To ask Her Majesty’s Government when they expect to receive the results of the review by Sir Peter Hendy of Network Rail projects in Control Period 5; whether those results will be subject to a period of consultation; and if so, who they plan to consult on them.


This question was answered on 25th September 2015

Sir Peter Hendy will report back to the Secretary of State for Transport this autumn with a proposal for re-planning the Control Period 5 enhancements in a way that is efficient, deliverable and affordable.

As part of this re-planning exercise Network Rail is consulting widely, including with train and freight operators.