Old Oak Common Station: Construction

(asked on 19th November 2024) - View Source

Question to the Department for Transport:

To ask His Majesty's Government what discussions they have had with the Welsh Government on (1) Network Rail's planned works at Old Oak Common, and (2) the current performance of the Great Western Railway.


Answered by
Lord Hendy of Richmond Hill Portrait
Lord Hendy of Richmond Hill
Minister of State (Department for Transport)
This question was answered on 3rd December 2024

The Wales Rail Board meets regularly and facilitates the UK and Welsh governments to discuss matters of mutual interest. The Board discusses performance of the Great Western Main Line and plans to manage rail services during construction of the new station at Old Oak Common. I continue to work with HS2 Ltd, Network Rail and train operators to minimise disruption to passengers on the Great Western Main Line, both during the construction of the station and its operation.