Smart Meters Bill (Second sitting) Debate
Full Debate: Read Full DebateBill Grant
Main Page: Bill Grant (Conservative - Ayr, Carrick and Cumnock)Department Debates - View all Bill Grant's debates with the Department for Business, Energy and Industrial Strategy
(7 years, 1 month ago)
Public Bill CommitteesQ
Derek Lickorish: Yes, there is.
Q
Richard Wiles: We manufacture SMETS 1 and SMETS 2 devices. We are prepared to ramp up our production line to make sure that SMETS 1 can run in parallel to ensure that any potential shortfalls in capacity can be overcome by our increased production. We can continue to keep the momentum and supply chain running in that respect. Regarding installers, by the end of SMETS 1, we are probably looking at around 12 million devices. If the current installation rate continues through to July next year, that equates to around 1.3 million smart meters per month that need to be installed.
Whether we need additional installers is something that Trilliant has not supplied services on, other than installation processes, but organisations are geared up to supply the installation requirement for SMETS 1 and SMETS 2 to meet that deadline.
Q
Richard Wiles: Looking at the existing number that I have been made aware of, that may need to be increased. There may need to be additional practices and we need to ensure that whoever wants a smart meter gets it installed in time by 2020.
Derek Lickorish: It has been worked out for me—it says so here—that the additional resources to meet 2020 need to increase from where they are today by 283%. They need to be ready now to start running to meet 2020. I do not think that is possible because these need to be highly trained people. This is not a straightforward job for an electrician; it is more complicated than that. Before I come to resources, the current productivity rate of the teams working out there is less than half what was originally thought. You have to take that into consideration; it is not factored into my 283% increase.
As for manufacturing, subject to clarity about the SMETS 1 end date, because the supply chain is already winding down for that now, if clarity could be given on that, it would ensure that that manufacturing stream was kept running.
On manufacturing capacity for SMETS 2, once you have resolved the interoperability, once you have SMDA approval, once you have tested all these devices at scale, with DCC, it must be about 12 months. Anything less would have the potential to lock in problems for the future because of the model we have chosen. It is a difficult one to answer, but if we satisfy that, there is no reason why manufacturing capacity will not be available.
Thank you. If we can keep the answers brief, we will be able to get in Mr Carden and Mr Morris.
Q
Dr Sarah Darby: Potentially, this is part of a very big transformation of our energy system. If we are relying heavily on renewable supply, particularly for electricity, we have to be able to match demand with supply in real time very effectively. The smart meters are part of making that possible. That means effectively that they are part of the transition to a renewables-based energy system with very carefully managed demand and supply together. The environmental benefits of that would be very considerable.
Q
Dr Sarah Darby: Yes.
Q
Dr Sarah Darby: Yes, I would think so.
Dr Richard Fitton: I would add one point. The smart meter is a tool as well and from that tool we can hang things. With it comes this whole idea of being able to attach more efficient things for your home, such as appliances and heating systems. Once it gets in the house, people can then start to do smart things with it. You have got to consider those savings as well as the generic smart meter savings.