Ajax Armoured Cavalry Programme Debate
Full Debate: Read Full DebateLord Coaker
Main Page: Lord Coaker (Labour - Life peer)Department Debates - View all Lord Coaker's debates with the Ministry of Defence
(3 years, 1 month ago)
Lords ChamberMy Lords, Ajax is now a programme on an end-of-life watch. Clearly things have gone from bad to worse, with the Public Accounts Committee pursuing an inquiry, the National Audit Office accepting the need for an urgent investigation, and the Government’s own Major Projects Authority saying that delivery appears to be unachievable. Now the Government themselves in their own Statement say that it is not possible to determine a realistic timetable for the introduction of Ajax vehicles into operational service. Some £3.5 billion of money has been spent so far, for the delivery of just 14 Ajax vehicles.
My first question to the Minister is: what is actually going on? Can the Minister now guarantee that the problems of noise, instability, inability to fire if moving—among others—will be fixed, and tell us what the timescale is, or is it just trials, trials, and more trials followed by evaluation with no end? If all of this goes wrong, who picks up the bill—the taxpayer or General Dynamics? With noise and vibration issues still not resolved, despite the Government being warned in 2018, the number of personnel needing assessment has doubled to 310. Can the Minister tell us how many of the 248 Army personnel tested so far needed medical treatment, and for what? Will the Minister commit to the health and safety director’s report being published this year?
With the chair of the Defence Select Committee himself recently describing in the other place the Ajax procurement plan as a “dog’s dinner,” can the Minister tell us what alternatives to Ajax are being looked at, since Warrior is being scrapped and replaced with Boxer, which has no turret? Is it the CV-90, or an upgraded Warrior, or a Boxer with a turret? It must have a gun, as the Minister will know, to protect dismounted troops on the battlefield. What is it going to be?
The reality is stark, with jobs at risk in South Wales as the Government will know, troop numbers being cut—the decision partly based on the delivery of all Ajax vehicles—but 575 out of the 589 have yet to be delivered. And yet the £5.5 billion ceiling, which the Government tell us is an absolute maximum, is fast approaching. The £3.5 billion was spent for 14, with 575 outstanding, but not a significant amount of the budget is left.
In closing, I ask the Minister: the Government’s plan A for our armoured fighting vehicles looks like failing, so where is the plan B, and when will we get it?
My Lords, the Minister in the other place said
“I have previously described Ajax as a troubled programme.” —[Official Report, Commons, 9/9/21; col. 487.]
I could not have put that better myself.
One of the changes since Covid is that Ministers are no longer required to read out Statements from the other place, which might be a great relief to the Minister concerned, but perhaps means that noble Lords do not always hear the detail which is enshrined in the Statements we are debating.
The devil very much is in the detail here. As the noble Lord, Lord Coaker, has pointed out, a few details need to be explored in some depth. So far, £3.5 billion has been spent, and the Minister has said that the upper limit is still £5.5 billion. Defence procurement has long been a troubled area, with projects going overtime and overbudget. The Minister in the other place has said very clearly that this project will not go overbudget; it is very clearly going to go overtime. Can the Minister tell us whether she believes that the project is actually achievable at all?
The Minister in the other place said that the problems are not “irresolvable”, but how do we know? The problems are apparently electrical and mechanical. Do we know if there is a solution to them and, if so, what that solution might be? Has General Dynamics been given any timeline for resolving these problems, or is it just being left for it to come back at some vague date in the future to tell us there are going to be yet more trials? What assessment have the Government made of the gaps in our own capabilities if the Ajax programme is not delivered in a timely fashion—indeed, if it will not be delivered at all?
Beyond that, we have already heard that 310 people are deemed to be in need of urgent assessment. Is that the total number of people who have been involved in the trials, or are there more people? Do we have any sense of the duty of care we should be thinking about when we consider who we are asking to be part of these trials, particularly given that some of the concerns about noise appear to have arisen before the trials started? If the noble Lord, Lord Lancaster, were here, he would probably jump up later to explain that, actually, during trials you have teething problems. That is fine, but in this case we knew there were problems before the trials started. Can the Minister give us some indication of when the Government knew of the problems? What action are the Government planning to take to ensure that the 310, or however many people have so far been involved in trials, are not put further at risk? This procurement project seems at the moment to be a failing project, and that is clearly to the great detriment of this country.