To ask the Senior Deputy Speaker whether a decision on the restoration and renewal of the Palace of Westminster is still expected to be takenĀ in 2025.
The R&R Client Board published the strategic case for the R&R Programme in March 2024. This set out that three options for how to deliver the R&R works to the Palace (including full decant, continued presence and enhanced maintenance and improvement) will be developed in detail. This detailed work, which will include estimated costs and timescales as well as risks and mitigations for all three options, is expected to be presented to the Houses by the end of 2025 to enable an evidence-based decision on how best to restore the Palace.