M20: Repairs and Maintenance

(asked on 4th September 2018) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government how many days of work were carried out on the roadworks on the M20 between London and Folkestone in August 2018; and how many days did contractors work during August 2018 on that stretch of motorway.


Answered by
Baroness Sugg Portrait
Baroness Sugg
This question was answered on 14th September 2018

For Highways England’s major projects currently being carried out on the M20 between London and Folkestone, the information is provided in the table below:

Project Description

Number of days in August when live work was being carried out

Total workforce hours

M20 junction 3-5 smart motorway

24

27,401

M20 junction 10a improvements

22

32,500

M20 junction 8-9 Temporary Solution

25

10,707