Thursday 9th May 2024

(6 months, 2 weeks ago)

Written Statements
Read Hansard Text Read Debate Ministerial Extracts
Claire Coutinho Portrait The Secretary of State for Energy Security and Net Zero (Claire Coutinho)
- Hansard - - - Excerpts

This statement concerns an application for development consent made under the Planning Act 2008 by North Lincolnshire Green Energy Park Ltd for development consent for the construction and operation of a combined heat and power enabled energy generating development, with an electrical output of up to 95 megawatts, incorporating carbon capture, associated district heat and private wire networks, hydrogen production, ash treatment, and other associated developments on land at Flixborough industrial estate, Scunthorpe.

Under section 107(1) of the Planning Act 2008, the Secretary of State must make a decision on an application within three months of the receipt of the examining authority’s report unless exercising the power under section 107(3) of the Act to set a new deadline. Where a new deadline is set, the Secretary of State must make a statement to Parliament to announce it. The current statutory deadline for the decision on North Lincolnshire Green Energy Park application is 10 May 2024.

I have decided to set a new deadline of no later than 18 July 2024 for deciding this application. This is to ensure there is sufficient time for the Department to consider the outcome of the piece of work being carried out by officials from the Department for Environment, Food and Rural Affairs to consider the role of waste incineration capacity in the management of residual wastes in England. This follows the direction issued by the Minister for Food, Farming and Fisheries to the Environment Agency on 4 April to temporarily pause the determination of environmental permits for new waste incineration facilities up until 24 May 2024.

The decision to set the new deadline for this application is without prejudice to the decision on whether to grant or refuse development consent.

[HCWS453]