Reinforced Autoclaved Aerated Concrete: Hospitals Debate
Full Debate: Read Full DebateLord Bishop of London
Main Page: Lord Bishop of London (Bishops - Bishops)Department Debates - View all Lord Bishop of London's debates with the Department of Health and Social Care
(1 year, 2 months ago)
Lords ChamberTo ask His Majesty’s Government what steps they will take to support NHS trusts with the cost of ensuring hospital sites are safe until reinforced autoclaved aerated concrete can be removed.
The NHS has had a mitigation plan in place since 2021 for hospital buildings with confirmed RAAC. That is backed by significant additional funding of £698 million for trusts to put in place necessary remediation and fail-safe measures. Additionally, in May, we announced that the seven most affected NHS hospitals will be replaced by 2030 through the new hospital programme.
I thank the Minister for his Answer. The NHS Confederation and NHS Providers both point out that they welcome the new hospital programme. However, the issue with RAAC is part of a much bigger maintenance backlog. Some hospitals that are not the most critical will have to wait up to 12 years for the concrete to be removed. Given that timeline and the risk highlighted in recent days, will the Government consider accelerating the new hospital programme?
First, we are doing everything we possibly can to make sure that the programme is accelerated as quickly as possible for good-safety reasons and for clinical reasons as well. In terms of the other hospitals, it is a case of making sure every step of the way that we have structural engineers and we take every safety measure. I managed to visit a lot of these hospitals over the summer and saw first hand the expert work they are doing there.