Grenfell Tower Debate

Full Debate: Read Full Debate

Grenfell Tower

John Healey Excerpts
Thursday 19th October 2017

(6 years, 6 months ago)

Commons Chamber
Read Full debate Read Hansard Text

Urgent Questions are proposed each morning by backbench MPs, and up to two may be selected each day by the Speaker. Chosen Urgent Questions are announced 30 minutes before Parliament sits each day.

Each Urgent Question requires a Government Minister to give a response on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

John Healey Portrait John Healey (Wentworth and Dearne) (Lab)
- Hansard - -

(Urgent Question): To ask the Secretary of State if he will update the House on Government action following the Grenfell Tower fire.

Sajid Javid Portrait The Secretary of State for Communities and Local Government (Sajid Javid)
- Hansard - - - Excerpts

It is now just over four months since the tragedy of Grenfell Tower. Since then, the Government, the local council and the wider public sector have been working hard to ensure that everyone affected by the fire gets the support they need and that all tall residential buildings across the country are safe.

Since I last updated the House on 5 September, the number of households seeking rehousing has risen to 202. As before, this increase has been caused by members of larger households choosing to be rehoused separately. The local council has now secured more than 200 suitable local permanent properties. Negotiations are under way on others, and by Christmas it expects to have more than 300 available. As of this week, 112 households have accepted an offer of either temporary or permanent accommodation. Of these, 58 have moved in, 44 into temporary accommodation and 14 into permanent accommodation.

The Government are determined that everyone who needs support gets it regardless of their immigration status. We have previously established a process to grant foreign nationals who were resident in Grenfell Tower or Grenfell Walk 12 months’ leave to remain in the country with full access to the relevant support and assistance. Last week, the Immigration Minister announced a dedicated route to permanent residency for the survivors. This policy will allow them to apply for free for two further periods of two years’ limited leave. After this time, they will be able to apply for permanent residence.

Meanwhile, our work to ensure the safety of other tall buildings continues. A total of 169 high-rise social housing buildings in England feature some of the aluminium composite material cladding, and our programme of testing has identified 161 that are unlikely to meet current fire safety standards. The particular focus of current efforts is now on supporting remedial work on those 161 buildings. We are also improving our understanding of the situation for the privately owned high-rise residential buildings with ACM cladding, so that all such buildings can be as safe as possible.

We have made clear to councils and housing associations that we expect them to fund measures that they consider essential to making buildings safe. However, if councils have concerns, they should get in touch with us. We will consider the removal of financial restrictions if they stand in the way of essential work. To date, 32 local councils have expressed concern to us in principle. We have liaised more closely with seven of those, and one of them has now submitted supporting evidence for consideration by my Department.

John Healey Portrait John Healey
- Hansard - -

The terrible tragedy of Grenfell Tower was a national disaster. At such times, people look to the Government to lead and to act. The survivors, and the relatives of at least 80 people who lost their lives, deserve no less. I do not doubt the Secretary of State’s good intentions, and I pay tribute to the work of the frontline staff, volunteers and local groups who helped immediately after the fire and are still helping to support the survivors; but, more than four months after the fire, the facts are these.

Only 14 of more than 200 Grenfell families have new homes. Fewer than one in 10 of the country’s 4,000 other high-rise tower blocks has been tested by the Government. The Secretary of State has refused any Government funds for essential fire safety work on other high-rise blocks. Can he confirm that 152 Grenfell households are still in hotels, although the Prime Minister said on 17 July:

“I have fixed a deadline of three weeks for everybody affected to be found a home”?

The Prime Minister told the House on 22 June:

“We can test more than 100 buildings a day”.—[Official Report, 22 June 2017; Vol. 626, c. 169.]

Can the Secretary of State confirm that, in fact, the Government have tested the cladding on fewer than 300 high-rise blocks? On 20 July, he told the House that the Government would

“make sure that they have the support that they need.”—[Official Report, 20 July 2017; Vol. 627, c. 1025.]

Can he confirm that he told the Communities and Local Government Committee last week that there would be no Government funding for councils or housing associations for essential retrofit fire safety work?

Grenfell survivors have a deep mistrust of those in power who failed to respect social housing residents for so long. When Ministers make pledges but fail to act, or fail to ensure that others act, that fuels a wider lack of trust and confidence. The buck stops at the top. Will the Secretary of State now, four months on, secure the extra homes that are needed for all the Grenfell families, provide the Government funds that are needed for urgent remedial work and to retrofit sprinklers, and set a date to come to the House to tell us that every other tower block in the country is safe—not “as safe as possible”, as the Secretary of State said earlier—for the people who live in it?

Many of the Government’s decisions, reviews and inquiries are good, but they will not be good enough until the Government get a grip, and get these fundamental problems sorted out.

Sajid Javid Portrait Sajid Javid
- Hansard - - - Excerpts

I know that the right hon. Gentleman cares as deeply about helping the survivors of this terrible tragedy as I do, and as the entire Government do, and it is a real shame that he should try to treat it as some kind of political points-scoring opportunity. He knows exactly what the situation is, not least because I updated the Select Committee—whose members included his colleagues—just last week. The Committee had an opportunity to go into many of the issues in detail, as a Select Committee should, and I am sure that the right hon. Gentleman followed all that. This is not what the victims of the tragedy want to see, and it not what the country wants to see. They want to see all of us working together to do whatever we can.

The right hon. Gentleman asked me about housing. I have talked about that before, but I am happy to say again that the victims of what was easily one of the most terrible tragedies ever to have taken place in our country are people, not statistics. We must work with them and listen to what their needs are. For example, there were 151 households at the start, with Grenfell Tower and Grenfell Walk—the two buildings—taken together, but we are now working with 202 households. That has happened because some of the survivors have asked to split where there are larger families or for other reasons, and we have listened to that. We have listened to every single case, and not one request has been turned down. That, of course, means we have to find even more permanent and temporary accommodation, but that is not our consideration; our consideration is the needs of the victims themselves.

It is right that every family should be properly assessed for their housing need, and should be listened to. Every single family has been offered an assessment by professional housing officers. Some of them have met a number of times, because if they change their mind we need to listen to them. Literally only a handful have not yet had that meeting, but that is at their request, because they are not ready; they will typically be a bereaved family who are not ready to engage. They would rather not go through that process now, and we have listened to them, too.

After the assessments, we have tried to determine—obviously the council was leading the work—whether the survivors wanted to be back in an apartment block again, or if they want a house, and whether there are any other needs. Some families say they do not want to live in the borough, but would prefer to move closer to family elsewhere. All of that is being listened to; we are trying to action all of that and listen to it.

There can be a time lag when families have identified a property—as I have said, 112 families have accepted offers of temporary or permanent accommodation. That lag occurs between acceptances and moving in, because every family has been offered a moving-in package so they can choose the décor, the furniture and any other things that will make their life comfortable. That has been listened to, and of course that will take time.

That is how we are treating these people: as real people and survivors, not as statistics. I know the right hon. Gentleman is not saying that they are statistics, but sometimes it does come across like that. I urge him to work with us, and to listen to what work is actually going on.

The right hon. Gentleman also asked me about the building test. I have given the House an update on the numbers, and a fuller update was given last week at the Select Committee. He asked particularly about the speed of the tests. The Prime Minister rightly said previously that the testing facilities can test up to 100 samples a day. They were specifically testing the samples of ACM—aluminium composite material—cladding that were sent in, and they were done at the speed that they were sent in; the testing facilities can only operate at the speed at which the samples are sent in.

Those tests have subsequently been superseded by the more comprehensive systems tests, which test the whole ACM cladding system. As the right hon. Gentleman knows, that was tested during the summer and it gave a fuller result. I have just shared the numbers of social buildings and private buildings tested so far, and following on from those results, both the interim and remedial action plans that have been put in place.

Finally, the right hon. Gentleman asked about council funding. He rightly said that I have stated before that I will make sure that all councils have the support they need. That is exactly what I and this Government are doing. Councils are rightly expected to carry out all essential works, and they will determine, as the legal owners of the properties, what is genuinely essential work; and if they cannot afford it, that should not be a reason not to do the work. Whether they are interim measures or the final remedial measures, the work must happen, and if the councils need support through financial flexibilities, we will provide that. Again, I gave a fuller account to the Select Committee, so perhaps the right hon. Gentleman will take another look at that.