High Speed 2 Railway Line: Wendover

(asked on 26th October 2016) - View Source

Question to the Department for Transport:

To ask Her Majesty’s Government whether HS2 Ltd considered examples of HS1 tunnel construction when they examined the case for the Wendover short mined tunnel.


This question was answered on 8th November 2016

The cost estimates proposals for a mined tunnel past Wendover were based on the specific requirements for the tunnel and topography of the route at this location.