A5036 Park Lane Footbridge Replacement

(Limited Text - Ministerial Extracts only)

Read Full debate
Tuesday 4th July 2023

(10 months ago)

Westminster Hall
Read Hansard Text

Westminster Hall is an alternative Chamber for MPs to hold debates, named after the adjoining Westminster Hall.

Each debate is chaired by an MP from the Panel of Chairs, rather than the Speaker or Deputy Speaker. A Government Minister will give the final speech, and no votes may be called on the debate topic.

This information is provided by Parallel Parliament and does not comprise part of the offical record

Richard Holden Portrait The Parliamentary Under-Secretary of State for Transport (Mr Richard Holden)
- Hansard - - - Excerpts

It is a pleasure to serve under your chairmanship, Sir Robert. I thank the hon. Member for Bootle (Peter Dowd) for securing this debate on the replacement of the A5036 Park Lane footbridge. He is absolutely right that if it were in my constituency, I would be doing exactly the same as him. I have been doing this with the A689 in my constituency; we are looking at road safety measures at Crook and various other places where we have speeding issues. He is obviously doing his job as a constituency MP absolutely to the letter.

I will make a couple of general points before I address the issues the hon. Gentleman raised. Good transport connections are key to ensuring that road users use our transport network safely. They play a crucial role in supporting productivity, innovation and economic growth across the country. We have provided a series of devolution deals to mayoral combined authorities to ensure that transport connectivity maximises economic growth and supports thriving communities. The Government are fully committed to delivering our vision of levelling up the British economy, strengthening the bonds of our cities and unlocking England’s economic potential, particularly through the northern powerhouse, while ensuring that the Liverpool city region and the north of England play a key role in a resurgent economy.

As the hon. Gentleman said, the A5036 is an urban two-lane dual carriageway that widens out into three lanes at the current signal control junction at Park Lane and Park Lane West. It is the main access road to the port of Liverpool. We have had many discussions and debates about its potential. To the west of the junction, there was a pedestrian footbridge, which was the only crossing facility over the A5036 in the vicinity of the junction. As he said, it was at the heart of the community. National Highways was considering options for its removal as part of a broader look at structures that have been on our roads for decades and perhaps need upgrading or replacing. As he knows, the bridge was struck in October 2022 by an HGV, which resulted in its demolition, as it was deemed unsafe to try to patch it up.

Following that incident, the first priority of National Highways was to ensure that crossings could still be maintained on the road, so it installed a temporary, signal-controlled crossing for access to the west of the junction, next to the existing bus stops. National Highways has now completed the replacement of this initial crossing solution, with a signal-controlled toucan crossing for cyclists and pedestrians that has enabled the removal of the traffic management measures and temporary speed limits. That is a temporary solution, but because of the volume of traffic on the road, including the number of HGVs, it has been constructed to a permanent standard. However, National Highways accepts that the current arrangements have resulted in most pedestrians taking a detour from their usual routes in order to use the new crossing.

As I said, prior to the incident, National Highways had been considering options for replacing the bridge, which was far from ideal as it was accessed by a stepped ramp that provided really poor accessibility for vulnerable users, wheelchair users, motorised wheelchair users, mums with buggies taking the kids to school and other users. In considering the permanent options, National Highways has a duty to ensure that it invests money to deliver schemes that are safe and offer value for money. However, I can assure everyone that across all its activities, National Highways’ top priority, which it takes very seriously, is ensuring public safety.

As the scale of the works to replace the bridge has become clearer, the cost estimates have increased substantially, particularly when we reflect on the modern standards for access. National Highways is completing a review to assess the various options for providing a crossing point that will ensure that users can cross the road at this location safely. Junction improvements that provide signalised crossing points or a bridge are under consideration, but the full cost for those and the difference between the two will be outlined in the near future. I have had a word with National Highways and it will communicate the outcome of the review to local stakeholders within the next few months—I hope that it will be well before the end of the year—and it will also confirm timescales for the construction of any permanent solution.

Following that review, when the options with the costings have been put forward, I will be very happy to meet the hon. Member and National Highways, after they have had a preliminary meeting, to talk about any issues—if he is not happy with the solutions that National Highways comes forward with. I recognise that the outcome of the review will affect the community in Bootle, but it is right that we strive to reach a proper, long-term solution that is safe and delivers value for money. We will continue to work with National Highways to reach a solution and as it looks to communicate that in due course.

Question put and agreed to.