To ask His Majesty's Government by what date they expect the work to remove dangerous cladding from high rise residential buildings in England to have been completed.


Answered by
Baroness Taylor of Stevenage Portrait
Baroness Taylor of Stevenage
Baroness in Waiting (HM Household) (Whip)
This question was answered on 8th April 2025

No leaseholder in a high-rise residential building should wait a day longer for remediation than necessary. The Remediation Acceleration Plan published last December states that by the end of 2029 all high rise buildings (18 metres and over) with unsafe cladding in a government funded scheme will have been remediated. The joint plan with developers published alongside the Remediation Acceleration Plan established targets for developers to start or complete remedial works on all their buildings by the end of July 2027.