Lords ChamberTo ask His Majesty’s Government what progress has been made on removing cladding from high-rise buildings.
My Lords, over half—57%—of all 18 metre-plus buildings identified with unsafe cladding have started or completed remediation. For 18 metre-plus buildings with aluminium composite material—ACM cladding—like that in Grenfell, 96% of identified buildings have started or completed remediation. We have been clear that those responsible must make swift progress or face action. We will update on the remediation acceleration plan this summer.
I thank my noble friend for that Answer. Many blocks still to be done contain the same panels as Grenfell. Can we be assured that the companies identified in the Grenfell report as using dishonest strategies and making false claims, such as Kingspan, Celotex and Arconic, are not involved in any replacement work? The companies are reported to have manipulated test data and manipulated the market. The Minister and other noble Lords will have read the exposure of the crooks running Arconic in a devastating article in the Sunday Times two days ago. Why are these people not behind bars?