Tower Blocks: Dangerous Cladding

John Healey Excerpts
Tuesday 22nd January 2019

(5 years, 9 months ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts

Urgent Questions are proposed each morning by backbench MPs, and up to two may be selected each day by the Speaker. Chosen Urgent Questions are announced 30 minutes before Parliament sits each day.

Each Urgent Question requires a Government Minister to give a response on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

John Healey Portrait John Healey (Wentworth and Dearne) (Lab)
- Hansard - -

(Urgent Question): To ask the Secretary of State for Housing, Communities and Local Government if he will update the House on the action taken and planned by the Government with respect to high-rise residential blocks with dangerous cladding.

Kit Malthouse Portrait The Minister for Housing (Kit Malthouse)
- Hansard - - - Excerpts

There is nothing more important than ensuring that people are safe in their homes, and we remain determined to ensure that no community suffers again as the community did so tragically and appallingly at Grenfell Tower. Within days of that tragedy, a comprehensive building safety programme was put in place to ensure that residents of high-rise blocks of flats are safe and feel safe now and in the future. Our Department has worked with fire and rescue services, local authorities and landlords to identify high-rise buildings with unsafe cladding and to ensure that interim safety measures are in place until issues are permanently remediated. Measures have included waking watch, which has been put in place in all high-rise buildings with ACM cladding, with the oversight of the National Fire Chiefs Council. As of 31 December last year, interim measures have been in place on all 176 high-rise private residential buildings with unsafe ACM cladding.

Permanent remediation must rightly now be our key focus. On 18 December, we published our plan to implement the recommendations of Dame Judith Hackitt’s independent review of building regulations and fire safety, which will create a stronger regulatory framework and fix the issues for the long term. We have repeatedly called on private building owners not to pass costs on to leaseholders who find themselves in this position through no fault of their own. We have also warned private building owners that, unless they remove and replace unsafe ACM cladding from their high-rise residential buildings now, local authorities have the power to complete the works and recover the costs from the owner. As a result of our interventions, we have secured commitments from owners of 268 privately owned buildings, 212 of whom have either started works, completed them or have commitments in place to remediate. There remain 42 private residential buildings for which the owner’s plans are unclear, so we are maintaining pressure and rule out no solutions.

This is obviously a matter of great importance to many colleagues and, indeed, to many constituents, and that is reflected in the huge amount of activity that is taking place both within the Department, externally within the industry and, critically, in this House. There is an Adjournment debate tomorrow, and I will appear at oral questions and before the Housing, Communities and Local Government Committee on Monday.

John Healey Portrait John Healey
- Hansard - -

It should be a cause for national shame that, over 19 months after the Grenfell Tower fire, I am having to drag Ministers to the House because there are still buildings in this country cloaked in Grenfell-style cladding and residents who do not know whether their homes are safe, as the Daily Mirror has revealed today. It is shocking that the Government’s own figures show that there were 437 high-rise blocks with the same Grenfell-style cladding and that 370 are yet to have it removed and replaced. It is shocking that the Minister knows every one of those blocks but will not name the landlords or tell the residents. Whatever he says he is doing, it is not working. For over 19 months, any progress made has simply been too slow, too weak and always following pressure from this House and from Labour. If the Government cannot fix problems this serious and urgent, what on earth are they in office for?

Here is a six-point plan to sort out the problems, and this is what we have been arguing for months. First, widen the Government testing programme to cover all suspect cladding, not just ACM cladding. Secondly, set a deadline for all blocks to be made safe. Thirdly, make clear the legal duty for block owners to get this work done, and to pay for it without passing on the bill to hard-pressed leaseholders. Fourthly, set up a loan fund for private blocks. Fifthly, name the landlords and tell the residents so that the public know the safety status of all high-rise blocks. Finally, toughen the sanctions, up to and including taking over blocks to get this vital fire safety work done.

For more than nine months, as the Minister has repeated today, the Secretary of State has said that he is not ruling anything out. It is time to rule things in, and it is time to reverse the refusal to act on all these fronts.

In the days after the Grenfell tragedy, the Prime Minister promised the nation:

“My Government will do whatever it takes to…keep our people safe.”

When will the Minister finally be able to come to this House to tell us and the public that the Government have honoured that pledge?

Kit Malthouse Portrait Kit Malthouse
- Hansard - - - Excerpts

I am sorry that the right hon. Gentleman has sought to make this such an antagonistic exchange in what is a difficult and complicated situation that requires significant amounts of engineering and construction work, which will necessarily take time. He will know that the response from both the Department and the Government in the aftermath of the Grenfell tragedy was immediate and wide-ranging. The commissioning of Dame Judith Hackitt to conduct her inquiry was an important step forward in tackling this issue.

Since then, significant resource and effort have been injected into the need to remove this cladding, but the vital first step was to make sure that people living in high-rise blocks with ACM cladding were safe immediately, and those steps were put in place immediately. We now know, and can tell everyone in tower blocks with this cladding, that they are safe tonight. The Government’s primary focus was to make sure there were enough interim measures in place and that local fire and rescue services were satisfied that the buildings were immediately safe, while at the same time providing the resources, assistance and support—and, yes, cajoling some in the private sector to do their duty and replace this cladding.

That is what we continue to do, and we are making significant progress. However, the right hon. Gentleman is correct that we will get to a point where, for a small number—we are now down to a small number—of owners or contractors who put this cladding on buildings, we will need to consider more assertive measures, and those measures are under active consideration at the moment. All the while, in all of this—he may present himself as an expert, but I am certainly not an expert—we are guided by expert opinion, which includes Dame Judith Hackitt’s review and the independent expert advisory panel that was constituted in the immediate aftermath of Grenfell. We follow their advice in making sure that we can guarantee people’s safety tonight.