It is a pleasure to serve under your chairmanship, Mr Chope. It is always a pleasure to respond to debates called by my hon. Friend the Member for Hertford and Stortford (Mr Prisk) and attended assiduously by our right hon. Friend the Member for Saffron Walden (Sir Alan Haselhurst), because the arguments are always eloquently made and extremely well informed. I know that both of them have been dedicated for many years to securing the best possible service for their commuting constituents, as am I.
My hon. Friend raised many interesting points, and in the time available I will focus on three of them. On the important issue of compensation, ultimately we all want the same thing: a timely and reliable train service. If we had that, there would be no need for compensation because passengers would not be delayed. We are working hard as a Department and an industry to deliver solutions to the problems he mentioned, particularly failures by Network Rail. He is absolutely right to say that Abellio Greater Anglia has worked extremely hard to solve many of its own internal issues, and of course there are still problems, such as trains breaking down, partly as a result of the ageing fleet, but ultimately everything hinges on the relationship between Network Rail and the operator. We will shortly publish the results of the Nicola Shaw review, which considers some of the fundamental questions about how to join up Network Rail’s activities and those of operators in ways that focus entirely on delivering for both passengers and freight customers. I cannot say more about it, but I look forward to seeing the proposals.
It is important when things do not work that passengers have quick, easy and in many cases automatic access to appropriate compensation. We have some of the most generous compensation schemes in Europe for rail passengers. Through the “delay repay” scheme, we already offer relatively generous levels of compensation: passengers can claim back 50% of their ticket price if they are delayed for 30 minutes or more. However, as my hon. Friend pointed out, given that the average journey time from Hertford East to Liverpool Street is only 49 minutes, that is not necessarily particularly helpful for his constituents. We want the system to be even better, which is why we committed in our manifesto—the Chancellor has since confirmed that commitment—to reduce the threshold for compensation from 30 minutes to 15 minutes. I intend to announce the details of the change in the next few months. It is always a commercial negotiation when we deal with the rail industry, and we want to ensure that we secure the right deal for taxpayers.
Given the timing of the franchise competition, to which my hon. Friend referred, that will become an in-franchise change for both Abellio Greater Anglia and Govia Thameslink Railway, which already operates as the franchise holder. It is entirely consistent with what we have done in many cases. We intend to roll out the system right across England, so it will become a relevant negotiation to have with franchise operators.
Of course, we are not standing still on compensation. We made some changes last year to the national conditions of carriage so that passengers can claim compensation in cash instead of rail vouchers. As my hon. Friend rightly pointed out, the industry must do better. I pay tribute to Which?—a fine consumer-focused campaigning organisation. We are considering the responses to the Which? super-complaint and working with Transport Focus to ensure that operators publicise the compensation that they offer, because the data suggest that only 12% of passengers who are entitled to compensation bother to claim it. That is unacceptable. We want to ensure that the offer is widely publicised and available.
My hon. Friend might be interested to know that last week c2c, which runs the franchises into London from the east, introduced a pence per minute automatic delay scheme. If a train is delayed for more than two minutes, passengers will start to receive compensation automatically if they are registered for a c2c smartcard ticket. He will be pleased to know that Abellio Greater Anglia, which is also part of the south-east flexible ticketing programme funded by the Government, will introduce its own smartcard next month. It is expected to launch in Cambridge and then roll out across the network, giving the operator the opportunity to introduce a similar system to c2c’s, so that signed-up smartcard users can receive compensation automatically, without having to do anything about it. I am sure that we all welcome that.
The Minister’s comments are encouraging. To return to the advent of the new franchise, she described the 15-minute rule as an in-franchise agreement. Does that mean it will be discussed at the time the franchise is let, or will it be negotiated across that period and perhaps introduced later?
The proposal is to introduce it across all UK franchises at the same time. We will not wait for franchise renewal to come up; it will be introduced. In some cases, where it cannot be introduced as a franchise commitment, it will be funded by Government. We have funding for that, and we are absolutely determined to do it.
The second issue my hon. Friend spoke about is rolling stock. As he pointed out, many of his constituents travel on trains that date from the 1970s, which was a fine decade for fashion but not necessarily a fine one for train quality. Although those trains are still running reliably, which is a tribute to the way they were made and the way they are maintained, they are the oldest electric rolling stock in the country. As both he and our right hon. Friend the Member for Saffron Walden know, the bidders for the new East Anglia franchise have been challenged to specify a massive improvement in the quality of the trains they will run.
In fact, the way we let franchising now is based on both the financial aspects of the bid and the quality that will be delivered. That quality is referred to as the Q score and the weighting for rolling stock quality has never been higher than in this franchise. It is the most significant weighting that has ever been given to rolling stock and we absolutely expect that bidders will include new rolling stock in their bids. That is because, as has been pointed out, the journey time improvements in particular cannot be achieved with the speeds that the existing rolling stock can achieve.
As always, there is a balance to be struck between taxpayers and fare payers, so rather than specify exactly what bidders should do, we have given them the freedom to deliver what they think will give the best performance for passengers. Having visited the CrossCountry franchise only last week and seen the refurbished class 170 trains, I can assure my right hon. and hon. Friends that customers often cannot tell whether a train is new or refurbished to 21st century standards, because in either case it will have the appropriate toilet facilities, and brand new seating and lighting. To all intents and purposes, it looks and feels like a brand new train. That quality is what we are looking for bidders to propose, and my expectation is that the bids will include a high concentration of new rolling stock.
We will also for the first time hold the successful bidder to account contractually for the improvements that they propose for the franchise. We are introducing a contractual customer experience regime, with tough penalties if the operator fails to deliver. At the moment, we have lots of feedback and information, but this will be the first time that we have contractualised those customer experience obligations, with financial penalties if the successful bidder fails to deliver.
As my hon. Friend mentioned, we will see improvements on Great Northern lines, and his constituents will see those improvements even sooner. The deal that was announced last week to replace the wonderful 1976 trains with 25 new six-car trains will bring benefits in 2018. It is worth mentioning that the deal, which is worth just over £200 million, will create jobs right across the UK supply chain from Poole to Hebburn and provide much-needed capacity. My hon. Friend pointed out the capacity problems on the routes, so we can all welcome the improvement.
My hon. Friend is right to raise the question of what can be done about track capacity. Indeed, he and our right hon. Friend are not lone voices. Our hon. Friend the Member for Broxbourne (Mr Walker) campaigns vigorously on this issue, and support is growing. I am well aware of vocal support for a four-track solution to this long-standing problem. My hon. Friend the Member for Hertford and Stortford will be aware that it is a difficult problem in terms of the layout of the track and what surrounds it, and in terms of the platforming restrictions at Liverpool Street. However, as time goes on and as the proposals for developments along the Lea valley come to fruition, the economic case that can be made for this work on the track grows ever stronger.
Although there is no four-tracking solution currently on the cards, I remain interested and I am always happy to discuss the subject with my hon. Friend and the broader group of interested people. However, a three-tracking scheme is being delivered in the current period—it will be done by 2019—between Tottenham Hale and Stratford, which will help to relieve some of the capacity squeeze closer to London.
My hon. Friend invited me to specify other works that will be going on. I do not have the details about other works, but I will write to him to let him know what other enhancements and renewals are taking place on his local lines.