Question to the Ministry of Housing, Communities and Local Government:
To ask Her Majesty's Government what estimate they have made of the average time taken between the first planning application for a shale gas well being received and final consent being granted for drilling.
Mineral Planning Authority decisions to grant or refuse planning permission for exploratory wells have taken between 17 and 83 weeks from date of validation to the date the decision was issued.