Planning and Infrastructure Bill

Debate between Lord Lansley and Baroness Pidgeon
Baroness Pidgeon Portrait Baroness Pidgeon (LD)
- Hansard - - - Excerpts

My Lords, a lot of the discussion this afternoon has been very technical, as it would be around planning, but this group of amendments is much more practical. They are about electric vehicle infrastructure, making sure that we can easily support the next generation of electric vehicles and make it easy for people to transition to domestic electric vehicles at home, as well as in the commercial sectors. I thank the noble Lord, Lord Lansley, and the noble Baroness, Lady Jones of Moulsecoomb, for putting their names to my amendments in this group.

Amendment 57 would allow for cross-pavement solutions to be considered as public charge points in this legislation to ensure that such infrastructure fell within the scope of regulatory provisions governing public electric vehicle charging, to make it easier, quicker and cheaper for people to move to electric vehicles at home. Currently, EVs can be a more affordable and convenient alternative to petrol or diesel cars and they can save households up to £1,000 a year, but only if you have a driveway. Up to 40% of households in the UK do not have access to off-street parking, so they rely on public charge points, which can cost up to 10 times more than charging at home. For millions of households that is unaffordable, and it is unacceptable to expect only certain consumers to pay the price for the transition to electric.

Cross-pavement solutions have real potential to tackle that challenge, and they have been proven to be a workable solution in 38 local authority areas to date, but the current process for applying for one is lengthy and costly. Drivers report that you have to pay up to about £3,000 for the planning application, the permitting and charge point installation costs, and waiting up to 12 to 15 months simply for a decision from their local authority on whether permission to install one has been granted. So many residents have given up trying to secure cross-pavement solutions and electric vehicles because of these delays and costs.

This amendment seeks to make the transition to electric fair. It asks that cross-pavement solutions are treated in the same way that public charge points are being treated, simplifying the process for applying for these solutions by allowing them to be treated under street works permitting. This would make it quicker, easier and less costly for residents. Crucially, local authorities would still have some control over the decision on whether the cross-pavement solution is appropriate and safe for that location, and whether it can go ahead.

Amendment 58 would extend permitted development relating to electric vehicle charging points where there is an agreed cross-pavement charging solution and the charger does not overhang the footway by more than 15 centimetres. The Government have extended permitted development rights to households wishing to install charge points where the houses are close to the street and they have off-street parking. This amendment seeks to extend these rights to households without off-street parking that wish to install a charge point so that they can get a cross-pavement solution. It does not conflate the charge point with the cross-pavement solution; they are still two separate entities. It would simply ensure that those residents who are applying for a cross-pavement solution can then install a proper charge point that allows them access to the cheaper charging rates that residents with driveways are already able to use.

Electric Vehicle Association England provided me with this quote from its recent survey. One respondent commented how the council refused to consider installing a charger gully, saying, “We got a free charger and installation along with our car purchase, but we haven’t been able to make use of it, as our local council refuses to consider charging gully solutions”. Another hybrid car owner, when asked why they did not choose an EV, said it was due to the difficulty of installing a charger. They said: “Our council has no policy or provision for pavement gulleys to make it easier. There are no on-street public chargers either”.

Another quote is:

“You shouldn’t need a driveway to own an electric car. My Plan for Change is boosting funding for infrastructure to allow cables to run safely beneath pavements. That’s cheaper, at home charging”.


Those are not my words but the Prime Minister’s a week and a half ago. There is a need to make it easier for everyone to be able to move to electric vehicles through simplifying the system and allowing people without driveways to be able to move to EVs. I hope the Minister will work with me to make this vision a reality through this legislation.

Amendments 64 and 67, which are in my name, cover HGV electric charging points. Amendment 66 covers EV charging infrastructure plans. As we transition to cleaner vehicles and technology allows for HGVs to run on electric batteries, there is a need to support charging infrastructure in the planning system. The lack of adequate charging infrastructure remains one of the major obstacles to greater e-HGV adoption. According to a report by National Grid, 70% to 90% of HGVs will be charged or refuelled overnight in their depot or at their destinations, but the remaining 10% to 30% will rely on public charge stations. e-HGVs are very much a reality—in fact, we had one outside the House only a few weeks ago. There are a number of announced plans for charging stations right across the country from a variety of companies, but I know from my inbox that, where a company might want to move to e-HGVs, they find that the local authority will not grant planning permission for the necessary infrastructure at a depot, stopping the decarbonisation of this industry.

These amendments are about a clear installation programme for HGV electric charging points at key transport points, and the provision of EV charging infrastructure at freight depots and HGV facilities when they are new or substantially renovated. This amendment would future-proof the logistics infrastructure by embedding EV readiness into the design and permitting process. This supports depots and warehouses to be ready for the transition. Depot charging, as I said, is the preferred option where possible for operators as it allows trucks to charge while at a natural stopping point, not requiring additional stops to recharge in transit, which can also leave cargo vulnerable to theft. It also reduces future retrofitting costs and planning delays by integrating charging requirements from the outset.

Amendment 67 is about the prioritisation of electricity grid connections for EV infrastructure. It tackles a major barrier to infrastructure rollout: delays in grid connection approvals. Some fleet operators may face up to a 15-year wait for a grid connection to meet their need for electric infrastructure, severely hampering a willingness to invest. This amendment recognises the strategic importance of logistics infrastructure for national supply chain security and decarbonisation.

Finally, Amendment 66 is about placing a duty on local authorities to produce a local EV charging infrastructure plan to assess the demand and need for EV charging infrastructure in their area, including both private and commercial vehicles. This will ensure a comprehensive understanding of need to focus efforts. Local authorities are critical to the rollout of EV infrastructure, but often lack a co-ordinated or strategic plan. This duty empowers them to take a proactive role while ensuring consistency across regions.

The amendment would ensure local accountability and planning for EV infrastructure deployment, aligning with national decarbonisation targets. Importantly, it establishes a recurring review cycle every three years to ensure that plans are responsive to evolving demand and technology. So this package of amendments would make a huge difference to supporting the transition to electric vehicles. I look forward to the Minister’s response to these issues and all the amendments. I beg to move.

Lord Lansley Portrait Lord Lansley (Con)
- View Speech - Hansard - -

My Lords, I support the noble Baroness, Lady Pidgeon, who I thought admirably set out the importance of the case. Frankly, we are only a decade away from the point where we intend that all the new cars that are to be bought are to be electric vehicles. As she rightly said, something approaching 40% of the people who we expect in future to buy cars are in premises that do not have charging facilities, and we want to enable that to happen. It is all part of the green energy transition that we want to support. So I very much support everything that she said and I hope that we can find a solution.

As far as I can see, the clause to which this amendment refers intends to support the process of adding public charge points to the road architecture but does not necessarily allow individual householders to be able to find the appropriate cross-pavement charging solutions for this. My noble friend Lord Lucas has an amendment in this group the purpose of which is to give permitted development rights for this. I know that the Government will say, “Well, permitted development rights relate to the curtilage of one’s own premises, they do not extend out into the pavement for this purpose”. But I hope the spirit of this debate might be that we all agree on what we want to achieve—the question is what the best way is to achieve it.

I suggest to the Minister that one way we might look at this is to look at Section 50 of the New Roads and Street Works Act, which is about the process of applying for a street works licence. This clause is intended to enable those who have a street works licence to access the necessary works in the street. As the noble Baroness said, that is an expensive solution for an individual householder and not likely to be an easy route. The question to the Minister is whether we might actually find, as he is in the business today of streamlining applications, whether we can streamline applications for street works licences for individual householders, or groups of householders, in order for them to get a street works licence by what is effectively a deemed consent, rather than having to make individual applications. It is a bit like an assumption that the licence will be granted, save if there are particular exceptions or objections. That might get us to the point where householders or groups of householders can get the cross-pavement charging solutions that they require—and I think that it is urgent that we make that happen. So I hope that it is something that we can progress during the course of this Bill.

I will raise just one other point, which is about the green energy transition and the amendments relating to HGVs. I ask that we not only look at electric charging points for HGVs but recognise that HGVs—mentioned by my noble friend Lord Naseby earlier—can, very readily and unlike many other road vehicles, use hydrogen cost-effectively as a solution. But they need a network. My Japanese friends have told me that Japan is creating a network of hydrogen refuelling points for its HGV fleet. The Japanese are orders of magnitude ahead of us on this.