Electricity Generation: Infrastructure

(asked on 22nd July 2026) - View Source

Question to the Department for Energy Security & Net Zero:

To ask His Majesty's Government what proportion of Transmission Entry Capacity projects due for delivery by 2030 do not yet have a corresponding entry in the Transmission Works Report.


Answered by
Baroness Curran Portrait
Baroness Curran
Parliamentary Under-Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 5th August 2026

The Transmission Works Report (TWR) is being updated in light of revised connection offers issued as part of the connections reform process. All projects that accept a ‘Gate 2’ connection offer (confirmed connection location and date) will have a corresponding entry in the TWR, regardless of their connection date.