Question to the Department for Transport:
To ask Her Majesty's Government how many days of work were carried out on the roadworks on the M20 between London and Folkestone in August 2018; and how many days did contractors work during August 2018 on that stretch of motorway.
For Highways England’s major projects currently being carried out on the M20 between London and Folkestone, the information is provided in the table below:
Project Description | Number of days in August when live work was being carried out | Total workforce hours |
M20 junction 3-5 smart motorway | 24 | 27,401 |
M20 junction 10a improvements | 22 | 32,500 |
M20 junction 8-9 Temporary Solution | 25 | 10,707 |