All 1 Debates between Adam Holloway and Paul Maynard

Tue 28th Nov 2017

Lower Thames Crossing

Debate between Adam Holloway and Paul Maynard
Tuesday 28th November 2017

(6 years, 12 months ago)

Commons Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Paul Maynard Portrait The Parliamentary Under-Secretary of State for Transport (Paul Maynard)
- Hansard - - - Excerpts

I congratulate my hon. Friend on securing this debate on the lower Thames crossing. He raised his constituents’ concerns diligently, and I would expect no less from such an assiduous constituency MP. Before I respond to the detailed points he raised, I reassure all those who are impacted by congestion at Dartford that tackling congestion on the strategic road network has to be a priority for the Government and Highways England.

I beg my hon. Friend’s forgiveness for reflecting briefly on how we got to where we are. The idea of a tunnel crossing at Dartford was first proposed in the 1920s. Initially, a crossing between Tilbury and Gravesend was suggested to replace the ferry service, but that was rejected in favour of a route further upstream, nearer Dartford. Of course, the Tilbury to Gravesend ferry is still in operation today, providing a half-hourly service.

Meanwhile, the Dartford crossing has provided the only road crossing of the Thames east of London for over 50 years. It is now one of the busiest roads in the country, used 50 million times a year by commuters, business travellers, haulage companies, emergency services and holidaymakers alike, connecting communities and businesses; providing a vital link between the channel ports, London and the rest of the UK; enabling local businesses to operate effectively; and providing access for local residents to housing, jobs, leisure and retail facilities on both sides of the river. In summary, it is a critical part of our strategic road network.

The crossing opened in stages as traffic demand grew. The west tunnel opened in 1963, the east tunnel in 1980 and the bridge in 1991. The existing crossing, as my hon. Friend pointed out, is at capacity for much of the time and is one of the least reliable sections of our strategic road network of motorways and major trunk roads. As he well knows, congestion on and the closure of the existing crossing occur frequently. That creates significant disruption and pollution, which impacts on communities and visitors locally, regionally and, indeed, up and down the UK.

The Government recognise that a lower Thames crossing is needed to reduce congestion at the existing Dartford crossing and to support economic growth across the region. The objectives of the scheme include affordability for both the Government and users, value for money, improved resilience of the Thames crossings and the major road network, and minimising adverse impacts on health and the environment by improving safety.

In 2009, the Department examined five locations where an additional crossing could be built. The most easterly of those were found to be too far from the existing crossing to ease the problems at Dartford and were eliminated from further consideration. In 2012, the Department began to appraise the remaining three locations, leading to a public consultation the following year. Location A was at the existing crossing, location B would have connected the A2 and the Swanscombe peninsula with the A1089, and location C was to the east of Gravesend. Later that year, the Government announced a decision not to proceed with location B because of the impact on local development plans and the limited transport benefits.

The Government published their response to the consultation in July 2014, confirming the need for an additional crossing between Essex and Kent. It commissioned Highways England to carry out a more detailed assessment of the remaining two locations, A and C.

More than 47,000 people took part in the consultation, making it the largest-ever public consultation for a UK road project. Highways England analysed the consultation findings and reported back to the Department for Transport, and in April 2017 we announced that our preferred route for the crossing was at location C. The route comprises a bored tunnel under the Thames, a new road north of the river, joining the M25 between junctions 29 and 30, and a new road south of the river, joining the A2 east of Gravesend. The preferred route announcement allows for detailed design and assessment to be carried out on the route. Highways England has written to everyone within the development boundary and has contacted the 22,000 people who have registered for updates.

Having responded to the feedback received during the preferred route consultation, Highways England is now undertaking further work to understand the extent to which it might be appropriate to increase the tunnelled section of the route to reduce noise and other environmental impacts. Furthermore, in relation to some of the concerns my hon. Friend has just raised, Highways England is now putting forward some important changes to the project design in response to the feedback it received in the consultation.

The changes include a new design for the junction with the M25 to help it blend better with the local landscape; a new junction and link road at Tilbury to reduce the impact of HGVs on local roads; the removal of the proposed A226 junction at Gravesend Road to reduce the impact on local villages, as my hon. Friend mentioned; a new design for the junction with the A2 and a widening of the A2 through to junction 1 of the M2 to help improve traffic flow; and a proposal for three lanes in each direction between the A2 and A13, rather than just two, as this could provide greater benefits. In addition, Highways England will be assessing carefully the air quality and other environmental impacts of three lanes as it continues its design work. All the updates to the route design will be consulted on in 2018. This will allow all interested parties, including my hon. Friend, a further opportunity to give feedback on the latest version of the route.

An option to create a new crossing at Dartford was thoroughly assessed but rejected as it would not provide sufficient additional free-flowing capacity to the network. A new route at the existing crossing would not improve traffic resilience and would still cause severe congestion. The route would take at least six years to build and cause severe disruption affecting hundreds of millions of journeys while under construction. It would also worsen air quality and noise pollution in the immediate Dartford area.

The lower Thames crossing should not be seen as an isolated proposal. We have listened to concerns about the existing Dartford crossing.

Adam Holloway Portrait Adam Holloway
- Hansard - -

I appreciate the constructive way in which my hon. Friend and the other Ministers have approached this since the decision was made, and, as I said, Highways England is being very decent, but I must return to my earlier point. How is a road that will reduce congestion at Dartford by only 14% still about traffic mitigation? It is not about sorting out Dartford; it has morphed into an issue of economic development, and we are kidding the public if we suggest otherwise.

Paul Maynard Portrait Paul Maynard
- Hansard - - - Excerpts

I recognise the point my hon. Friend is trying to make. I have tried to make it clear that I am focusing on the traffic management aspects of the project, rather than the issue of wider economic benefits to which he refers.

I want to explain some of what we are seeking to do to improve matters at the Dartford crossing. Like many people, I recognise the concerns about the crossing. Anyone who has to drive through it will always bear in mind the possibility of severe delays. Highways England keeps the safety and performance of the crossing constantly under review to identify areas that can improve the crossing for all road users. The traffic safety system, introduced as part of the Dart charge, continues to be improved, together with the management of dangerous goods and abnormal loads.

Actions are being taken to improve the management of traffic during incidents and ensure the reopening of lanes as soon as possible afterwards. The road signing on the northbound Dartford crossing approaches is being reviewed, as is the movement of different types of vehicle as they approach the crossing, to see what improvements can be made.

Work continues with local authorities on both sides of the crossing to improve traffic flows between the local and strategic road networks, and I know that my hon. Friend the Member for Dartford (Gareth Johnson) is closely involved in those very discussions. That includes joint working by Highways England and Kent County Council on a number of improvement measures for the junctions used by traffic approaching the crossing directly from Dartford. Highways England will continue to monitor the conditions at the crossing to understand how various factors are contributing to its underlying performance. It will also evaluate the impact of the measures implemented, and the public will be kept informed of the findings.

Last but not least, as was announced alongside the preferred route for the lower Thames crossing, we are committed to delivering a £10 million package of measures over the next four years to improve traffic flow at and around the existing Dartford crossing. The roads Minister, my hon. Friend the Member for Hereford and South Herefordshire (Jesse Norman), meets the chief executive of Highways England monthly, and I can assure my hon. Friend that the performance of the existing crossing is kept under regular review.

I heard very clearly my hon. Friend’s suggestions about connected and autonomous vehicles, and I assure him that they are a frequent topic of debate in the Department. We want to ensure that all road projects take account of the future use of technology, and of how that might change road use in particular.

We recognise that there is more to be done at the existing Dartford crossing, and I am sure that Highways England will keep my hon. Friend and neighbouring Members updated on its plans and future actions. I was pleased to hear that representatives of Highways England were able to meet my hon. Friend today, so that they could go through the plans in more detail, and I hope that that engagement will continue and deepen.

I trust that I have reassured my hon. Friend about some key facts. The Government understand the critical role played by the Dartford crossing and the M25 in our strategic road network, but we also understand its local significance for residents on both sides of the estuary, including those in my hon. Friend’s constituency. We take congestion at the Dartford crossing, and in the wider Dartford area, very seriously, which is why we are taking action to improve matters in both the wider strategy network and the Dartford area.

Adam Holloway Portrait Adam Holloway
- Hansard - -

Will the Minister give way again?

Paul Maynard Portrait Paul Maynard
- Hansard - - - Excerpts

I will, since I have the time.

Adam Holloway Portrait Adam Holloway
- Hansard - -

I greatly appreciate it.

Honestly, I love my constituents, but if I thought it was right to put the crossing there, I would man up, look them in the eye and say, “I am really sorry, but this is the correct decision.” Under any Government, including a Labour Government, I would say, “This is the right thing to do.” However, it is not about that. It is blindingly obvious to anyone that if we do not fix the M25 at Dartford, we will not fix the problem. What is the Department’s response to the fact that its own figures say that this new crossing will reduce congestion by only 14% at today’s rates, let alone by the time the thing is built? There is a desperate need for a new crossing at Dartford, and the Government will have to come back to it at some point.

Paul Maynard Portrait Paul Maynard
- Hansard - - - Excerpts

I recognise the principal point that my hon. Friend is trying to make. The message that I am trying to communicate in return is that there are more ways than one of tackling the problem. I believe that substantial improvements can be made at the Dartford crossing in terms of ensuring its reliability and its stability, to ensure that when incidents do occur the road can be cleared as quickly as possible. I also think, however, that there is a wider strategic justification for the lower Thames crossing, which is why the Government made their announcement back in April.

We have to plan not just for the short term, but for the medium and the long term as well. We must develop the proposals for the lower Thames crossing as part of one of the biggest programmes of investment in the strategic road network in a generation. It supports motorists by investing in our motorways and our major A roads, which will boost economic growth, locally, regionally and nationally. That is why I think that we have made the right decision for the people of Kent, and for the people of Britain as a whole.

Question put and agreed to.