My Lords, these draft regulations were laid before the House on 13 February. They make consequential amendments to the Town and Country Planning Act 1990 and other primary legislation, as well as to the planning application fee regulations. These amendments reflect the two new routes for planning permission for Crown development that were introduced through the Levelling-up and Regeneration Act 2023. This legislation forms part of a wider suite of statutory instruments needed to implement these new routes. These routes are crucial to ensure that there is a more timely and proportionate planning process for nationally important public services and infrastructure.
I will start by providing some context and background to these regulations. Recent experience, including the response to Covid-19, has exposed that the existing route for securing planning permission for urgent Crown development, which was introduced in 2006, is not fit for purpose—so much so that it has never been used. Furthermore, government departments have struggled to secure local planning permission for nationally important public service infrastructure, such as prisons. The Levelling-up and Regeneration Act made provision to address these challenges by providing two new routes for planning permission for Crown development in England.
The first route, referred to as Crown development, is for planning applications for Crown developments that are considered of national importance. These applications are to be submitted to the Planning Inspectorate directly instead of to local planning authorities. A planning inspector will consider and determine the application, unless the Secretary of State for Housing, Communities and Local Government recovers the application to determine herself.
The second route is an updated urgent Crown development route. This will enable applications for nationally important developments that are needed urgently to be determined rapidly under a simplified procedure. Applications under the urgent route will be submitted to the Secretary of State for Housing, Communities and Local Government.
These new routes can be used for developments only where it is clearly justified. Provisions in the Levelling-up and Regeneration Act require that applications can be accepted by the Secretary of State only if she deems that the proposed development is of national importance and that it is urgent, in the case of the urgent Crown development route. I made a Written Ministerial Statement on 13 February which set out the principles under which national importance and urgency will be determined. Applicants are required when submitting an application to set out the reasons why they consider that the development is of national importance and, in the case of urgent Crown development, is needed as a matter of urgency.
I turn to the detail of the regulations. This is the first of a suite of statutory instruments needed to implement the Crown reforms. It makes amendments to primary legislation to reflect the two new Crown development routes. For instance, it amends references to planning permission set out in a range of different pieces of legislation. It also removes references to the previous urgent Crown development route in Section 293A of the Town and Country Planning Act, which now applies only in Wales. This instrument also sets the fee for an application for planning permission under both routes. This is the same as the fee that would have been paid to the local authority if the application had been submitted to it.
Following this statutory instrument coming into force, a further suite of statutory instruments will be made through the negative parliamentary procedure. These instruments will set the procedures for the two routes and make further consequential changes to secondary legislation in order to reflect the implementation of these routes. We have published these instruments in draft ahead of this debate to provide proper transparency on how the routes will operate.
My Lords, this has been a helpful debate. As ever, our great experts on planning in the House contributed to a good discussion. I will, of course, attempt to answer all the questions. I am sure that noble Lords will pull me up if I do not if I do not answer them. I will, of course, check in Hansard afterwards and reply in writing on anything to which I have not responded to fully.
The noble Lords, Lord Young and Lord Shipley, asked who is able to apply for planning permission through these routes. Section 293 of the Town and Country Planning Act defines who is an applicant known as an appropriate authority for the purpose of applications under these routes. For example, this includes where land belongs to a government department or is held in trust for His Majesty for the purposes of a government department. That department is considered to be an appropriate authority. For land belonging to His Majesty in right of the Duchy of Lancaster, the Chancellor of the duchy is the appropriate authority and for land belonging to the Duchy of Cornwall, a person that the Duke of Cornwall appoints is the appropriate authority. So land that goes into any of those routes will be appropriate for this route.
The uses for Crown development and confirmation of which developments Crown development can be used for was the subject of the question asked by the noble Lord, Lord Young. I am sure that he will ask again if I have got that wrong. It will be for the Secretary of State to assess on a case-by-case basis what is deemed nationally important, and it would not be appropriate to comment now on specific schemes. However, it is likely that the Crown development route will be used most for HMG programmes relating to nationally important public service development. For example, this would include, but not be limited to, new prisons or border infrastructure. Traditionally, those things are difficult in the planning process. The route could also be used for defence-related development, as PINS is able to put in place special procedures to handle information dealing with matters of national security. Special provisions exist whereby the Secretary of State can issue a direction limiting the disclosure of information relating to matters of the security of a premises through Section 321 of the Town and Country Planning Act 1990. The Crown development route can also be used for particularly sensitive or significant development being brought forward by, or on behalf of, the Crown. We expect few applications to be submitted through this route every year. It is not going to be used all the time; it would be an exception.
In terms of urgent Crown development, again, it will be for the Secretary of State to assess on a case-by-case basis what is deemed nationally important and needed urgently. When I looked at the papers for this SI, the first thing that came to my mind was the time when, during Covid, we were getting desperately short of mortuary space. This is a bit of a morbid subject but, in the middle of a pandemic, it is vital that you think about that and you may want to have an urgent process to deal with that sort of thing.
It would not be appropriate for me to comment on specific schemes, but the urgent Crown development route is expected to be used very rarely, where other planning application routes just cannot be used to secure a decision quickly enough. The pandemic might have been one of those instances. It will be used only where development needs to be put in place quickly, in a matter of days or weeks, and where it is in the national interest—for things such as medical centres, the storage and distribution of key goods and services in the event of a pandemic or, potentially, mortuary space.
The noble Lord, Lord Shipley, asked who makes the decisions—he was correct in his assumption on that; I hope that that is helpful—and whether the public will be able to object. I will come to those issues in a moment.
The noble Lord asked about how national importance is defined. The Government are committed to a planning system in which decisions are made locally. However, it is a well-established principle that, in limited circumstances, it is necessary for the Secretary of State to make planning decisions where issues of more than local importance are involved. In general, the Secretary of State will consider a development to be of regional or national importance only if it would: involve the interests of national security or foreign Governments; contribute to the provision of national public services or infrastructure, such as prisons or border infrastructure; support a response to international, national or regional civil emergencies; or otherwise have significant economic, social or environmental effects and strong public interest. The applicant will have to set out, as part of a statement accompanying the application, evidence demonstrating that at least one of those principles has been met.
The noble Lord, Lord Shipley, asked how “urgency” is defined. The applicant will be required to provide a statement to accompany the application setting out why they consider that the development is both nationally important and needed as a matter of urgency. The Secretary of State will accept applications through the urgent development route only where the applicant can demonstrate that the proposed development is both of national importance and needed urgently. The applicant will need to demonstrate that the proposed development needs to be made operational in an accelerated timeframe and that it is unlikely to be feasible using other application routes, including the Crown development route, and will need to evidence the likely consequences of not securing a decision within the accelerated timeframe. I hope that that is helpful.
The noble Baroness, Lady Thornhill, asked me about mayoral powers and strategic planning. I share her pain, as any local councillor will, over the planning process. I will never get back the hours that I have spent in discussion about great crested newts and rare species of bats and insects, so I feel her pain on that. However, these reforms are for national and very urgent issues only.
On mayoral or strategic powers, the Crown reforms will affect the ability of combined or mayoral authorities to call in applications of potential strategic importance. The relevant combined authority will instead be consulted for development coming forward through the Crown development route, so it will be done at that strategic level.
In response to all noble Lords’ questions about how further information on this will be provided, we will publish updated planning practice guidance to reflect the new routes coming into force. We intend to publish the amended guidance closer to the implementation of the routes.
The noble Baroness, Lady Thornhill, asked about transparency. As I said, applicants need to demonstrate that the application is of national and urgent importance, and the Secretary of State can accept that application only if she considers that that is the case.
When a decision is made to accept an application, as I set out in my opening speech, a letter will be written to the MP whose constituency the development falls in and will be deposited in the Libraries of both Houses. Application documents will be available and applications to both routes will be determined on planning merits, with the reasons behind whether to grant or refuse set out in the inspector’s report or the Secretary of State’s decision letter. I hope that that is helpful.
In my opening speech, I set out in some detail how community engagement will work; the noble Lords, Lord Shipley and Lord Jamieson, raised it again. Of course, community engagement is very important. Any comments made during the consultation and publicity period that raise material planning matters will be taken into account as part of the decision-making process. The local planning authority will also have a role to play. It will need to place the application and documents on its planning register and, as PINS does not have a local presence, the local planning authority will be required to affix site notices during the mandatory publicity period and notify owners or occupiers who adjoin the site. So, for that purpose, it will work just the same as the local planning process.
Regarding urgent Crown development community engagement, as I said, we would encourage consultation with local communities, where possible. If it is possible to do meaningful engagement in a timeframe, we would encourage that. Where it is not possible, the Secretary of State should use alternative methods to make sure that community views can be taken into account.
The noble Lord, Lord Jamieson, talked about fixing the planning system; we hope we will be able to do that. Working very quickly, we have already managed a major consultation on the NPPF and published a revised version in December. Yesterday, the other House had a long debate on the Planning and Infrastructure Bill, which will come to this House shortly. My belief is that there will always be a need for an urgency procedure for decision-making in councils. There will always be a need for some kind of urgent process and for the Secretary of State to be able to make a decision on national grounds. I hope that that has answered all noble Lords’ questions.
The Minister has been enormously helpful in answering the questions, but she did not touch on the question of whether a decision to use this route would be justiciable. She may not be able to answer that, but I assume that it would be.
The Minister mentioned the case of Covid and the mortuaries. As I understand it, this system can be used only where the Crown owns the land, so if it does not own the land, it will have to buy it before it can use this SI. If something is urgent but the Crown does not own the land on which the building is needed, I wonder whether the CPO will hold things up, or whether that can be part of a streamlined process.
I was assuming that it would be an application made on land already owned, but I will write to the noble Lord and set that out in further detail.
On his other point, my understanding is that all things are, technically, judicially reviewable, but I will find out the detail of that and set it out. Obviously, if we are going to put an urgent and national process in place, we want it to be able to speed through as quickly as possible, but, in the planning world, it would be most unusual for there to be no process of review should that be needed. I will get our planning team to check that for the noble Lord, and I will write to him with the exact details.
I have a question; it is not dissimilar to the one from my noble friend Lord Young. As I understand it, from what the Minister has laid out, it will in essence be up to the Minister or Secretary of State to determine whether this is urgent, nationally significant and so on. My real question is: what constraints will there be on him or her in determining that? Where is the opportunity to challenge, review or assess? I know that the Minister is going to come back on the issue of judicial review. Clearly, we do not want to have an urgent process be bogged down by it for two or three years; however, we would want some constraint on it. So what process is in place to ensure that the Minister is not in a position to determine all of this by himself or herself?
I am grateful to the noble Lord for reiterating those points. I set out that there is a set of criteria deeming whether an application is of national importance. The applicant will need to say which of those criteria they are using to say that it is of national importance. The same applies to the urgent procedure: the applicant will need to demonstrate one of those criteria for it being urgent, and the Secretary of State will decide whether or not that is the case. Out of the criteria I set out, the applicant will need to demonstrate that at least one applies. That is how it is going to work. I will have to come back to noble Lords on whether it will be reviewable.
In conclusion, the two new routes for planning permission that we are seeking to implement are necessary and timely; all noble Lords agree with that, I think. These regulations represent a crucial step to their delivery. I hope that the Committee will welcome the regulations, which address this critical requirement for a proportionate planning procedure for nationally important Crown developments.