Emergency Services Network: Critical Communications System Debate

Full Debate: Read Full Debate
Department: Home Office

Emergency Services Network: Critical Communications System

Lord Addington Excerpts
Monday 29th January 2024

(10 months, 3 weeks ago)

Lords Chamber
Read Full debate Read Hansard Text Watch Debate Read Debate Ministerial Extracts
Lord Sharpe of Epsom Portrait Lord Sharpe of Epsom (Con)
- View Speech - Hansard - - - Excerpts

My Lords, the noble Lord has asked me a large number of questions. To reassure all noble Lords, there is no reason at all why Airwave cannot be extended beyond 2030. As for how we got to where we got, it is worth reminding the House that it was the Home Office that referred Motorola to the Competition and Markets Authority in April 2021; that resulted in Motorola leaving the Emergency Services Mobile Communications Programme in December 2022. My noble friend the Chief Whip answered a Question back in 2022 which mentioned the £11.3 billion figure referred to by the noble Lord. That was for a programme that was supposed to run between 2015-16 and 2036-37. Unfortunately, any estimates that I give now would not be comparable in duration or end date; the end date is now expected to be 2044. However, the CMA charge control imposed on Motorola will involve a saving to the taxpayer. The numbers are very much up in the air.

Lord Addington Portrait Lord Addington (LD)
- View Speech - Hansard - -

My Lords, can the Minister assure us that the Government will look at the original tendering process to find out exactly why this went wrong, since it clearly has? As an aside, can the Government give us an assurance that no one from Fujitsu or its Horizon programme is let anywhere near it?

Lord Sharpe of Epsom Portrait Lord Sharpe of Epsom (Con)
- View Speech - Hansard - - - Excerpts

My Lords, I suppose this could have been spotted earlier, but the fact is that Motorola’s dual role in it arose as a result of the company acquiring Airwave at the same time as it was awarded the contract for ESN, so the Home Office’s options at that point were limited. We sought to agree measures to protect the delivery of ESN and, when it became clear that those measures were insufficient, the Home Office raised its concerns with the Competition and Markets Authority. As for future suppliers, the contracts will be awarded later this year, and I shall make sure that the noble Lord’s concerns are reflected.