Mark Hendrick Portrait Sir Mark Hendrick
- Hansard - - - Excerpts

I concur with the hon. Gentleman. Whether it is with Northern Ireland authorities or with our own Government, there is no reason why there should not be good co-operation and good insulation schemes. That is what I would have expected with these 387 houses in my constituency.

In the meantime, I requested a meeting with the Secretary of State on the matter, as a matter of urgency. Except for a very brief encounter in the House of Commons Tea Room, when the Secretary of State said that she was looking into the matter as she passed me by, she seemed uninterested in the case and reluctant to discuss the matter. She did, however, refer me to an official, who then assured me that Preston City Council was working with the NEA fuel poverty charity. However, what the Department did not know was that this was the case only because of my direct intervention and contact with the chief executive of Preston City Council at the time, because, as I said earlier, the council officer had sat on the letter from the NEA.

By July 2016, the chief executive was indicating that she needed extra funding in order to carry out surveys to get a “detailed picture of issues”, so clearly the £2.5 million was not enough to deal with the problems, and in fact was only to be targeted at those homes which had complained about the work—62 of the 387 homes. That did not take account of the fact that many of the other homes had problems, but because the residents thought that people in other properties were complaining on their behalf as well, they did not come forward and make their direct complaints. Therefore, the fact that work was to be carried out on the 62 properties only, neglected all the work that needed to be carried out on the other affected properties, whose residents, for a variety of reasons, had not come forward and made their own complaints. That was, in my view, totally unjust and short-sighted.

On 24 November 2016, I emailed the Secretary of State at the Department for Business, Innovation and Skills—the right hon. Member for Tunbridge Wells (Greg Clark)—to ask what assurances and safeguards were in place to ensure that the properties would be safe, dry and warm, and that any installations would be done in a professional manner. In December 2016, BIS responded, asking for more detail. In January 2017, my office contacted BIS to ask what detail it required. My office staff were told that the policy team would get in touch. We waited and waited, and the policy team did not get in touch. However, work was already under way on the 62 properties, which were designated as phase 1. Those properties that were left were designated as phase 2 and the residents were told that they would be surveyed. However, there was no indication from any organisation as to how or if funding would be made available for phase 2.

In the meantime, I received an email from Councillor Martyn Rawlinson of Preston City Council, telling me that the management of the repairs on the 62 houses was as bad as the original work that was carried out. Some of the houses had been left half done for several months. E.ON originally said that all repairs necessary would be done, but E.ON was then saying that homeowners should get their own insurers to get the work completed, which was outrageous—an absolute disgrace—and by then the residents had been putting up with this nonsense for four years, with many of them having work done twice to their property, and still not to their satisfaction.

By 29 November 2017, I was ready to let E.ON know about my concerns over the progression of the remedial works, and asked it for a timescale setting out when all the works would be carried out and completed, and for a point of contact to be established for the residents. My office chased E.ON for a response for over a month, and a month later—January 2018—we finally received correspondence. E.ON confirmed that it was trying to divert attention from its responsibilities in the matter towards Preston City Council, which had no direct responsibility, and still has no direct responsibility, for the work to be carried out. It is E.ON that surveyed the houses in August 2017 for phase 2 of the repairs. I am told that those so-called “surveys” were in fact not proper surveys, but door-knocking exercises to ask people whether they were having problems, or had had problems previously; nothing at all was done of a technical nature, and certainly nothing that could generate a work order to remedy what problems they were having. In addition there is not, and has not been, any indication from the Government or E.ON of how the rest of the work for the 300-plus houses will be financed. We are seeing good will, but nothing in the way of resources to complete the work.

On 11 February I received an email from Councillor Martyn Rawlinson, with photographs of some horrific scenes within houses due to the damp issues. It is inconceivable that people should be left to live in such conditions, with no one apparently willing to rectify the problems as soon as possible.

On 8 March this year, I wrote to the Under-Secretary of State for Housing, Communities and Local Government, the hon. Member for South Derbyshire (Mrs Wheeler), describing my disappointment with the then Secretary of State and the Department, and appealing for help. On 27 March I received a response from the Under-Secretary telling me that the responsibility had moved from her Department to the Department for Business, Energy and Industrial Strategy.

I tabled a series of parliamentary questions to BEIS about the use of cladding on properties. That culminated in a letter from BEIS indicating that remedial work on 62 of the properties should be completed shortly, and that E-ON was in discussions with National Energy Action to help other households. In the meantime I received a variety of complaints from the residents, one claiming to have spent £1,500 after a ceiling caved in after wet weather. In a separate case, an elderly homeowner had to leave her property and move in with her son because the damp was affecting her health.

Since then, the Minister for Energy and Clean Growth has responded to my parliamentary question, PQ177184, indicating that the retrofit on 62 of the properties was completed in the summer of this year and that work has been carried out to estimate the extent of the work that is necessary to sort out the work required to the other properties. As I said earlier, that resulted in questions being asked on the doorstep. In addition, talks have been taking place between Ofgem, BEIS and the energy suppliers in an attempt to secure funding for the remaining houses.

This saga has been running for six years, from 2012 to where we are now, in October 2018. It has been an absolute tragedy for those living in those 387 houses, who have been trying to put up with substandard housing and great inconvenience. The result has been unsafe properties with associated health risks. In the meantime, I am reliably informed that in many cases the cladding has been removed, but properties have been left with holes in the walls. The landlord has said that they will be finishing off the work, but will only repair the holes and paint the brickwork. They are not prepared to install any new insulation. One of the complainants wonders where the money has gone for the work that should have been done to her property. The landlord has told her that she should speak to E.ON or Preston City Council.

Let me tell the Minister that I recall spending three years in the Department for Environment, Food and Rural Affairs as Parliamentary Private Secretary to the then Environment Secretary, the right hon. Member for Derby South (Margaret Beckett). During that time, when my party was in government, we dealt with fuel poverty issues through the Warm Front scheme, which was applied to about 10,000 homes in my constituency, particularly in the area of Deepdale. The scheme focused on energy efficiency by installing new central heating boilers and providing loft insulation and double glazing for terraced housing that was not too different from the housing that we see in Fishwick ward. It was extremely effective, and popular with residents.

May I ask the Minister why the more recent schemes that are using cladding of the type mentioned in Fishwick are being employed when the detriment to both property and residents is known? Why has it taken six years to get to where we are now for the residents of Fishwick? Are the Government willing to help to direct the residents to a satisfactory and available source of finance to rescue what is, in fact, a Government scheme?

Jim Cunningham Portrait Mr Jim Cunningham (Coventry South) (Lab)
- Hansard - -

I was in that Department during the period of the last Labour Government. One of the things that is absent here is enforcement, but, more important, if there is a Government scheme and the Government are subsidising it, there should be a list of approved quality builders, perhaps with certifications. I have also found, in isolated cases with which I have dealt, that it is mainly elderly people who cannot get redress. They are told to go to the council, but the trading standards offices are undermanned, and they have limited powers under the law. Should we not do something about some of those matters?

Mark Hendrick Portrait Sir Mark Hendrick
- Hansard - - - Excerpts

I agree with my hon. Friend. When I was in DEFRA there were recommended contractors. Those contractors could ensure a certain level of quality and even though we got the odd complaint from people under the Warm Front scheme, we did not get anything like the number of complaints or the state of the work that we get now. Unfortunately, the company in question has gone into liquidation, but the Government should still look at how they can help.

Why have the residents of Fishwick had to endure this substandard work and why has it not been rectified properly despite the fact that the contracting company, Ecogen, went into liquidation soon after that work was completed? Why do the Government not concentrate on energy-efficient boilers, loft insulation and double glazing? The Minister might well tell me that in other areas they are concentrating on those solutions, but then why is there this move towards cladding—an ugly and harmful solution?

I am thankful for securing this debate and look forward to hearing the answers to my questions from the Minister.