Electricity Generation: Infrastructure

(asked on 22nd July 2026) - View Source

Question to the Department for Energy Security & Net Zero:

To ask His Majesty's Government how many megawatts of transmission connection projects in the Transmission Entry Capacity register have been completed to date, out of the total capacity currently in the queue.


Answered by
Baroness Curran Portrait
Baroness Curran
Parliamentary Under-Secretary of State (Department for Energy Security and Net Zero)
This question was answered on 5th August 2026

According to National Energy System Operator (NESO), as of 24 July, the Transmission Entry Capacity (TEC) Register included 81.7GW of generation capacity that has been built. 284.64GW of generation capacity has received revised ‘Gate 2’ connection offers (confirmed connection location and date) under the reformed connections process. The TEC Register will be updated by NESO as connection offers are accepted or declined.