UK Decarbonisation and Carbon Capture and Storage Debate
Full Debate: Read Full DebateJim Shannon
Main Page: Jim Shannon (Democratic Unionist Party - Strangford)Department Debates - View all Jim Shannon's debates with the Department for Business, Energy and Industrial Strategy
(7 years, 10 months ago)
Westminster HallWestminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.
Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.
This information is provided by Parallel Parliament and does not comprise part of the offical record
It is a pleasure to speak in the debate. I congratulate the hon. Member for Coatbridge, Chryston and Bellshill (Philip Boswell) on raising the issue. I may have a slightly different opinion from my dear friend and colleague, my hon. Friend the Member for East Antrim (Sammy Wilson).
My hon. Friend may regret it, but it will not diminish our friendship in any way whatever. It is good to have a broad church of opinion within our party.
I will pose some questions because it is important to do so. Environmental issues are of great importance, so it is essential that our strategy is effective. I say to the Minister that I am not sure that we have managed to achieve all we could or should thus far. That is the question many have posed, including the hon. Member for Coatbridge, Chryston and Bellshill during his introduction.
It is opportune that we are having the debate on the back of the industrial strategy Green Paper announced by the Department for Business, Energy and Industrial Strategy yesterday. Many believe that the Department has not achieved value for money for its £100 million spend on the second competition for Government financial support for carbon capture and storage. Other hon. Members have said that there must be an investment to get a return, and that the return will justify the investment.
It is my understanding that CCS is a process to avoid the release of carbon dioxide into the atmosphere, and that it has the potential to help to meet the UK’s target for a reduction of CO2 emissions in both the power and industrial sectors, which is commendable. We have pledged to cut 1991-level emissions by 57% by 2030. While that is a great goal, how will we achieve it? Hon. Members have outlined potential job creation and the opportunities that will come if it is done in the right way. To achieve the goal is most certainly a challenge, given the untried nature of the technology.
I point out to the hon. Gentleman that the technology is truly tried and tested. The curious scheme in Northern Ireland aside, I would urge both hon. Members from Northern Ireland, who are my friends, to read the Oxburgh report and contrast the less than £85 per KWh that is achievable under this system with the Hinkley Point strike price of £92.50. Furthermore, the networks already exist. That is the attraction of having an existing infrastructure.
I will respond to the hon. Gentleman’s intervention during my comments. The future costs for the duration of the CCS project are unknown, and perhaps the figures do not add up on all of the lines.
Two projects that were shortlisted for the CCS process both failed to meet the proposal goals. The work done centrally by the Department in sustaining negotiations for the second competition for the project with its preferred bidders must be noted—a process is in place. The hon. Member for Coatbridge, Chryston and Bellshill has clearly outlined some of the evidence, and I will pose some questions on that. I can clearly say that I support the principle of what we are trying to achieve, but I wonder whether it can be achieved by that process. There are lessons to be learned, and hopefully valuable commercial knowledge and technical understanding of how to deploy the competition projects will have been gained, as he said. If we have that information, let us see how we can use it to further the project.
There are currently no examples of large-scale CCS projects in the UK, and only 16 operational projects worldwide. BEIS should maximize its expertise for future CCS strategies and put into practice the lessons it has learned—in other words, the evidence should be used for the betterment of delivering such projects. If and when CCS projects are self-sustaining and economically viable, we will see clean electricity from renewable sources, which we wish to see and are committed to trying to achieve. However, the sticking point is in the phrase “if and when”, meaning we could achieve those things “if and when” the Government and BEIS find a happy medium and the in-between. Hon. Members are often tasked with finding a balanced in-between or the correct way forward.
The substantial future benefit of the CCS process is to avoid the release of CO2, as several hon. Members have indicated. However, it is clear that there are serious problems and critical issues with such projects that we cannot ignore. As I have discussed, there are no large-scale examples of long-term storage projects in the UK, despite a series of UK Government and EU initiatives aimed at incentivising their development. It has been argued that CCS technology is too expensive to be commercially viable for private developers without Government support in the shape of a strike price. Government involvement is critical in taking this forward.
I am aware of the work carried out by the parliamentary advisory group on carbon capture and storage, which found that good design could make CCS affordable. However, I have reservations about the cost of CCS competitions to the taxpayer.
Does my hon. Friend agree that a high strike price will be paid for out of the pockets of every one of his constituents who consumes electricity? That is the big problem with schemes of this nature, for which there is a move away from cheap fossil fuels to dear renewable sources.
The Minister will take note of my hon. Friend’s comments and am sure will respond later.
We have seen not one but two failed voyages into the unknown of CCS projects, for which we have spent £168 million with no further resolutions and only lessons learned. We do not want this to be like the Mary Celeste— setting sail, getting nowhere and disappearing. It is my understanding that the cancelling of the second competition will impact on investors’ confidence, who in future may demand better conditions before engaging with the Government again, which will prove detrimental to the cost-effectiveness of future projects.
We do not want this to harm the future and where we are going. I feel strongly that both the Government and BEIS need success guaranteed in both financial and environmental areas before embarking on such voyages in the future, and as such I believe that every consideration must be given to how this particular project will help us to achieve our goals, and indeed whether it can do so.