Clause 32 provides the powers to set procedural requirements in building regulations, which, among other things, will include the procedures for a new building control route for the design, construction and refurbishment of higher-risk buildings, the mandatory occurrence reporting framework during the design and construction of those buildings, and the golden thread of information during design and construction. I will explain each of the paragraphs—there are quite a few of them—in turn.

Proposed new paragraphs 1A and 1B of the Building Safety Act 1984 provide for building regulations to set procedural requirements relating to work, particularly for applications for building control approval. They will provide the basis for the new gateway process for creating new higher-risk buildings, and for a new refurbishment process when carrying out certain building work on higher-risk buildings. We will also be able to put in place new procedures for building control applications to be made to local authorities. The powers provided under the paragraphs will enable building regulations to make provision about notices that must be given to building control authorities—for example, when work commences—the issue of certificates, and the effect of such certificates. These regulations will also make provision for consultation arrangements, such as when building control authorities need to consult fire and rescue authorities on fire safety measures relating to building work. They will also include timeframes for providing consultation responses. Regulations made under these powers can also set out the grounds for granting or refusing an application.

With regard to the gateways, these paragraphs will allow for building regulations to set out new prescribed documents that must be included in applications for building control approval alongside plans for higher-risk buildings. They will also allow building control authorities the ability to set requirements when granting applications for building control approval. For example, the powers taken in proposed new paragraph 1B of schedule 1 to the Building Act 1984 would allow for staged approval routes for higher-risk buildings to provide greater flexibility for more complex developments—as we know, there can be many varied and complex developments. Applicants will be able to submit their application in stages with permission from the regulator, and in those circumstances building control approval will be strictly limited to the approved stages of work. Applicants will then need to submit plans and documents for other stages of work for building control approval before work on those stages begins.

Brendan Clarke-Smith Portrait Brendan Clarke-Smith (Bassetlaw) (Con)
- Hansard - -

It is very good to see you in the Chair this afternoon, Mr Efford. The Minister is discussing the powers that have been strengthened for both the regulator and local authorities—something I certainly welcome—and, following on from that, the ability to set requirements when granting applications for building control approval. Could the Minister talk a little more about these gateways and explain in further detail what happens in them, particularly gateways 2 and 3?

Christopher Pincher Portrait Christopher Pincher
- Hansard - - - Excerpts

I am obliged to my hon. Friend. The gateways are a crucial means of ensuring the quality and consistency of work, so that poor work or work that does not meet sufficient standards is spotted and stopped. Gateway 2 will be a hard stop that replaces the present building control deposit of plans stage: a gateway 2 application will be submitted to the Building Safety Regulator for approval. It has to demonstrate building regulations compliance, including that plans should be realistic for the building in use and will deliver a building that is safe to occupy. It will be an offence to start building work without Building Safety Regulator approval. We will say more about those gateways in secondary legislation.

Gateway 3 replaces the current completion and final certificate stage of building work—that is, when building work is complete. Again, it will be a hard stop, whereby an application must be submitted to the Building Safety Regulator with building plans and information about the building. The Building Safety Regulator can and will carry out inspections, and if it is satisfied—as far as it can determine—that the building complies with the building regulations requirements, it will issue a completion certificate. These are quite stringent processes that, as I trust my hon. Friend will recognise, are powerful tools. In circumstances where building control approval is strictly limited to the approved stages of work, applicants will then need to submit their plans and documents for other stages of work for building control approval before work on those building stages can begin.

The powers that we have taken in proposed new paragraph 1B will also allow applicants to submit applications for building control approval with plans and any relevant prescribed documents they consider appropriate for refurbishment in higher-risk buildings. That will ensure that applicants are not subject to disproportionate requirements when proposing relatively minor refurbishments, which could be replacement windows or changes to the central heating or lighting system, for example. However, the regulator will be able to refuse the application if prescribed information is not provided on request. All these provisions together will strengthen the regulatory oversight of design and construction.

--- Later in debate ---
Christopher Pincher Portrait Christopher Pincher
- Hansard - - - Excerpts

I think it will—in fact I am sure it will—because it will require that, in design, construction and refurbishment, information that is needed to demonstrate compliance with specific building regulations is available. It will also require that information garnered through mandatory occurrence reporting, which we discussed in Committee last week, will be available, and there will be a clear legal requirement on duty holders to hand over that information. The power will also be used to require certain information about safety occurrences to be provided to the regulator. I will discuss that a little more in a moment.

New paragraph 1D also creates the power to make regulations to set out the information and documents that must be stored in the golden thread, and to set out standards that the golden thread must be held to. We know there is currently a lack of information about higher-risk buildings, which makes it difficult to design, construct and refurbish them safely. We are also aware that where there is that information, it is often not kept up to date, not accurate or not accessible. We believe that having accurate, up-to-date information is critical to ensuring that buildings are managed safely, and this new paragraph will ensure that the information is recorded and that it is accurate, kept up to date and accessible to those who need it.

Dame Judith’s review recommended that a golden thread be put in place for higher-risk buildings. We agree, and the recommendation is being executed, recognising that it is critical to ensuring that buildings are safe.

New paragraph 1E enables the implementation of a key recommendation of Dame Judith’s independent review: mandatory occurrence reporting, which I mentioned a moment ago, for higher-risk buildings going through the design and construction phases. Mandatory occurrence reporting is intended to provide a route by which valuable building safety intelligence and trends will reach the Building Safety Regulator and be shared with industry.

The effect of that proposed new paragraph is to enable regulations to be drawn up that require duty holders in design and construction to establish a mandatory occurrence reporting framework to facilitate the reporting of occurrences on site so that the duty holders, who have an obligation to report them to the regulator, become aware of occurrences in good time. Mandatory occurrence reporting will aid in driving intelligence-led enforcement on the part of the Building Safety Regulator, promoting safety-conscious culture change and improving safety standards and best practice across the built environment.

Proposed new paragraph 1F enables building regulations to prescribe the form and content of documents or information that must be given as part of a building control application. Those documents will be a key part of the new building control routes for higher-risk buildings. Proposed documents include a design-and-build approach document, a fire-and-emergency file and a construction control plan. The documents must demonstrate compliance with building regulation requirements and be realistic for the building in use—I made that point to my hon. Friend the Member for Bassetlaw. That will ensure the consistency and quality of building control applications for higher-risk buildings.

The proposed new paragraph also allows for building regulations to set out how documents and information must be given. For example, it may be necessary to submit documents to the Building Safety Regulator via an online portal. It will also enable certain building applications to be refused if a document is not provided to the building control authority on request.

In order to check compliance, building control authorities must be able to inspect and test work, equipment, services and fittings, and to take samples. New paragraph 1G provides powers for building regulations to make provision for that. Building regulations will also be able to prohibit work from being covered for a period to allow the building control authority to inspect the work and to provide for the building control authority to cut into or lay open the work. Related amendments are also being made to section 33 of the Building Act to enable a building control authority to require a person carrying out the work to carry out tests of the work.

New paragraph 1A, which we discussed earlier, will allow building regulations to set prescribed timetables according to which building control authorities will need to determine applications—for example, gateway 2 applications, change control applications, and gateway 3 applications. That will help prevent unnecessary delays.

New paragraph 1H will allow building control authorities to extend that timetable where necessary, with agreement from the applicant—for example, if a development in hand is particularly complex. That will provide greater flexibility than under the current regime.

New paragraph 1I enables the drafting of regulations to allow persons affected by decisions made under the Building Act, or building regulations, to appeal against them. The Government supports the recommendation of Dame Judith’s independent review that the regulator must be “fair and transparent”. Where developers want to challenge a decision by a building control authority, it is right that they can do so. This clause makes provision to create routes of appeal to the regulator and the tribunal in England, and to Welsh Ministers or a magistrates court in Wales, whichever is appropriate. It also makes provision to set up procedural and administrative arrangements.

Brendan Clarke-Smith Portrait Brendan Clarke-Smith
- Hansard - -

We have discussed appeals. As part of the process, it is important that we have a robust and accessible appeals process, which is easy for people to undertake. Does the Minister share my opinion that these appeals need to be conducted in a reasonable amount of time? They have a habit of dragging on for long periods. With something as important as this, does he agree that people should have an assurance that when they make an appeal it is not just accessible but that they can expect an answer within a reasonable time period, to correct whatever problem has arisen?

Christopher Pincher Portrait Christopher Pincher
- Hansard - - - Excerpts

I am obliged to my hon. Friend for raising the issue of appeals. We have said in regulations that if the time limit is not met between the regulator and the applicant, and if an extension is not agreed, then the applicant can submit an application to the Secretary of State for a decision. That is a last resort. Through these provisions, we want to ensure that decisions can be made swiftly and efficaciously, so that challenges that may be brought to the Building Safety Regulator by a developer are dealt with rapidly, and a safe development can be advanced as quickly as possible. These include grounds for appeal, and the period during which an appeal can be lodged are also included in this clause.

There are a number of related consequential amendments in draft schedule 5. These include repeals of sections 16, 17 and 31 of the Building Act, which will become redundant with the introduction of new applications for building control approval under paragraphs 1A and 1B in clause 32.

That includes repeals of paragraphs 2 to 5 of schedule 1 to the Building Act, which are directly replaced by the new paragraphs 1A to 1I in clause 32, and amendments of existing references in the Building Act to, for example, the deposit of plans to the

“making of applications for building control approval”.

These new powers apply in Wales as in England, so the Welsh Government will be able to amend its building regulations as necessary. I appreciate that these are technical and rather dry paragraphs, but they are important to the success of the Building Safety Regulator, its powers and the appeals mechanism. Therefore, I commend clause 32 to the Committee.