to in the amendment. I make that commitment to the House today.

--- Later in debate ---
Moved by
4: After Clause 58, insert the following new Clause—
“Consultation with residents and stakeholders in relation to Phase 2a of High Speed 2 and associated works
(1) Before 1 May 2021, the Secretary of State must publish the report of a consultation with—(a) residents of the County of Shropshire, the County of Staffordshire, the County of Cheshire and any other areas deemed relevant by a Minister of the Crown, who may be impacted by the scheduled works, Phase 2a of High Speed 2, and associated works; and(b) any stakeholders deemed relevant by a Minister of the Crown.(2) The consultation must ask the views of residents and stakeholders listed in subsection (1) in regard to—(a) the impact of road traffic as a result of the works;(b) the impact of the works on the natural environment, including but not limited to the impact on ancient woodland;(c) whether there are sufficient transport provisions for the purposes of passengers connecting to Phase 2a of High Speed 2, and to address changes to general passenger movements caused by the works; and(d) if not, whether the construction of new railway stations and improvements to railway stations, including any associated reopening of lines, is necessary in relation to paragraph (c).(3) The report must be laid before both Houses of Parliament and a Minister of the Crown must make a statement to both Houses detailing any steps which will be taken to implement the findings of the report.”
Lord Rosser Portrait Lord Rosser (Lab) [V]
- Hansard - -

Amendment 4 in my name and that of the noble Baroness, Lady Randerson, requires the Government to consult the affected people of Shropshire, Staffordshire and Cheshire on how the construction works for HS2 phase 2a will impact on their communities and the natural environment, and whether there is sufficient transport provision to enable passengers to connect to phase 2a of High Speed 2, including whether the construction of new railway stations, improvements to railway stations and reopening of lines is necessary and needed.

The Government would be required to produce a report before the beginning of May next year on the outcome of the consultation, and lay it before both Houses of Parliament with a statement to both Houses detailing any steps that would be taken to implement its findings. The amendment does not seek to tell the Government what their response to the consultation should be, simply that they should consult further on the issues mentioned and produce a report to Parliament.

--- Later in debate ---
Baroness Vere of Norbiton Portrait Baroness Vere of Norbiton (Con)
- Hansard - - - Excerpts

I thank the noble Lord, Lord Berkeley, for raising that point. It is really important, so I will ask my honourable friend Minister Heaton-Harris, the Rail Minister, perhaps to write to him setting out his ambitions for rail nationwide, particularly how his ambitions for rail interact with the ambitions for HS2 and how that then produces greater rail connectivity.

Lord Rosser Portrait Lord Rosser (Lab) [V]
- Hansard - -

I thank the Minister for her response and indeed for her kind words. I also thank all other noble Lords who have participated in this debate.

My amendment calls for further consultation, seeking the views of residents and stakeholders

“who may be impacted by the scheduled works”,

including on whether there are

“sufficient transport provisions for the purposes of passengers connecting to”

HS2 so that they can benefit from it, with a report on that consultation to Parliament. Clearly, from that, the references are not to additional stations on HS2 itself but to whether there is a case for any additional stations, reopening of lines or improvements to stations associated with improving connectivity to and from phase 2 of HS2 for the people of the three counties mentioned in the amendment—namely, Cheshire, Shropshire and Staffordshire.

As one can see from the wording of the amendment, it is not about having another consultation on what the route should be or anything like that; it is about the impact of the works and about looking at transport links to and from HS2—that is, all transport links, not just rail links. The amendment specifically refers to “transport provisions” to enable better access for the residents of the three counties.

The amendment would not tie the Government’s hands to any specific course of future action or policy; nor would it delay progress on phase 2a of HS2, as it does not stipulate that there should be no further progress until the consultation has been completed and the report put before Parliament. The issue is that there is a need to make sure that local residents affected feel that their voice is being heard by HS2 and that their views are being listened to. They should not, as I said, feel that consultation is something of a tick-box exercise in which they are told what is going to happen rather than being engaged on a continuous, regular basis. They should feel involved in decisions affecting them and be aware of what is happening and when.

The Government appear satisfied with the consultation that has taken place with local residents on phase 2a of HS2. I have to say that that is not the message that I get. I do not think that the Government should be satisfied with what has taken place to date, albeit it may have been extensive. It comes back to the question of whether people feel that they are being told what is going to happen, as opposed to them having an impact on decisions affecting their lives.

I hope that he will not mind my doing so—if he does, I apologise in advance—but I refer to the words of the noble Lord, Lord Randall of Uxbridge, who said the following in Committee on 9 November. In relation to phase 1, in which the noble Lord was much involved, presumably at that time the Government were saying much the same thing as we have heard today about the extent and thoroughness of the consultation that there had been. The noble Lord, Lord Randall of Uxbridge, said:

“HS2 does not listen to the concerns of NGOs, Members of Parliament or ordinary members of the public. As an example, when I ceased to be the Member of Parliament for Uxbridge, I was succeeded by no less than the current Prime Minister, but he has just as much trouble getting answers out of HS2 as I did.”—[Official Report, 9/11/20; col. GC 376.]


Clearly, if the Prime Minister cannot get answers out of HS2, what chance do the residents of Shropshire, Staffordshire and Cheshire stand without the help of this amendment and the helpful role that it will enable the new Minister for HS2 to play in ensuring that there is proper and continuing engagement by HS2 and progress on ensuring improved transport links in the three counties to and from HS2 phase 2a? I have listened carefully to what has been said, but I wish to test the opinion of the House.

--- Later in debate ---
The committee looked in detail at all these issues and did not make an adverse report. It is important we take account of the points being made today. The Minister has a crucial job to do in reassuring noble Lords this evening that HS2 has made progress in the way it approaches its environmental commitments and responsibilities and will be going forward in tune with the sentiments expressed in these amendments.
Lord Rosser Portrait Lord Rosser (Lab) [V]
- Hansard - -

I think we have reached the stage at which noble Lords would like to hear the Government’s response to an interesting debate. A significant number of noble Lords has spoken on the basis of considerable experience and knowledge in this field. We have agreed an amendment today providing for consultation and a report to Parliament on the impact of HS2 phase 2a on the natural environment, including the impact on ancient woodland, which could enable local residents to be engaged in decisions affecting their environment.

As a general point, we could not support an amendment if the effect of it was—and I do not know whether this will be the case in this instance—to delay progress of HS2 phase 2a. I note the requirement in the amendment that scheduled works must not destroy any ancient woodland, either directly or indirectly, and I am not entirely clear what the impact of that would be on the progress of HS2 phase 2a.

I also note that my noble friend Lady Young has indicated she will not seek to push her amendment in this group to a vote. Like other noble Lords, I will listen with considerable interest to the Government’s response and the extent to which they can offer assurances acceptable to the noble Lord, Lord Blencathra, and my noble friend Lady Young of Old Scone.

Baroness Vere of Norbiton Portrait Baroness Vere of Norbiton (Con)
- Hansard - - - Excerpts

My Lords, I thank all noble Lords for what turned out to be a very interesting debate. I was interested in the observations of the noble Baroness, Lady Randerson, when she noted the complexity of these arguments put before noble Lords today. Many people do not agree on this, yet when one looks at it at face value, it is easy sometimes to reach an automatic conclusion that it must be a bad thing to cut down a tree, but people start talking about where the replacement tree would come from, and it is complex. I would like to reassure your Lordships’ House that HS2 takes its environmental obligations very seriously and follows the advice of the experts, recognising also that that advice may change as more scientific work is done in this area.

Phase 2a has been designed to avoid or reduce adverse significant effects on habitat, protected species and other features of ecological value, where reasonably practicable. However, it is not possible to build a major public transport infrastructure project without creating some adverse significant effects on the environment on or near the proposed route.

One of those effects is on biodiversity, the subject of my noble friend Lord Blencathra’s first amendment. Where adverse significant effects cannot be avoided, mitigation and compensation measures are included to reduce effects on species and habitats. These include the translocation of species, the provision of replacement habitats, and special measures, such as ecological underpasses and green bridges, to facilitate the movement of species across the route. My noble friend Lord Randall mentioned that rail corridors are often good wildlife corridors.

I am proud to say that HS2 was the first major transport project in this country to seek no net loss in biodiversity on a route-wide basis. The phase 2a Bill has been in Parliament since 2017 and, in that time, there has been a step change in our national ambitions to protect and enhance our natural environment. This has not passed HS2 by. During the consideration of the Bill by the Select Committee in this House, HS2 demonstrated greater ambition on the environment. A commitment has been made to enhance the phase 2a scheme’s no net loss objective, by identifying and implementing appropriate opportunities to move towards gains in biodiversity. HS2 Ltd’s green corridor initiative will create a network of habitats along the phase 2a corridor. The Government have also committed £2 million of funding for biodiversity improvements, £5 million for the community and environment and the business and local economy funds, the phase 2a woodland fund and two area-specific funds. These funds total £11 million and they will improve biodiversity.

The legislative commitment sought by my noble friend Lord Blencathra simply goes beyond what can and should be committed to at this stage of the Bill. Casting in iron a commitment to 10% net gain, when land take on the scheme has already been fixed, would be disproportionately expensive, would entail extensive redesigns of the scheme and may lead to significant delays. In all likelihood, further land purchases would be required, going beyond the existing boundaries of the phase 2a scheme and requiring the return of the Bill to the House of Commons.

I know that some noble Lords believe that land purchases may not be required and, as I said earlier, sometimes people disagree on this, but we believe that it would probably be one of the approaches we would have to ensure to reach this legislative goal. However, there are no assurances that we would be able to do this quickly, and the Government would have no alternative other than to get additional compulsory purchase powers to deliver this requirement—if it became a requirement.

I believe that the steps that HS2 has taken, the assurances that have been given and the funds that have been provided to improve biodiversity are the correct approach for the phase 2a scheme. I reiterate that the phase 2a scheme and HS2 as a whole are already committed to no net loss of biodiversity. I hope that, on this basis, my noble friend is able to withdraw his amendment.

The noble Lord’s second amendment is on ancient woodland. We will be returning to this topic further down the track, with some amendments on reporting. I am afraid—and I believe my noble friend knows this—that I simply cannot support his amendment. When designing a complex transport infrastructure scheme, such as HS2, it is necessary to balance competing priorities. The noble Earl, Lord Caithness, made this point. Ancient woodland sites are fragmented and scattered across our countryside. They can be difficult to avoid without incurring substantial adverse effects to other environmental sites or local communities.

The phase 2a scheme has been designed to avoid or reduce impacts on homes, businesses and heritage sites, to reduce losses of our most valuable agricultural land and to prevent impacts to other protected sites. The scheme must also be mindful of wider issues, such as safety and affordability. Noble Lords understand that it is extremely challenging—it may be impossible—to design a scheme of this scale that avoids impacts to ancient woodland entirely, but this does not mean that we do not take this seriously. Where impacts to ancient woodland sites are unavoidable, HS2 Ltd has sought to reduce them by changing the scheme design to reduce the amount of woodland taken.

Although impacts on ancient woodland cannot fully be compensated, its loss can be addressed and somewhat mitigated through a broad range of measures, including planting native broad-leaved woodland to enhance linkages between current ancient woodlands and salvaging ancient woodland soil to be used in new sites.

I return briefly to the question asked by the noble Lord, Lord Snape, who asked me to define ancient woodland. It is quite a tricky beast. Ancient woodland is defined as an area that has been wooded since 1600, but a lot of other things go into that. It could of course be the case that an ancient woodland, as currently defined, consists almost entirely of new trees. They are not necessarily old trees; it has just been woods for a long time.

This returns us to the soil translocation measures. Again, there is some disagreement as to whether it will work, but you know what, my Lords? It is worth giving it a try because, if an ancient woodland can be new trees and it is all about the fungus and the soil—I am feeling like David Bellamy—perhaps it is worth looking at the soil translocation measures. HS2 Ltd has committed to translocating soil but then spending 50 years managing and monitoring in all locations where the translocation of soils has happened. In this way, we will actually know: we will be able to determine the effectiveness of these measures and learn lessons for future infrastructure projects.

The design within the phase 2a Bill is at a relatively early stage of maturity. The area of ancient woodland loss is currently reported in various documents and is set out as the reasonable worst-case assessment. We believe that there may well be improvements as detailed designs come to pass. As I mentioned in other places, more steep cuttings and so on can help to retain ancient woodland. All sorts of things that can be done will be looked at by HS2.

This amendment would result in lengthy delays and costs to the entire phase 2a scheme as, clearly, it would have to go back to square one. There would be a significant redesign. I reassure my noble friend that I will be accepting an amendment later on relating to reporting on ancient woodland, tabled by the noble Baroness, Lady Young of Old Scone. I hope that he will take comfort from that, and I request that he does not press his amendment.

I have an answer to the question asked by my noble friend Lord Framlingham. HS2 trains will run at 360 kilometres an hour. The track is designed to a slightly higher speed of 400 kilometres an hour, but of course that is pretty much within the same ballpark.

I turn, finally, to biosecurity. I will address the amendments in the names of my noble friend Lord Blencathra and the noble Baroness, Lady Young, together. The amendments seek a commitment that all seeds, trees and shrubs planted on the project be sourced within the United Kingdom, due to concerns about biosecurity. That all seems fairly straightforward; various other noble Lords were then able in their contributions to provide some insight as to why it is not as straightforward as that. Biosecurity is an issue that we should, and do, take very seriously. We know the tremendous harm that can be wrought—we have heard about it today—however, it is not the only relevant concern. As some noble Lords have noted, we have to think about climate change and of other challenges that our woodlands may face. This balancing act was given detailed consideration by the House of Lords Select Committee, and I thank it for that.

Assurances have already been given that the nominated undertaker will grow all trees for the phase 2a scheme in the United Kingdom. It is not the case that HS2 Ltd will procure mature plants from abroad—only seeds. At least two-thirds of the required seed stock for phase 2a planting will come from Great Britain, with the remaining third being procured from an appropriate region of provenance within Great Britain and from non-British sources.

DfT officials agreed to consult with the Forestry Commission and Natural England, of which my noble friend Lord Blencathra is deputy chair, because these are the sorts of experts that we need guidance from. We are consulting with them to ensure that this seed stock is from an appropriate region of provenance and to secure stock from within Great Britain as far as is reasonably possible.