Railways: Line Resilience Debate

Full Debate: Read Full Debate
Department: Department for Transport

Railways: Line Resilience

Baroness Kramer Excerpts
Monday 10th March 2014

(10 years, 8 months ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Lord Berkeley Portrait Lord Berkeley
- Hansard - - - Excerpts



To ask Her Majesty’s Government what progress they have made in commissioning a study into alternative inland resilient rail routes to avoid the coastal route between Exeter and Newton Abbot.

Baroness Kramer Portrait The Minister of State, Department for Transport (Baroness Kramer) (LD)
- Hansard - -

My Lords, the Government have commissioned Network Rail to undertake a study to identify options for providing a resilient rail route west of Exeter and rail access to the coastal communities in the Torbay area. We have also asked Network Rail to implement schemes already identified to resolve weather-related problems in the Thames valley and west of England. However, the immediate priority is to restore rail services on this route as soon as possible.

Lord Berkeley Portrait Lord Berkeley (Lab)
- Hansard - - - Excerpts

I am grateful to the Minister for that Answer but, as we have had a lovely weekend and spring is clearly in the air, it is very easy for Ministers to forget about the disasters of the winter and to hope that they go away and that they will not have to spend the money. Will the Minister agree to come back to the House in a year’s time, just before the election, and say, “We have implemented all these long-term resilience measures that I mentioned, and a few more, and they are either finished or well on their way, and funded”?

Baroness Kramer Portrait Baroness Kramer
- Hansard - -

I always hesitate to say anything other than yes to the noble Lord, Lord Berkeley. As he will be well aware, we have a timetable for the long-term resilience project. We have completed the projects that were timetabled for 2013-14, such as the Whiteball tunnel, and others are timetabled for future years. However, the essence of what the noble Lord is talking about in terms of having a programme to make sure that we achieve resilience will be done over the next few months. The study that Network Rail is doing will lead to an interim report being published in July, which will result in a very important discussion in this House.

Lord Bradshaw Portrait Lord Bradshaw (LD)
- Hansard - - - Excerpts

Will my noble friend also take into account in her consideration the fact that, in finding an alternative route, the opportunity probably exists to cut 20 or 25 minutes off the journey time from Cornwall, which would be a massive improvement, akin to that achieved by HS2 between London and Birmingham? Perhaps she would have a look at that.

--- Later in debate ---
Baroness Kramer Portrait Baroness Kramer
- Hansard - -

I hope that very shortly we will have the terms of reference for the Network Rail study, which it intends to carry out in close co-operation with local authorities and LEPs. Network Rail has made a request to me that people pass ideas on particular routes back to it directly. However, if any Peer wishes to do so through my office, I will make sure that that information is communicated so that the study is as thorough as it needs to be.

Lord Faulkner of Worcester Portrait Lord Faulkner of Worcester (Lab)
- Hansard - - - Excerpts

My Lords, the Minister’s initial Answer was very welcome and we look forward to seeing the outcome of those studies. Will she take this opportunity to congratulate Network Rail on bringing the line through Dawlish back into use significantly earlier than appeared to be likely? I understand that Network Rail had something like 100 people working seven days a week on the restoration of the line, and it is to come back into use on 4 April or even earlier. I declare an interest as a member of the First Great Western stakeholder board.

Baroness Kramer Portrait Baroness Kramer
- Hansard - -

I say to the noble Lord, Lord Faulkner, that that is probably the most delightful question I have ever received because it indeed gives me the opportunity to congratulate and thank Network Rail for its incredibly hard work both during the days of crisis and since. We expect the Dawlish line to be back in use no later than 4 April—well in time for Easter—and that took a very strenuous effort. While I am at the Dispatch Box, perhaps I may also thank: the travelling public, who handled this situation so well; the bus and coach companies, which provided an alternative to rail; the train operators themselves, which provided, for example, special ticketing arrangements whereby people did not lose out because they could not make advance bookings; Flybe, which doubled the number of its flights to Newquay; and probably others whom I have missed. There are many to thank and I appreciate this opportunity to do so.

Lord Dykes Portrait Lord Dykes (LD)
- Hansard - - - Excerpts

How long will it be before the completion of the new north Oxford to London line?

Baroness Kramer Portrait Baroness Kramer
- Hansard - -

I say to my noble friend Lord Dykes that I do not have the data in the foremost part of my mind. As he knows, the matter is very much under discussion and I will get back to him with whatever detail is available.

Lord Brooke of Alverthorpe Portrait Lord Brooke of Alverthorpe (Lab)
- Hansard - - - Excerpts

My Lords, among those for whom there is a residual problem are the poor, beleaguered commuters travelling from Hastings to London, who for weeks now have had disruption due to flooding and have been trying to secure refunds from the rail operative. What are the Government doing to bring those rail companies into line, ensure that people are given a full refund for the tremendous inconvenience that they are suffering, which goes on and on, and bring this to an end quickly?

Baroness Kramer Portrait Baroness Kramer
- Hansard - -

This is the Tonbridge to Hastings route, which was closed because of a landslip. My understanding is that the reopening is delayed due to ground movement. We very much hope that the line will open again shortly but if there are issues—and I understand from the noble Lord that there are—will he pass them to my department and we will make sure that that they are passed on to the appropriate institutions for proper answer?

Lord Jenkin of Roding Portrait Lord Jenkin of Roding (Con)
- Hansard - - - Excerpts

I draw my noble friend’s attention to the excellent report produced by the Department of Energy and Climate Change on the severe weather over Christmas 2013. This indicates that a great deal can and has been done but one needs to know about it and find out what it all is. Would not a report of that kind, produced by my noble friend’s department, be extremely valuable?

Baroness Kramer Portrait Baroness Kramer
- Hansard - -

I assure your Lordships that there is constant monitoring, and a cross-departmental ministerial recovery group now meets weekly to discuss flooding issues. We take it in turns within my department to attend that meeting and make sure that the process is ongoing. It is also accurate to say that responsibilities have been divided up among a number of us to make sure that monitoring is effective; my responsibility will be as the ministerial representative for flood recovery for Gloucestershire and Worcestershire. Similarly, others have regional responsibilities and I will make sure that we report back as we get information through that process.

Lord Davies of Oldham Portrait Lord Davies of Oldham (Lab)
- Hansard - - - Excerpts

My Lords, the Minister knows that the floods have already cost something like £170 million. We are aware that the Prime Minister says that money is no object, and we will bear that in mind when the costings come through. However, how will Network Rail cope with the additional funding that will be necessary, either for the alternative line to which my noble friend Lord Bradshaw referred or for making the Dawlish line absolutely secure? Is the Minister being somewhat premature in praising Network Rail without convincing everyone that its funding will be adequate?

Baroness Kramer Portrait Baroness Kramer
- Hansard - -

Perhaps I can give the noble Lord some reassurance. Network Rail has estimated the cost of resilience projects—not recovery, which is handled separately—at £31 million. It is putting £5 million of its existing funding into the pot, and new money of £26 million is going towards that. If, when we get the interim report, we are starting to look at something much bigger—effectively, new construction—we will need to sit down and plan that properly.