Railways: High Speed 2

Viscount Astor Excerpts
Wednesday 11th July 2012

(12 years, 4 months ago)

Lords Chamber
Read Full debate Read Hansard Text Read Debate Ministerial Extracts
Asked By
Viscount Astor Portrait Viscount Astor
- Hansard - -



To ask Her Majesty’s Government what progress they have made in reviewing the economic viability, value for money and benefit-cost ratio of the High Speed 2 London to Birmingham, and London to Leeds and Manchester, lines.

Viscount Astor Portrait Viscount Astor
- Hansard - -

My Lords, HS2 is a controversial proposal designed to operate a high-speed rail link between London and Birmingham, and eventually onwards to Leeds and Manchester. It is controversial for a number of reasons.

The first is the route: a new line cutting through some of the most unspoilt countryside in England, where there are already two existing lines, one operated by Virgin Trains and the other by Chiltern Railways. Either line could be upgraded or the new line could follow one of the existing motorway routes—an option suggested by the Transport Select Committee—which would cause minimal disruption compared with HS2.

However, I want to concentrate on cost. The question is whether the cost of £33 billion is worth the benefits that might accrue. We all want better services from north to south, but I challenge the assumption that HS2 is the answer. The Government’s case rests on the assumption that rail travel is destined to grow at the rate projected by the Department for Transport, but one has to say that the department’s record in projecting future passenger numbers is not good.

In the words of the National Audit Office, the department used “hugely optimistic assumptions” about passenger numbers on HS1. Passenger numbers from 2007 to 2011 were only one-third of the original 1995 forecast and two-thirds of the 1998 forecast. The NAO went on to say that the costs had exceeded the savings from shorter journey times, and the Public Accounts Committee said that costs would eventually rise to £10 billion.

I am sure that the Minister will quote the support of the All-Party Parliamentary Group for High Speed Rail. However, it is a group set up specifically to support high-speed rail, so I would remind him of another report by the Public Accounts Committee, which came to the opposite conclusion and recommended:

“The Department must revisit its assumptions on HS2 and develop a full understanding of the benefits and costs of high speed travel compared to the alternatives”,

and that it should consider the alternatives, such as investment in more local train routes.

The department claims to have improved its forecasting, with better computer modelling and more computer power, but of course wrong assumptions in produces wrong statistics out, whatever the rise in computer power. What it has failed to take into account is that the projected benefits are largely dependent on business use, and business use is changing.

Why travel so often when Skype and internet conferencing are becoming the norm? Reductions to already short journey times are largely irrelevant to business efficiency as carriages are now linked to the internet and provide a good working environment. To assume that all time spent on trains is wasted is simply not credible. The department’s own report Productive Use of Rail Travel Time and the Valuation of Travel Time Savings for Rail Business Travellers asserts that a reduction of 10 minutes in journey time increases the amount of working time by only 0.75 of a minute.

HS2 does not deliver a step change in journey times. It connects to the centre of Birmingham but there is no onward connectivity and a change is required; nor does it connect to Heathrow, as promised in the Conservative Party manifesto. This connection is offered as a possibility, some time after phase 2, in 2033. What is more, a route via Heathrow would cause the least damage to the Chilterns, crossing through its narrowest part. HS2 will cut the journey time from London to the centre of Birmingham but only by barely half an hour, and much less if you want to make an onward connection.

By the Government’s own admission, the benefit-cost ratio for phase 1 declined from 2.4 in March 2010 to 1.4 in January 2012, and to just 1.2 in April 2012. However, even this overestimates the true position, as the DfT also admits that its assumptions are based on out-of-date gross domestic product figures. If one takes into account the latest GDP forecast and uses the later rail demand model, the benefit-cost ratio dips below 1—well below the Government’s own ratio for acceptable capital expenditure benefits.

In an earlier statement to the Transport Select Committee, the then Transport Secretary Philip Hammond agreed that below 1.5 he would need to seriously review the viability of the project. A full Y route to Manchester and Leeds produces only a modest increase to 1.4 in the benefit-cost ratio. It seems to me that the department is going to have to review the project.

We know that peak-time services from Euston in the evenings are only 56% full and that Manchester services are 45% full. We know that total journeys per person by all transport modes are declining, not increasing, so to justify the projected increases by 2032 there would have to be a large shift from road to rail. Looking ahead to 2032, we know that most cars will be electric and therefore very fuel-efficient. The Government accept that HS2 does not reduce CO2 emissions. There is no evidence that HS2 is going to cut road usage. By 2032, electric cars could easily be driving themselves on the main routes, as has already been tested in America.

What will increase in the future, as I think everybody agrees, is commuter use of the rail network, but HS2 does not solve that issue. I believe that the answer is an upgrade of the existing line, more frequent services, more carriages and longer platforms—which could all be achieved at a fraction of the cost for the same result.

The recent growth following the upgrade of the west coast main line led to huge improvements in service frequencies and journey times and shows what can be done by improvements to existing services. Upgrading is estimated to cost about £2 billion and the department says that it produces a benefit-cost ratio of over 5.0. That is real value for money. This would cater for all the future demand predicted by the department and provide the capacity much sooner so that any crowding problems were addressed much faster. It would also cause significantly less disruption to the existing network than what is proposed.

We are also told that 1 million jobs will be created, but the evidence to support this claim is questionable. Various comparisons are made concerning Europe and the TGV, but a close analysis of what has happened in Europe shows a very local movement in jobs and not necessarily a total increase in jobs in the wider area. Just 1,500 permanent jobs will be created by HS2, but the department admits that seven out of 10 jobs attributed to phase 1 will benefit London, not the regions. We could create a lot more jobs in the north by supporting industry there with direct investment, grants, help with bank finance and better local services.

We need to spend money upgrading our entire rail network. We need infrastructure spending that links the rail network to airports and then to city centres. Those in the north have been pressing for a northern hub that connects key northern cities by rail. East Anglia, for example, is desperate for better services and connections. The concern is that HS2 will inevitably drain funding away from the rest of the network and that desperately needed improvements will not get funding.

The commendable House of Commons Transport Committee report called for a proper transport strategy before HS2 phase 1 and phase 2 proceed. It also called for an explanation of how HS2 fits within an overall transport strategy and for the summary and assumptions of the financial case so they can be properly examined.

We need a rail strategy that will bring real benefits to northern businesses rather than just marginally faster journey times to London. The planned HS2 does not connect to HS1, which is not much help to passengers arriving from Europe. They will still have to get the Tube or the bus across London.

HS2 fails on the four key principles that even HS1 managed to pass: it does not follow existing noisy transport corridors; it does not follow the shortest route through areas of outstanding natural beauty; it is not proposed to be tunnelled through the most sensitive areas; and it does not provide benefits for local communities affected by the route or by access to the service.

I have done a quick canter through this about as fast as a train will go, because time is limited. I have given notice to the Minister of the questions I have asked this evening. I am sure he will be able to address the issues of cost and benefit and try to prove the Government’s case for HS2.

--- Later in debate ---
Earl Attlee Portrait Earl Attlee
- Hansard - - - Excerpts

My Lords, I congratulate my noble friend Lord Astor for securing this debate on a very important subject. I also thank noble Lords for their typically well informed contributions. It is certainly not a matter of nimbyism. It is important and right to raise questions about a project as significant as HS2 and I am happy to try to address such questions this evening. Large scale infrastructure projects are not new or unusual. They have been going on for many years and they have been controversial. For instance, the Jubilee line extension was controversial at the time of its conception, but where would we be without it now?

In his opening speech, my noble friend questioned the benefits that we expect HS2 to deliver. I want to reassure him on this point. I believe passionately in a successful Britain, a country that can compete and thrive in a global economy. To achieve this we need infrastructure fit for the 21st century and beyond. We cannot just make do and mend. Good transport equals good economics. One of the best ways to support British business, power up the recovery and put people back to work is to invest in, and modernise, our transport networks. HS2 will revolutionise travel in our country, transforming connectivity between London, the Midlands and the North, and, as the noble Lord, Lord Adonis, said, it is the best decision. It will provide a step change in the capacity of the rail network to accommodate the growing demand for long-distance travel, providing up to 18 trains an hour, each with up to 1,100 seats. Without it, our main north-south rail arteries will become increasingly disrupted and overcrowded, damaging both our economy and our way of life.

HS2 will slash journey times for passengers between our key cities and regions. It will be a truly national network benefiting the whole country. While the high-speed line itself runs to Birmingham, Manchester and Leeds, the new trains will be designed to continue onto the current network, providing direct services to destinations further afield, such as Liverpool, Newcastle and Glasgow. It will help rebalance the economic geography of the country, supporting thousands of jobs and unlocking growth and opportunity for generations to come. It will be a truly transformative project.

Some noble Lords have questioned whether a new high-speed network is the best way to provide the additional north-south capacity our country needs, suggesting instead a programme of enhancements to the existing network, but this would provide only a short-term answer to the demand challenges addressed by HS2, and even then, only at the cost of significant disruption to passengers on affected lines, all the while sacrificing the connectivity benefits high-speed rail will bring.

Several questions related to the approach taken to assessing the economic viability of the project. In January, when my right honourable friend the Secretary of State for Transport announced her decision on HS2, she set out the economic case underpinning this project and the department will shortly be publishing further updated economic analysis. However, the benefit-cost ratio analysis forms only one part of the decision-making process for this strategically important project. There are wider strategic considerations as well, which I outlined a moment ago. I will try hard to answer as many supplementary questions as I can and when I fail I will, of course, write.

The noble Lord, Lord Rosser, asked about the two hybrid Bills. He will know that each hybrid Bill requires a very considerable amount of work to determine what powers are needed. Several noble Lords, including my noble friend Lord Astor and the noble Lord, Lord Stevenson of Balmacara, claimed that there is no economic case for HS2. I beg to disagree. HS2 continues to have a good economic case. The Government have always been clear that as well as offering good value for money in itself, there are wider social and economic benefits associated with improving connectivity and supporting regeneration in our major cities.

My noble friend Lord Bates was concerned that HS2 will not rebalance the economy. He talked about the north-south divide and the unintended benefit for London at the expense of the regions. The Government’s position has the support of businesses and their representative organisations across the country, which express their belief in the importance of improving our transport network, and specifically our intercity rail network, in order to enable higher economic productivity.

The noble Lord, Lord Stevenson, asked about the release of the Major Projects Authority report. The Cabinet Office has a policy of not releasing the reports for two years, but they will be released at the appropriate point. Noble Lords asked me about the DfT’s record in forecasting and modelling transport demand and they suggested that it is poor. The Department for Transport has significantly improved its passenger forecast modelling in recent years. As acknowledged by my noble friend Lord Astor, we have a better understanding of what drives passenger demand, better computer modelling and our approach to risk analysis has improved.

The position of HS1 and HS2 are very different. Eurostar was accessing a completely new market for intercapital rail travel in competition, it transpired, with a burgeoning short-haul deregulated aviation market. HS2 will relieve a seriously congested existing railway between the two largest conurbations in the country—a long-existing market where demand is well understood and predicted to grow. My noble friend Lord Bradshaw suggested that our appraisal is based on the over-inflated value put on business travellers’ time. The analysis underpinning HS2 has been based on the Department for Transport’s well established approach to appraisal, one that is recognised across the transport industry and conforms to the highest standards of evidence. I know that my noble friend is very concerned about this point, especially in connection with the appraisal of road transport schemes.

Many noble Lords talked about route selection. In terms of the London to West Midlands alignment, HS2 Ltd considered more than 90 options for stations and sections of the route. There are obvious benefits to staying close to existing transport corridors where possible, which is why HS2 Ltd’s recommended route crosses part of the Chilterns close to the A413 and the Chiltern line and, indeed, uses part of the Great Central line. Overall, an M40 route would be an inferior option. It would be longer, have lower maximum speeds, impact on more population centres, resulting in unacceptable impacts on communities and it would be more expensive. In answer to one noble Lord—I think it was my noble friend Lord Bates—since the main capacity constraint is in the south, HS2 will start in the south.

The noble Lord, Lord Stevenson of Balmacara, suggested that the nation could not afford it. The nation cannot afford not to invest in HS2. Investment in HS2, and our wider rail network, can help us overcome the economic challenges we face and secure the country’s economic future. The construction costs will be spread over two decades and on this basis will involve an average level of annual spending of less than £2 billion a year at 2011 prices.

My noble friend Lord Astor suggested that a new railway is not needed to solve the railway capacity problem. By the mid-2020s forecasts show that without HS2, our main north-south rail arteries will be becoming increasingly disrupted and overcrowded, damaging our economy and our way of life, as pointed out by my noble friend Lady Scott of Needham Market. The Government have carefully considered the option of providing additional rail capacity, including upgrading existing lines. These might provide a short-term fix, but not a long-term solution. While alternatives may offer a good benefit-cost ratio, none is able to offer the scale of benefits or change that HS2 offers and would not deliver the increase in capacity that we require. Even the best alternative proposed would lead to decades of disruption on the existing network and lead to unreliable and overcrowded services and more freight on our roads. In answer to the question from the noble Lord, Lord Rosser, the capacity constraints make HS2 essential. The value of time saved is taken into account in the BCR.

My noble friend Lady Seccombe talked about community engagement. The Government and HS2 looked long and hard at possible changes to the route. However, the final design of the route is not yet set. The final design will be developed in consultation with local communities as part of the environmental impact assessment. Once that is complete, we expect to consult on the environmental statement in spring 2013. I encourage everyone with an interest to participate in that consultation. We want local communities to get engaged in the design through their local forums. I do not understand how the problem described by my noble friend arose. I hope that she will brief me later after the debate.

Viscount Astor Portrait Viscount Astor
- Hansard - -

My Lords, as we have 10 minutes, may I ask my noble friend to address one issue? Does he accept that the benefit/cost ratio has fallen below 1.5? I will quite understand if he is unable to give a detailed answer, but perhaps he would be kind enough to write to me and other noble Lords who have spoken today.

Earl Attlee Portrait Earl Attlee
- Hansard - - - Excerpts

My Lords, I have already undertaken to write where I have not answered. I am endeavouring to get through all my Box notes as fast as possible.

I know that there is no easy way of building a railway in our country but the concerns of local residents are an important priority for the Government and HS2 Ltd will ensure that local views are fed into the design process and that local communities are aware of what progress has been made with the railway.

My noble friend Lady Seccombe asked what the Government are doing to address blight. The Government recognise that HS2 is already having an impact on communities along the line of route. That is why the exceptional hardship scheme was introduced. When the Secretary of State for Transport announced the decision to proceed with HS2 in January 2012, the Government also committed to introducing a generous compensation package for the long term that goes beyond what was required in law. Developing the right property compensation package for HS2 is complex, as it must be fair to those affected by HS2 proposals while also recognising our broader responsibilities to the taxpayer. The Government will shortly be consulting on the detailed proposals to help affected property owners, with the aim of introducing long-term compensation measures as soon as possible.

My noble friend Lord Astor asked about the HS2/HS1 link, a point raised previously by the noble Lord, Lord Berkeley. I can assure my noble friend that the Government intend to connect HS2 to HS1 through a link built in the first phase. This will enable trains to run directly between HS2 and HS1 without the need for passengers to change trains. There are clear strategic advantages from integrating Britain’s new high-speed rail network with the only existing high-speed line in this country and thence to the growing high-speed rail network on the continent.

My noble friend Lord Astor talked about the demand for HS2 in a digital age. Some have questioned the demand projections underpinning the case for HS2, positing a world in which improved digital communication replaces the handshake and the face-to-face conversation and thus the train journeys that make them happen. If we turn to history, it is clear that the advent of the telegraph, the telephone and now the tweet have not lead to reductions in travel demand—far from it. I reassure the House that the Government will continue to keep the economic case and indeed the wider business case under review throughout the life of the project to ensure that it reflects the latest research, evidence and understanding of the project.

HS2 is much more than just a BCR. It is about a step change in capacity and connectivity for passengers. It is about unlocking the potential of our major cities and regions, supporting jobs and driving growth. It is about building a dynamic society, a thriving economy and a successful Britain. HS2 is not just viable; it is a vital part of our future prosperity.