Infrastructure and Projects Authority Debate

Full Debate: Read Full Debate
Department: Cabinet Office

Infrastructure and Projects Authority

Baroness Smith of Basildon Excerpts
Wednesday 10th October 2018

(6 years, 2 months ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Young of Cookham Portrait Lord Young of Cookham
- Hansard - - - Excerpts

I say to the noble Lord that I was around 20 years ago during the gestation of HS1 and precisely the same arguments were adduced against that: it was environmentally unsustainable; it was not value for money; there were other, greater priorities. I do not think that anyone in your Lordships’ House today would now argue that we should not have gone ahead with HS1. My own view is that in 20 years’ time, or whenever HS2 is complete, the same view will be taken of HS2.

Baroness Smith of Basildon Portrait Baroness Smith of Basildon (Lab)
- Hansard - -

The Minister will be aware, of course, of the IFG report entitled What’s Wrong with Infrastructure Decision Making? produced in 2017. I hope he has had the opportunity to look at its recommendations and will explain to the House which of those recommendations the Government have implemented. Also, when he talks about the skills needed by civil servants, will he accept that in these long-term projects the turnover of project managers is far too frequent? There is a stop–start approach, when what is needed, as well as the skills, is that civil servants, or whoever is in charge, should undertake a project from beginning to end so that we can see some continuity.

Lord Young of Cookham Portrait Lord Young of Cookham
- Hansard - - - Excerpts

I concur with that observation. There is a strong argument for having continuity of leadership within departments when you have these projects that run over many years. But as I said a few moments ago, the IPA is seeking to address that problem by building up the skills within the Civil Service with a new leadership programme and other initiatives. But I take the point, and I will feed it back to the IPA and the departments, that continuity within project leadership is essential if these projects are to be delivered within budget and on time.