Commons ChamberI agree entirely with the hon. Gentleman’s intervention. That is the thrust of our new clause, which I trust he will support. It stipulates that the redevelopment board will advise the Secretary of State on the delivery of an “integrated and comprehensive design” for the enlarged Euston station, and it is for the integrated programme board to make sure that the designs and construction plans for Euston fit with proposals for other Euston schemes.
Access is a real issue, so while the construction is under way, which it will be for many years, we want to ensure that pedestrians and cyclists have continuous access through the site, east to west and north to south, insofar as it is “reasonably practicable” to do so. A design panel will work to ensure that the relevant partners can agree an appropriate design. Whoever is appointed for these purposes by HS2 will be obliged to work with that panel to ensure full buy-in to the design. Indeed, there will be an obligation on the nominated undertaker to take proper notice of the recommendations made by the design panel, and if for some reason the nominated undertaker does not follow those recommendations, our new clause states that it will be required to explain why that is so. The new clause makes sure that the community is properly engaged throughout the construction works at Euston so that its concerns will be recognised and its voice heard.
The provision is even more important, given today’s publication of the Parliamentary and Health Service Ombudsman’s report on a complaint about HS2. It effectively concludes that there are fundamental problems with the way HS2 Ltd communicates with the residents affected by their plans and the way it handles complaints.
The report dealt with specific complaints, but it is worrying that the Chairman of the Public Administration and Constitutional Affairs Committee has said:
“There is still a culture of defensive communication and misinformation within this public body and that is not acceptable. Unless those responsible for delivering HS2 understand that first and foremost they serve the public, they will continue to be criticised for having complete disregard for the people, some of them vulnerable, who are impacted by this large-scale infrastructure project.”
If my hon. Friend would not mind, I am conscious of my time drifting away.
The Chairman continued:
“We expect HS2 Ltd to prioritise its response to Ian Bynoe’s forthcoming recommendations on communication and engagement and on complaint handling. This is a matter of primary importance for HS2 Ltd, and must be treated as such.”
I trust that the Minister will take on board the criticisms of the Committee and make sure that any necessary cultural and other changes are made so that there is no such repetition. I urge him further to consider, even at this late stage, accepting our representations in the context of this new clause.
The new clause also provides that when the Secretary of State sets out the Government’s periodic railway investment plans, in what we have come to term “control periods”, he or she should set out the costs of and funding for the anticipated works in the planning period before the works start and during the control period in which the works will fall.
Yes, previous infrastructure projects have had similar assurances woven into them and they have been observed, but this is such a huge infrastructural undertaking, the likes of which has never been done before in such a manner, on such a scale or over such a lengthy period of time. We believe that the people of Camden need to have more than just the assurances that have been given. On this occasion, we believe that we have to take the extra step of working those assurances directly into the Bill.
The Minister will not need me to remind him that throughout the Public Bill Committee Labour tabled a number of amendments and new clauses that pressed the Government to justify the inclusion of wide-ranging blanket powers granted to the Secretary of State for the purposes of the construction and operation of HS2. Each time the Minister responded by resisting our attempt to curtail the scope of the Secretary of State’s powers on the basis that the Government was taking a “belt and braces” approach so as to be absolutely sure. I am now therefore asking for the loan of his belt and braces— not to protect my dignity, but to protect the people of Camden.
I do not intend to impugn the sincerity of HS2 Ltd or of the Minister, and he knows that. In the light of the comments from the Public Administration and Constitutional Affairs Committee and the special set of circumstances that apply, we firmly believe that these provisions need to be enshrined in statute. I shall test the will of the House on new clause 22 by putting it to the vote.