High Speed 2 Railway Line: Wendover

(asked on 9th June 2021) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government what recent assessment has been made of the effect of HS2 Phase One construction and operation at Wendover on (1) local transport infrastructure, (2) permitted noise levels, (3) air quality, and (4) the Site of Special Scientific Interest at Weston Turville Reservoir.


Answered by
Baroness Vere of Norbiton Portrait
Baroness Vere of Norbiton
Parliamentary Secretary (HM Treasury)
This question was answered on 23rd June 2021

Information, reports, and studies which monitor the environmental effects of constructing HS2 are published online and updated monthly and annually. They include reports on air quality, dust, noise and vibration. The Phase One Environmental Statement as published reports the likely significant effects (as a likely worst case) of the broad range of environmental impacts along the route of the new railway on Wendover.