Storm Arwen: Power Outages Debate
Full Debate: Read Full DebateHilary Benn
Main Page: Hilary Benn (Labour - Leeds Central)Department Debates - View all Hilary Benn's debates with the Department for Business, Energy and Industrial Strategy
(2 years, 4 months ago)
Commons ChamberI am sorry, but I do not accept that. First, it is not right to criticise the Secretary of State for going up to the north-east on a Sunday to see members of the armed forces, and to thank the engineers and the community responders. As you will remember better than anyone, Mr Speaker, he came here last Wednesday to make a statement on the situation. There has not been a delayed response from the Secretary of State.
The hon. Lady also asked about generators. In fact, 755 were provided at the peak of the relief effort, and 500 are still being provided. I thought that she might join me in thanking some of those who are working so hard on the ground—not just the engineers, but those in the call centres. They are making tremendous efforts to ensure that those who have been disconnected are reconnected and that people have the help that they need in the short term, as well as ensuring that we learn the lessons of this unique storm.
Given that we are likely to see more severe storms, and even with the lessons learned from previous storms and the mutual aid system that the Minister has referred to, is not the review going to have to look at increasing capacity—I am talking about materials, machinery, generators, spares and people—in order to be able to deal with these events more effectively so that people do not have to wait so long to have their lights and heating put back on? Who does the Minister think has the principal responsibility for ensuring that that capacity is there when storms strike?
The right hon. Gentleman raises some good points, but I do not want us to prejudge the review. He has mentioned quite a few things that he thinks we were short of. I think he is saying that we were short of generators, for example. I have already said that 750 generators were deployed. Of course we need to look at whether we have the right number of generators in terms of the capacity, but I would not want to prejudge that important review and the process behind it. Let us wait and let the review run its course. We have learned some really important lessons from previous reviews, for example on setting up a dedicated phone line, the mutual support and the network of engineers from across the country. Let us not prejudge that review.