Portishead Railway Debate

Full Debate: Read Full Debate
Department: Department for Transport
Friday 26th November 2021

(3 years ago)

Commons Chamber
Read Full debate Read Hansard Text Watch Debate Read Debate Ministerial Extracts
Andrew Stephenson Portrait The Minister of State, Department for Transport (Andrew Stephenson)
- View Speech - Hansard - -

I congratulate my right hon. Friend the Member for North Somerset (Dr Fox) on securing this debate on an issue that I am very aware is of great importance to both him and his constituents. I also congratulate him on his Down Syndrome Bill earlier today, which I was delighted secured Government support.

My right hon. Friend has been a passionate advocate for the restoration of the rail link to Portishead for many years, frequently championing the case in this House, and outside the House directly to Ministers. The restoration of the railway is part of MetroWest, which is a third-party scheme promoted by the West of England Combined Authority and North Somerset Council. The Government have committed to funding the scheme, with £31.9 million of support to close the funding gap on this project. This is dependent on the success of the development consent order that my right hon. Friend mentioned, alongside the endorsement of a full business case through the rail network enhancement pipeline.

The application for a development consent order for the Portishead branch line MetroWest phase 1 scheme includes works and powers to enable the reinstatement of the railway line between Pill and Portishead, an upgrade to an existing freight line and two new stations. The section to be reinstated has significantly overgrown since the railway stopped running to Portishead in 1964 and would require some clearance work. The scheme also involves proposals for clearing vegetation along the existing freight line through the Avon gorge woodlands special area of conservation, which is home to a number of rare species of plants including the Bristol whitebeam.

The examination into this application for a development consent order began on 19 October 2020 and concluded on 19 April 2021. Following this, the Secretary of State received the examining authority’s report on 19 July, with a statutory deadline for a decision by 19 October. As with all nationally significant infrastructure projects such as this, this is a complex scheme and there can be detailed matters that need to be worked through even after an examination has closed.

My right hon. Friend will be aware that, following the written ministerial statement laid on 19 October by the Under-Secretary of State for Transport, my hon. Friend the Member for Witney (Robert Courts)—the Minister for Aviation, Maritime and Security—the decision on this development consent order application has been extended to 19 April 2022 to allow for further consideration of environmental matters. Since then, the Secretary of State has requested additional information from North Somerset Council, as the applicant for the DCO, and comments have been invited from interested parties on this response.

Liam Fox Portrait Dr Fox
- View Speech - Hansard - - - Excerpts

I hope it is not pointing out the blindingly obvious that when people look at projects like HS2, which are able to tunnel under the entire area of the Cotswolds, they find it a touch hard to swallow that we have significant delay because there is some overgrowth on a line that last ran in the 1960s. I hope the Government will understand that.

Andrew Stephenson Portrait Andrew Stephenson
- Hansard - -

My right hon. Friend makes a valid point, although I am sure he will remember that phase 1 of HS2, taking the line from London to the west midlands, took four years to get through the House and the detailed examination of tens of thousands of pages of an environmental statement. I, like him, want to see us moving forward projects at pace, but however we legislate for nationally significant infrastructure projects—whether by hybrid Bill, DCO or other means—there is a process we have to follow and it is, unfortunately, quite bureaucratic. But I think we also share a view that we must protect the environment and do everything we can to mitigate the impacts of all such schemes.

This is still a live planning application and it will now be for the Secretary of State to consider his decision in the light of the original report and the recommendations from the examining authority and all other relevant information, including the responses to the most recent consultations. As the Secretary of State is the decision maker for all applications for transport DCOs and the competent authority for any habitat regulation assessment, this is required to be undertaken to assess the impact of a scheme on a European-protected site, such as the Avon gorge woodlands special area of conservation. It is important that he, or any other Minister delegated to undertake a planning decision on behalf of the Secretary of State, brings an unbiased, properly directed and independent mind to his consideration of that application. Decisions on applications need to be based on planning matters only and all decisions need to comply with all necessary processes and legislation regardless of the risk or otherwise of potential legal challenge.

I am not involved in the decision on this DCO, but my right hon. Friend will understand that, as the decision on the application is under consideration in the Department, I cannot take part in any discussion of the pros or cons of the proposal. That is to ensure the process is correctly followed and remains fair for all parties.

I recognise that extending decision deadlines for DCOs has implications for the scheme’s delivery and the Government’s commitment to levelling up. It is therefore only used where it is absolutely required to take further necessary steps to ensure a legally robust decision. While a new deadline for a decision on the DCO has been set for 19 April 2022, the Department is working hard to enable a decision to be made ahead of that deadline.

I recognise that all transport schemes have an environmental footprint. It is right that we fully understand them and any other impacts resulting in such schemes, and ensure that they are mitigated appropriately, whether that is in relation to the planning decision or the funding decision.

With regard to funding for the scheme, I can assure my right hon. Friend that the Department will continue to work closely with the West of England Combined Authority, North Somerset Council and Network Rail counterparts on the approval process of the scheme’s full business case. I understand that the West of England Combined Authority and North Somerset Council sent a letter to the Secretary of State on 12 November that set out concerns about the extension to the DCO deadline and ongoing costs. A reply to that letter will be sent shortly.

In conclusion, the Government are committed to improving rail services in the wider Bristol area. I understand my right hon. Friend’s impatience for the scheme to progress, following his years of campaigning. As I have set out, the application for any development consent order needs to follow appropriate processes and any decision must be made in line with the relevant legislation to ensure that it is robust. We are aware of how important the scheme is to my right hon. Friend’s local area. Although I am unable to comment directly on the merits of the individual DCO application in respect of funding from my Department, we will continue to provide support to the West of England Combined Authority and North Somerset Council to help them to develop their business case.

I hope that my right hon. Friend is reassured that my Department fully appreciates the importance of the proposal to his constituency, and we heard that message loud and clear again today. I thank him for raising this important issue.