Floods: Earby

(asked on 4th March 2020) - View Source

Question to the Department for Environment, Food and Rural Affairs:

To ask Her Majesty's Government what assessment they have made of the most recent flooding in Earby; and whether the proposed further flood mitigation work there will take place in time to take advantage of any EU funding that has been agreed.


This question was answered on 18th March 2020

The Government recognises the impact the recent flooding incidents have had on communities and sympathises with those affected.

The Earby Flood Alleviation Scheme is split into Phase 2 and Phase 3. Phase 2 of the scheme is currently at the Outline Business Case stage and qualifies for £1.03 million in Flood Defence Grant in Aid. The project has sourced the following partnership funding: £635,000 of European Structural Investment Fund; and £15,000 from Pendle Borough Council. The project team are working with Pendle Borough Council to look for options to address the funding gap to allow the project to progress.