Debates between Alan Whitehead and Grahame Morris during the 2017-2019 Parliament

Thu 23rd Nov 2017
Smart Meters Bill (Third sitting)
Public Bill Committees

Committee Debate: 3rd sitting: House of Commons

Smart Meters Bill (Third sitting)

Debate between Alan Whitehead and Grahame Morris
Committee Debate: 3rd sitting: House of Commons
Thursday 23rd November 2017

(6 years, 6 months ago)

Public Bill Committees
Read Full debate Smart Meters Act 2018 View all Smart Meters Act 2018 Debates Read Hansard Text Read Debate Ministerial Extracts Amendment Paper: Public Bill Committee Amendments as at 23 November 2017 - (23 Nov 2017)
Alan Whitehead Portrait Dr Whitehead
- Hansard - -

Not entirely. That is one interpretation of the word “offering”. If we adopt that theoretically interesting but practically difficult interpretation, what are we doing here, worrying about the roll-out? Provided that we can ensure that the chosen vehicles for the roll-out—the energy supply companies—can at some stage up to the end of 2020 tick a box showing that they have contacted Mrs Miggins of Acacia Avenue and Mr Bloggins of somewhere else, and asked them “Do you want a smart meter: yes or no?” and those people answered, “Hmm, I don’t know,” that is the end of it. Presumably we could end up at the end of 2020 with 20% coverage and a small number of meters rolled out.

Grahame Morris Portrait Grahame Morris
- Hansard - - - Excerpts

I am following my hon. Friend’s arguments about critical mass and the number of people participating. Does he have a view about why Northern Ireland is not in the scope of the Bill? With regard to Scotland, the hon. Member for Stirling pointed out that it was because of problems with internet coverage, and so on. Is there a similar issue with Northern Ireland and is that relevant to helping to achieve critical mass in the number of people who apply?

--- Later in debate ---
Alan Whitehead Portrait Dr Whitehead
- Hansard - -

Thank you, Mr Gapes. I am happy to follow your guidance. In my defence I can only say that I think I was led by an intervention into an interesting anecdote about what happens in the United States as far as meter installation is concerned. I will endeavour not to go any further on that.

We have a smart meter installation programme that is voluntary and, at the same time, we need a proportion—not 100% but quite a lot—of smart meters installed in order to make the programme work by having worthwhile aggregated data, so we clearly need to put a lot of effort into ensuring that the benefits of the programme are explained to the public. The evidence suggests that the public overwhelmingly like smart meters when they are introduced and that they want to have them in their homes. We therefore need to make a lot of effort over the period to ensure that the two ends—the voluntary nature of the programme and the need for substantial roll-out—can be reconciled. That will constitute much of our debate over the next few sittings. What is it that we need to be doing and should be done, but perhaps has not been done to ensure that the roll-out programme gets its output properly organised and smart meters installed?

The first question is about what we mean by an offer for everyone to have a smart meter. We have gone over that for a little while, and I am sure the Minister will have something to say on that. We then need to consider what we mean by the 2023 date in the Bill. I have four possible explanations as to the thinking behind that date.

The first is that we may not actually meet the roll-out date of the end of 2020, so we may need Government control to continue up to the end of 2023. Let us remember that this is about Government control of licensing arrangements for the whole roll-out. We may need that control to continue to deal with the eventuality that the roll-out date is changed. We may, at some future date, say that the new target is 2021, 2022 or whatever, and that we still need that control in place. We do not want to be here in 2023—I probably will not be here, but other hon. Members may be—going through this whole thing all over again and saying that we would like to have that control extended to whatever date.

The second is to do with the remedial action that may need to be taken if smart meters are just offered up to 2020 and the offer proves to be just that. Conceivably, given what the Government have said is their aim for the roll-out, we may reach the target date for their offer to be made—the end of 2020—and it may turn out that it is not really a roll-out at all and that we need to do various other things. Perhaps the 2023 date is there so that we can consider what to do in the eventuality that the offer turns out to be not very good at all.

There is also the question of what is happening with the specification of smart meters. We will look further at that, but it is pertinent to the roll-out date. As we heard in evidence, the Data Communications Company is supposed to control everything as far as smart meters are concerned. It will receive and organise data, it will communicate between the centre, the smart meters and the many networks, and it may well be responsible for further patching networks to ensure that wide area networks work. All that will be done through the DCC. It was always necessary for the DCC to start its roll-out to enable smart meters that have been installed and those that will be installed to connect with it and therefore go live at the earliest possible date. However, the DCC systematically failed to go live when it should have done. It repeatedly announced delays in going live. It eventually went live in autumn last year, under circumstances in which most of the industry raised substantial eyebrows.

Grahame Morris Portrait Grahame Morris
- Hansard - - - Excerpts

We are dealing specifically with dates and with whether we have a justification for extending the roll-out period by three years. As my hon. Friend indicated, we are talking about huge sums of money. That may not be public money from the Treasury, but the consumer will certainly bear the scheme’s cost, which is of the order of £12 billion. It is relevant that the DCC, which is the company responsible for delivery, and the framework and arrangements that sit around it—the Minister seeks to amend some of the terms of those, particularly the dates involved—are fit for purpose. Is the DCC a stand-alone company or a subsidiary of a larger group or company?

Alan Whitehead Portrait Dr Whitehead
- Hansard - -

My hon. Friend asks two questions, one of which I fear is a little outside the scope of the Bill—

--- Later in debate ---
Alan Whitehead Portrait Dr Whitehead
- Hansard - -

Indeed, Mr Gapes, and I would not want to go down that path either.

Grahame Morris Portrait Grahame Morris
- Hansard - - - Excerpts

I am certainly not going to challenge your patience, Mr Gapes—

--- Later in debate ---
Grahame Morris Portrait Grahame Morris
- Hansard - - - Excerpts

That is certainly not my intention, Minister. My point relates to the amendment, the justification for extending the date by an additional three years and whether the delivery vehicle is fit for purpose. Was my hon. Friend surprised, as I was, when the witnesses told us that only 250 units had gone live to date? Does that imply that the company is fit for purpose?

Alan Whitehead Portrait Dr Whitehead
- Hansard - -

I thank my hon. Friend for that intervention, which is absolutely bang in scope.