Thursday 13th December 2018

(5 years, 5 months ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Young of Cookham Portrait Lord Young of Cookham
- Hansard - - - Excerpts

Can I write to my noble friend with the answer to that question? At the moment, as I indicated in my first reply, there is a dialogue between HS2 and the suppliers to ensure that the bids come in within the overall envelope that the Government have allocated. This may involve looking at some of the specifications that my noble friend has referred to. We are determined to stick within that envelope and all options will be looked at to make sure that we maintain the costs of this project.

Baroness Randerson Portrait Baroness Randerson (LD)
- Hansard - -

My Lords, Sir John Armitt from the National Infrastructure Commission thinks that HS2 could cost an additional £43 billion. Is it not time that the Government gave us an up-to-date estimate of the true cost of this plan? Do the Government accept that the north of England needs better east-west rail connections as much as it needs HS2 going all the way to the north and not stopping at Birmingham?

Lord Young of Cookham Portrait Lord Young of Cookham
- Hansard - - - Excerpts

To answer the first part of the noble Baroness’s question: as I said in my original reply, we will publish updated cost estimates as part of the full business case in 2019. In the second part, she reinforced the bid for more resources to go into public transport in the north; that has been noted and will be taken up in the spending review.