High Speed 2 Railway Line: Wendover

(asked on 9th June 2021) - View Source

Question to the Department for Transport:

To ask Her Majesty's Government whether new alternative noise and environmental mitigation solutions at Wendover on HS2 Phase One will be considered by HS2 Ltd and EKFB.


Answered by
Baroness Vere of Norbiton Portrait
Baroness Vere of Norbiton
Parliamentary Secretary (HM Treasury)
This question was answered on 23rd June 2021

HS2 civils contractor EKFB is undertaking the detailed design of noise and environmental mitigation. HS2 Ltd and EKFB continue to engage with those affected by the works to understand and engage with their concerns. They are currently developing the detailed design following the best practice approaches agreed with Qualifying Authorities set out in HS2 Planning Forum Notes.