I congratulate my hon. Friend the Member for Boston and Skegness (Matt Warman) on bringing this important debate to the House. I am speaking on behalf of my North West Norfolk constituents who would be adversely affected by the Grimsby to Walpole link, and by the eastern green link proposals for two offshore projects as part of the great grid upgrade. “Great for whom?” is the question that many of my constituents have.
Under the proposals, 90 miles of a new, high-voltage electricity transmission line would be constructed along with new substations, including at Walpole in my constituency, near to the existing substation. It would consist of a 50-metre-high pylon every 300 metres or so. That is half the height of the Elizabeth Tower and getting on for the height of Ely cathedral. In addition, National Grid is consulting on two new offshore electricity infrastructure projects, eastern green links 3 and 4, which are primarily subsea links bringing electricity from Scotland to England.
As we increase generation from renewables, there needs to be investment to connect those sources to homes and businesses. The issue, though, is how we do that in a way that minimises the impact on local people, our countryside and our communities. Three options for the Grimsby to Walpole scheme were considered—two onshore and one subsea. The subsea option looked at a Norfolk or a Lincolnshire landfall. There are undoubtedly challenges about a Norfolk landfall, given the number of designated sites in my area, with fewer issues for a Lincolnshire solution. They need to be assessed carefully. However, as in other areas, the default for National Grid has been to rule out such options without proper consideration, despite the fact that pursuing them would lessen the visual impact, the environmental effect and disruption to communities. That needs to be revisited as the process continues.
Having discounted the subsea option, National Grid is proposing nearly 100 miles of new pylons. Many constituents have raised strong concerns and objections to the preferred route, including the damaging visual impact that the pylons would have on our beautiful landscapes. Much of the land on the proposed route is grade 1 arable land. When we are looking to improve food security, taking that out of use goes against the Government’s intention.
Pylons and substations cause noise and disturbance for local communities. The proposed area could also affect many protected sites, including the Wash, one of the most important sites in Europe. Indeed, the Government have applied for UNESCO world heritage status for the east Atlantic flyway for migratory birds, including through Norfolk and Lincolnshire, which would be threatened by current plans.
When I met local councillors, parish councillors and parishioners, they were concerned about the location and the impact of a new large substation. They have also asked what assessment has been made of upgrading the existing pylon infrastructure. Of course, that would need reinforcement of the pylons that are there, but that would be less intrusive and more cost-effective. Considering improvements to existing lines is a requirement of the national planning policy statement, so that also needs to be addressed ahead of the next consultation.
In contrast to the Grimsby-Walpole plan, the eastern green links are for subsea cables, with landing points on the Lincolnshire coastline. They would then run underground for 80 miles to the proposed converter stations and a new transmission station in Walpole in west Norfolk—yes, underground. If the underground cable is a preferred option for that project, why not for the transmission line scheme? What scope is there for the proposed Grimsby-Walpole link to be integrated into that? Again, that needs to be looked at further.
On consultation, eight weeks is wholly inadequate, given the amount of documentation published and the length of time that National Grid has been working on this. To be polite, there has been a lack of a co-ordinated approach, but the two schemes could work better together, so we need a much more transparent process.
There are major concerns across west Norfolk about the proposals. People are rightly opposed to the damaging impact on our communities, countryside and farmland. The plans cannot be the final answer; they must be changed.