St Helena

(asked on 1st December 2014) - View Source

Question to the Department for International Development:

To ask Her Majesty’s Government what progress has been made in the construction of the St Helena airport; what is the estimated date that the first aircraft could land; and whether the construction is within budget.


Answered by
Baroness Northover Portrait
Baroness Northover
This question was answered on 15th December 2014

Construction of the St Helena Airport is more than 60% complete. It is currently within budget and on target to open for commercial flights in early 2016.